IP Library Granted Patent US 6,917,838
Granted Patent B2
US 6,917,838 · App. 10/174,067 · Granted Jul 12, 2005

Open-loop and closed-loop control method, and a control device for starting up and shutting down a process component of a technical process

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,917,838
App. No.
10/174,067
Granted
Jul 12, 2005
Kind
B2
Abstract

An open-loop and closed-loop control method is described for starting up or shutting down a process component of a technical process. At least one manipulated variable that is fed to the process is formed by a control device and an upstream model-assisted pilot control. The pilot control contains an optimizer and a process model. The optimizer is fed at least one command variable for the technical process. At least one optimized model manipulated variable which the optimizer outputs is fed to a process model of the pilot control and, is added to at least one output variable of the control device to form the manipulated variable. A model output variable of the process model is fed to the control device as a set-point and fed back to the optimizer along with variables which cannot be measured in the technical process. A device for implementing the method is also described.

Claims (21)

1. An open-loop or closed-loop control method for starting up and shutting down at least one process component of a technical process, which comprises the steps of:

providing a model-assisted pilot control having an optimizer and a process model;

feeding at least one command variable for the technical process to the model-assisted pilot control;

generating in the optimizer and outputting from the optimizer at least one optimized model manipulated variable, the process model of the model-assisted pilot control receiving the optimized model manipulated variable as an input variable;

feeding at least one model output variable output by the process model to a control device as a set-point, the control device disposed downstream of the model-assisted pilot control;

feeding the at least one model output variable back to the optimizer;

feeding internal variables output from the process model back to the optimizer;

adding the optimized model manipulated variable to at least one output variable output by the control device to form at least one manipulated variable;

feeding the manipulated variable to the technical process;

acquiring the optimized model manipulated variable and the model output variable from a look-up table during the start-up and the shutdown, or repeatedly forming the optimized model manipulated variable and the model output variable with the process model by feeding back an output of the technical process to the process model during startup and shutdown, to thereby track the technical process with the process model; and

in an event of a change in the command variable,

decoupling a control response of a device having the model-assisted pilot control, thereby preventing an interference response of the technical process in a case of effects due to interference.

2. The method according to claim 1 , which comprises determining a model of the technical process in the optimizer by formulating a quality function using mathematical and physical methods, and wherein the quality function is maximized or minimized with an aid of a suitable optimization method.

3. The method according to claim 1 , which comprises applying a combination of a rigorous dynamic modeling with an optimization to the technical process, taking account of boundary and secondary conditions.

4. The method according to claim 3 , which comprises forming the boundary and secondary conditions to be physical constraints of process engineering.

5. The method according to claim 1 , which comprises using at least one measurable output variable of the technical process for adjusting the process model.

6. The method according to claim 1 , which comprises identifying the process model at least partially from measurements if the technical process is in operation.

7. The method according to claim 1 , which comprises performing an injection before completion of the start-up, to permit the start-up at optimum cost while observing existing constraints if the process component is a steam generator with water injection.

8. The method according to claim 1 , which comprises using the model-assisted pilot control to exert a corrective influence on the control device.

9. The method according to claim 1 , which comprises forming the internal variables from variables that cannot be measured in the technical process.

10. The method according to claim 1 , which comprises checking the process model using measurements if the technical process is in operation.

Assignments (2)
MERGER Recorded Dec 26, 2019
From: ABB RESEARCH LTD.
To: ABB SCHWEIZ AG
Reel/Frame 051419/0309 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 2, 2005
From: KRUGER, KLAUS; RODE, MANFRED; FRANKE, RUDIGER
To: ABB RESEARCH LTD.
Reel/Frame 016628/0873 →