IP Library Granted Patent US 6,952,926
Granted Patent B2
US 6,952,926 · App. 10/416,486 · Granted Oct 11, 2005

Method for starting up and loading a combined power plant

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,952,926
App. No.
10/416,486
Granted
Oct 11, 2005
Kind
B2
Abstract

When loading a power station in a grid without any energy, this power station must be able to cover all the short-term power requirements, and at the same time to keep the grid frequency within a permissible tolerance band. The invention specifies a method of providing this capability by means of an efficient combination system. According to the invention, the gas turbine ( 1 ) is loaded in a lower power range such that it is controlled in accordance with a predetermined load program, without having to react to load transients in the grid ( 50 ). Before the power station is connected to the grid, the heat recovery steam generator ( 5 ) is heated up as an energy store, and a steam turbine ( 2 ) is raised at least to its rated rotation speed, with the steam control valves ( 9, 15 ) being highly restricted. The steam turbine reacts in the event of short-term load requirements from the grid, which cannot be covered by the gas turbine.

Claims (16)

1. A method for operating a combined cycle power station upon starting up an electrical black grid, comprising:

heating up a water/steam circuit and starting a steam turbine before the grid is charged with a load; and

loading a gas turbine at least in a part of its load range in accordance with a predetermined load program;

changing the steam turbine power to cover transient load requirements in the grid.

2. The method as claimed in claim 1 , comprising:

operating the gas turbine for a time period on idle operation or at a power level for supplying the combined cycle power station's own power supply requirements before being connected to the grid; and

charging the water/steam circuit with energy during said time period.

3. The method as claimed in claim 1 , comprising:

providing at least one holding point in the load program for the gas turbine; and

charging the water/steam circuit with further energy at the holding point.

4. The method as claimed in claim 1 , comprising:

temporarily supplying steam from a high-pressure section of a hear recovery steam generator to a low-pressure section, a medium-pressure section, or both, of the steam turbine.

5. The method as claimed in claim 1 , comprising:

storing steam energy with at least one drum of a heat recovery steam generator.

6. The method as claimed in claim 1 , further comprising:

covering transient load requirements of the grid with the power of a black starting diesel in addition to the steam turbine power.

Assignments (1)
CHANGE OF NAME Recorded Aug 17, 2016
From: ALSTOM TECHNOLOGY LTD
To: GENERAL ELECTRIC TECHNOLOGY GMBH
Reel/Frame 039714/0578 →