Method of constructing a rail track on a concrete slab and a temporary tie plate for use in the method

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,954,974
App. No.
10/278,981
Granted
Oct 18, 2005
Kind
B2
Abstract

In a method of constructing a rail track on a concrete slab, the concrete slab is poured around anchor members for fixing tie plates supporting the rails of the rail track. The method includes the following steps: suspending the rails premounted on their tie plates above the location at which the concrete slab is to be poured, each tie plate including a base under which is disposed a temporary tie plate for accurately guiding the anchor members, adjusting the position of the rails, pouring the concrete slab up to the height of the temporary tie plates, raising the rails and removing the temporary tie plates, and accurately positioning the rails premounted on their tie plates on the concrete slab in their final position and fixing the tie plates to the anchor members.

Claims (8)

1. A method of constructing a rail track on a concrete slab, in which method the concrete slab is poured around anchor members for fixing tie plates supporting the rails of said rail track, which method includes the following steps:

suspending said rails premounted on their tie plates above the location at which said concrete slab is to be poured, each tie plate including a base under which is disposed a temporary tie plate including guide bushes engaging in close-fitting openings in said base, said guide bushes including a close-fitting bore receiving an anchor member consisting of a threaded rod having a portion which projects beyond the bottom face of said temporary tie plate,

adjusting the position of said rails to move said bottom plate of said temporary tie plates accurately to the location at which said tie plates supporting said rails must rest,

pouring said concrete slab up to the height of said temporary tie plates,

raising said rails and removing said temporary tie plates, and

accurately positioning said rails premounted on their tie plates on said concrete slab and fixing said tie plates to said anchor members.

2. The rail track construction method claimed in claim 1 , wherein, after removing said temporary tie plates, spacers are placed inside said openings in said tie plates or around said threaded rods, said spacers accurately locating said tie plates on said concrete slab by virtue of having a body with a cylindrical part inserted in said opening whose outside diameter is a close fit to the diameter of said opening, said cylindrical part including an internal bore which is a close fit to the diameter of said threaded rod.

3. The rail track construction method claimed in claim 1 , wherein said rails are suspended above said slab to be poured by means of a gantry for moving said rails accurately to a required position.

Assignments (5)
CHANGE OF ADDRESS Recorded Jul 31, 2017
From: ALSTOM TRANSPORT TECHNOLOGIES
To: ALSTOM TRANSPORT TECHNOLOGIES
Reel/Frame 043382/0290 →
CORRECTIVE ASSIGNMENT TO REMOVE ERRONEOUS FILED PATENT NO. 6250442 PREVIOUSLY RECORDED AT REEL: 035455 FRAME: 0513. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Aug 10, 2015
From: ALSTOM TRANSPORT SA
To: ALSTOM TRANSPORT TECHNOLOGIES
Reel/Frame 036344/0852 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 20, 2015
From: ALSTOM TRANSPORT SA
To: ALSTOM TRANSPORT TECHNOLOGIES
Reel/Frame 035455/0513 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 14, 2015
From: ALSTOM
To: ALSTOM TRANSPORT SA
Reel/Frame 035422/0967 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 20, 2002
From: RADA, NICOLAS
To: ALSTOM
Reel/Frame 013600/0484 →