IP Library Granted Patent US 12686985
Granted Patent B2
US 12686985 · App. 18/728,740 · Granted Jul 21, 2026

Methods and apparatus for building expanded shaft augured foundation elements

Inventors: August Beck (Davidson, NC); Kord J. Wissmann (Davidson, NC)
Assignee: Geopier Foundation Company, Inc.
E02D5/36E02D2250/003E02D2250/0038
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12686985
App. No.
18/728,740
Granted
Jul 21, 2026
Kind
B2
Abstract

An apparatus for building expanded shaft augured foundation elements, comprising: a dual-section drilling augur having a lower section and an upper section, wherein the lower section and the upper section are configured to rotate relative to each other.

Claims (28)

1 . An apparatus for building expanded shaft augured foundation elements, comprising:

a dual-section augur having a lower section and an upper section, wherein the lower section and the upper section are configured to rotate relative to each other; and,

an augur conveyance restriction element disposed between the lower section and the upper section.

2 . The apparatus according to claim 1 , wherein the upper section rotates independently from the lower section.

3 . The apparatus according to claim 1 , wherein the upper section terminates in a flat, horizontal flange at a lower end of the upper section.

4 . The apparatus according to claim 3 , wherein the flange is a half-circle in profile when viewed from the bottom of the flange.

5 . The apparatus according to claim 3 , wherein the diameter of the flange is the same or less than the diameter of at least one flight of the augur.

6 . The apparatus according to claim 1 , wherein the lower section terminates in a flat, horizontal flange at an upper end of the lower section.

7 . The apparatus according to claim 6 , wherein the flange is a half-circle in profile when viewed from the bottom of the flange.

8 . The apparatus according to claim 6 , wherein the diameter of the flange is the same or less than the diameter of at least one flight of the augur.

9 . The apparatus according to claim 1 , wherein a lower portion of the upper section and an upper portion of the lower section form the augur conveyance restrictor element.

10 . The apparatus according to claim 9 , wherein the augur conveyance restrictor element is configured in an open configuration when the upper section is aligned coincident with the lower section.

11 . The apparatus according to claim 9 , wherein the augur conveyance restrictor element is configured in a closed configuration when the upper section is not aligned coincident with the lower section.

12 . The apparatus according to claim 1 , further comprising a hollow augur stem through which backfill material flows during operation.

13 . The apparatus according to claim 1 , further comprising a tip at a bottom end of the dual-section drilling augur through which backfill material flows during operation.

14 . A method for building expanded shaft augured foundation elements, comprising:

aligning a lower section and an upper section of a dual-section drilling augur to achieve an open configuration to allow for augur spoil conveyance.;

advancing the dual-section drilling augur in to a subsurface ground material, wherein as the dual-section drilling augur cuts into the subsurface material, cuttings are conveyed upwards on flights of the dual-section drilling augur, enabled by the open configuration;

placing backfill material into the dual-section drilling augur when design depth has been achieved;

raising the dual-section drilling augur to allow the flow of the backfill material out of the dual-section drilling augur at the design depth;

re-advancing the dual-section drilling augur downwardly into the backfill material until the backfill material forms cuttings on augur flights of the lower section;

reversing rotation direction of the dual-section drilling augur causing the upper section to swivel relative to the lower section and placing the dual-section drilling augur into a closed configuration which prohibits the upward conveyance of cuttings; and,

creating an expanded shaft, augured foundation element through a combination of downwardly movement and the reverse rotation of the dual-section drilling augur forcing the backfill material cuttings that are on the augur flights of the lower section to move down and outward relative to the dual-section drilling augur.

15 . The method according to claim 14 , wherein reversing rotation is rotating the dual-section drilling augur in a counter-clockwise direction.

16 . The method according to claim 14 , wherein backfill material is placed into a hollow augur stem of the dual-section drilling augur.

17 . The method according to claim 14 , wherein the backfill material flows out of the placing backfill material into the dual-section drilling augur from a tip at a bottom end of the dual-section drilling augur.

18 . The method according to claim 14 , wherein the expanded shaft is located at at least one of the bottom of the augured foundation element and at a distance above the bottom of the augured foundation element.

19 . The method according to claim 14 , further comprising continuing reverse rotation upwardly to extract the dual-section drilling augur to complete forming the augured foundation element.