Determining an operational limit of a power transmission line

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,107,162
App. No.
10/499,701
Granted
Sep 12, 2006
Kind
B2
Abstract

In a method, computer program and system for determining an operational limit of a power transmission line, time-stamped current phasor information and voltage phasor information for a first end and a second end of the line are determined, an ohmic resistance of the line is computed from the phasor information, and an average line temperature is computed from the ohmic resistance. This allows to determine the average line temperature without dedicated temperature sensors. The average line temperature represents the actual average temperature and is largely independent of assumptions regarding line parameters.

Claims (18)

1. A method for determining an operational limit of a power transmission line, comprising the steps of

determining time-stamped current phasor information and voltage phasor information for a first end and a second end of the line,

computing an ohmic resistance R of the line from the phasor information,

computing an average line temperature T 1 from the ohmic resistance R.

2. The method according to claim 1 , comprising the step of controlling a power flow through the line such that the average line temperature T 1 does not exceed a given maximum average line temperature T max .

3. The method according to claim 1 , comprising the steps of computing actual electrical parameters (R, X L , X C ) of the line and computing, from the actual electrical line parameters, a maximum load s max that is deliverable by the line.

4. The method according to claim 3 , comprising the step of controlling a power flow through the line such that an actual power s delivered by the line does not exceed the maximum load s max .

5. The method according to claim 4 , wherein the step of controlling a power flow through the line ensures that the average line temperature T 1 does not exceed a given maximum average line temperature T max .

6. A computer program for determining an operational limit of a power transmission line loadable into an internal memory of a digital computer, comprising computer program code means to make, when said program is loaded in the computer, the computer execute the method according to claim 1 .

7. A system for determining an operational limit of a power transmission line from time-stamped current phasor information and voltage phasor for a first end and a second end of the line, the system comprising:

a data processing device and means for

computing an ohmic resistance R of the line from the phasor information, and

computing an average line temperature T 1 from the ohmic resistance R.

8. The system according to claim 7 , further comprising:

means for controlling power flow through the line such that the average line temperature T 1 does not exceed a given maximum average line temperature T max .

9. The system according to claim 7 , further comprising:

means for computing actual electrical parameters (R, X L , X C ) of the line; and

means for computing, from the actual electrical line parameters, a maximum load s max that is deliverable by the line.

Assignments (2)
CHANGE OF NAME Recorded Dec 31, 2021
From: ABB POWER GRIDS SWITZERLAND AG
To: HITACHI ENERGY SWITZERLAND AG
Reel/Frame 058666/0540 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 6, 2020
From: ABB SCHWEIZ AG
To: ABB POWER GRIDS SWITZERLAND AG
Reel/Frame 052916/0001 →