US 6,939,422 · App. 10/240,030 · Granted Sep 6, 2005

Method for building sheet pile walls

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,939,422
App. No.
10/240,030
Granted
Sep 6, 2005
Kind
B2
Abstract

A method for building a sheet pile wall includes providing a first sheet pile having a leading sheet pile interlock with an interlock chamber, driving the first sheet pile into the ground while protecting the interlock chamber from ground material and providing a second sheet pile having a trailing sheet pile interlock with an interlock head. The method further includes coating a fixing agent as a surface layer on the interlock head of the trailing sheet pile interlock, engaging the coated interlock head of the trailing sheet pile interlock in the interlock chamber of the leading sheet pile interlock and driving the second sheet pile into the ground so that the trailing sheet pile interlock interlocks with the leading sheet pile interlock.

Claims (23)

1. A method for building a sheet pile wall, comprising the steps of:

providing a first sheet pile, said first sheet pile having a leading sheet pile interlock with an interlock chamber;

driving said first sheet pile into the ground while protecting said interlock chamber from ground material;

providing a second sheet pile, said second sheet pile having a trailing sheet pile interlock with an interlock head;

coating a fixing agent as a surface layer on an inside and an outside of said interlock head of said trailing sheet pile interlock;

engaging said coated interlock head of said trailing sheet pile interlock in said interlock chamber of said leading sheet pile interlock; and

driving said second sheet pile into the ground, wherein said trailing sheet pile interlock interlocks with said leading sheet pile interlock.

2. The method according to claim 1 , using a spreader to apply said surface layer of fixing agent onto said interlock head of said trailing sheet pile interlock.

3. The method according to claim 2 , wherein a spreader chamber of said spreader engages said interlock head of said trailing sheet pile interlock, said spreader chamber having a slightly bigger cross-section than said interlock head of said trailing sheet pile interlock.

4. The method according to claim 3 , using an injection nozzle to inject said fixing agent into said spreader chamber through an injection opening arranged in said spreader.

5. The method according to claim 1 , wherein a longitudinal opening gives access to said interlock chamber in said leading sheet pile interlock and the step of protecting said interlock chamber from ground material comprises:

a) inserting an obturating device into said interlock chamber, said obturating device comprising an inflatable tube;

b) inflating said inflatable tube so that said obturating device closes said longitudinal opening giving access to said interlock chamber;

c) driving said sheet pile into the ground, wherein said obturating device prevents ground material from penetrating through said longitudinal opening into said interlock chamber;

d) deflating said inflatable tube; and

e) withdrawing said obturating device from said interlock chamber.

6. The method according to claim 5 , wherein said obturating device comprises an obturating block, and inflation of said inflatable tube pushes said obturating block into the longitudinal opening of said interlock chamber.

7. The method according to claim 5 , said obturating device further comprises a flexible tube alongside said inflatable tube, and said interlock chamber is filled with sand through said flexible tube while withdrawing said obturating device from said interlock chamber.

8. The method according to claim 5 , further comprising.

inserting a front end obturator in the bottom end of said interlock chamber of said leading sheet pile interlock before driving said first sheet pile into the ground.

9. The method according to claim 5 , further comprising:

inserting a cleaning piece into said leading sheet pile interlock of said first sheet pile before interlocking it with said trailing sheet pile interlock of said second sheet pile.

10. The method according to claim 1 , wherein said fixing agent is an adhesive or cement.

Assignments (5)
CHANGE OF NAME Recorded Dec 5, 2008
From: ARCELOR COMMERCIAL RPS S.A.R.L.
To: ARCELORMITTAL COMMERCIAL RPS S.A.R.L.
Reel/Frame 021924/0638 →
CHANGE OF NAME Recorded Jan 19, 2007
From: ARCELOR RAILS, PILES & SPECIAL SECTIONS SARL
To: ARCELOR COMMERCIAL RPS S.A.R.L.
Reel/Frame 018777/0212 →
CHANGE OF NAME Recorded Jun 28, 2004
From: INTERNATIONAL SHEET PILING COMPANY SARL
To: ARCELOR RAILS, PILES & SPECIAL SECTIONS
Reel/Frame 014788/0059 →
ASSIGNMENT RECORDATION CORRECTION Recorded Apr 23, 2003
From: MOULIN, JEAN-MICHEL; RIX, ANDRE
To: INTERNATIONAL SHEET PILING COMPANY SARL
Reel/Frame 013989/0539 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 26, 2002
From: MOULIN, JEAN-MICHEL; RIX, ANDRE
To: INTERNATIONAL SHEET PILING CAMPANY SARL
Reel/Frame 013528/0757 →