IP Library Granted Patent US 6,839,722
Granted Patent B2
US 6,839,722 · App. 09/982,054 · Granted Jan 4, 2005

Method for referencing time-related entries in different files in a planning program

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,839,722
App. No.
09/982,054
Granted
Jan 4, 2005
Kind
B2
Abstract

A method for referencing time-related entries in different files in a planning program for project planning, and for determining and optically reproducing any time delays in the project implementation, with one or more nominal planning entries, which define times or time intervals, being entered in a reference file, until which or within which one or more individual projects are intended to be implemented, with actual entries, which are a measure of the time evolution of the respective individual project implementation, being entered in one or more further individual-project-related files, with the nominal planning entries being used as time reference data, with respect to which the actual entries of one or more individual projects are referenced, and with a time overrun which results or can be predicted on the basis of the actual entries in comparison with the nominal planning entries, of the respective reference nominal planning entry being determined by computation and being reproduced on a display device.

Claims (45)

1. A method for referencing time-related entries in different files in a planning program for project planning, comprising:

defining times or time intervals until which or within which at least one project is intended to be implemented;

entering said times or time intervals in a reference file as nominal planning entries for said at least one project;

entering actual times or time intervals in at least one further project related file, said actual times or time intervals being a measure of actual times of individual project implementations of said at least one project;

using said nominal planning entries as time reference data, said time reference data being referenced to said actual times or time intervals;

determining by computation an actual or predicted time overrun by comparing said actual entries with respective ones of said nominal planning entries; and

displaying said time overrun on a display device so as to determine and optically reproduce any time delays in the project implementation.

2. A method as claimed in claim 1 , wherein said step of displaying displays a colored marking in a reference file as a graphic.

3. A method as claimed in claim 1 , wherein said step of displaying displays at least one individual-project-related file on a screen of said display device.

4. A method as claimed in claim 1 , wherein said step of displaying displays said reference file or individual-project-related files on a screen as at least one of dot diagrams and bar charts in which said time overrun is reproduced as an elongated bar.

5. A method as claimed in claim 1 , wherein said step of displaying reproduces said time overrun as a numerical file in the reference file which is displayed on a screen as a table.

6. A method as claimed in claim 1 , wherein said project includes a plurality of sub-projects, and further comprising the steps of:

recording actual entries for each of said sub-projects;

considering said project in its totality during referencing to said time reference data.

7. A method as claimed in claim 1 , wherein said project includes a plurality of sub-projects, and further comprising the steps of:

recording actual entries for each of said sub-projects;

considering each of said sub-projects individually during referencing to said time reference data.

8. A method as claimed in claim 1 , wherein said actual entries are time values which indicate work carried out for an individual project by at least one person who is working on that project,

wherein said actual times are time values between a time of a start of the project and a last actual entry,

wherein said determining step calculating whether the nominal planning entry has been overrun, has probably been overrun or has not been overrun, and

wherein said displaying step displaying an actual or probable overrun.

9. A method as claimed in claim 8 , wherein said actual entries are time values for a sub-project.

10. A method as claimed in claim 8 , wherein said determining step compares the actual entries with preset actual entries entered for the respective individual project,

wherein said determining step calculating an actual or probable overrun on a basis of a difference between the preset actual entries and the associated actual entries.

11. A method as claimed in claim 10 , further comprising the steps of:

applying any time difference resulting from the comparison to a most recent preset actual entry; and

comparing the time value resulting from said applying step with the nominal planning entry in order to determine any overrun.

12. A method as claimed in claim 1 , further comprising the step of:

accepting a selection at a user end as to which individual project is to be referenced with respect to which nominal planning entry.

13. A method as claimed in claim 12 , wherein said accepting step includes accepting a selection as to which sub-project is to be referenced.

14. A computer program having program code to carry out on a computer the steps of:

defining times or time intervals until which or within which at least one project is intended to be implemented;

entering said times or time intervals in a reference file as nominal planning entries for said at least one project;

entering actual times or time intervals in at least one further project related file, said actual times or time intervals being a measure of actual times of individual project implementations of said at least one project;

using said nominal planning entries as time reference data, said time reference data being referenced to said actual times or time intervals;

determining by computation an actual or predicted time overrun by comparing said actual entries with respective ones of said nominal planning entries; and

displaying said time overrun on a display device so as to determine and optically reproduce any time delays in the project implementation.

15. A computer program as claimed in claim 14 , further comprising the step of:

storing program code to carry out said steps on a computer legible data storage medium.

16. A method for determining a time overrun in a project, comprising the steps of:

entering projected time intervals into a reference file of a project planing program as nominal planning data;

entering actual time intervals of a project implementation into a further file of said project planning program;

comparing said projected time intervals to said actual time intervals;

determining by computation an actual or predicted time overrun if at least one of said actual time intervals exceeds a corresponding one of said projected time intervals; and

displaying said actual or predicted time overrun on a display device.

Assignments (3)
CHANGE OF NAME Recorded Dec 5, 2017
From: GOOGLE INC.
To: GOOGLE LLC
Reel/Frame 044695/0115 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 17, 2012
From: SIEMENS AKTIENGESELLSCHAFT
To: GOOGLE INC.
Reel/Frame 028221/0677 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 20, 2002
From: BUCHNER, KLAUS
To: SIEMENS AKTIENGESELLSCHAFT
Reel/Frame 012636/0501 →