IP Library Granted Patent US 8,557,018
Granted Patent B2
US 8,557,018 · App. 10/553,362 · Granted Oct 15, 2013

Process for improving energy supply to a scrap bulk

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,557,018
App. No.
10/553,362
Granted
Oct 15, 2013
Kind
B2
Abstract

The present invention relates to a process for improving energy supply when heating and melting a scrap bulk wherein a preheated oxidizing gas with addition of fossil fuels melts a channel into the scrap bulk and further energy supply occurs through this channel. A significant improvement of the process is achieved by supplying hot blast to the scrap bulk from the top.

Claims (12)

1. Process for improving energy supply when heating and melting a scrap bulk within a vessel having side and top walls, wherein a hot blast of preheated oxidizing gas with addition of fossil fuels melts a channel into the scrap bulk, and further energy supply occurs through this channel and wherein said hot blast is supplied to the scrap bulk from said top wall, wherein said hot blast causes a gas stream in the scrap bulk, the gas stream involving hot gases leaving the scrap bulk through an outer ring within the vessel, thereby heating scrap in said outer ring,

wherein the hot blast blows onto the scrap bulk from a central top position,

and wherein a high hot blast velocity 500 to 900 m/sec is applied during a first phase and a reduced hot blast velocity approx. 300 to 500 m/sec during a second phase, wherein the hot blast let is enriched with oxygen to 30 to 50% in phase 1, whereas there is no or hardly any oxygen enrichment in phase 2.

2. The process as claimed in claim 1 , wherein the hot blast is divided into several separate jets.

3. The process as claimed in claim 1 , wherein the hot blast is distributed to a central jet with 35 to 65% of the total amount and several jets outside the central jet for the rest.

4. The process as claimed in claim 1 , wherein hot blast is supplied via a vertically adjustable lance.

5. The process as claimed in claim 4 , wherein the hot blast lance rotates around a vertical axis.

6. The process as claimed in claim 1 , wherein a hot heel remains in the furnace.

7. The process as claimed in claim 6 , wherein the hot heel in the furnace makes up 10 to 30% of the melt.

8. The process as claimed in claim 1 , wherein oxygen is injected via bottom blowing tuyeres.

9. The process as claimed in claim 8 , wherein the bottom blowing tuyeres are installed in an indentation of the furnace bottom.

10. The process as claimed in claim 1 , wherein the distance of the hot blast jet to the surface of the scrap is 0.2 to 0.5 m in phase 1 and is adjusted to a distance to the iron bath of at least 3 m during phase 2.

Assignments (4)
CHANGE OF NAME Recorded May 16, 2016
From: SIEMENS VAI METALS TECHNOLOGIES GMBH
To: PRIMETALS TECHNOLOGIES AUSTRIA GMBH
Reel/Frame 038710/0301 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 30, 2013
From: ITAG INNOVATIONS-TECHNOLOGIE AG
To: SIEMENS VAI METALS TECHNOLOGIES GMBH
Reel/Frame 031308/0934 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 2, 2009
From: KARL BROTZMANN CONSULTING GMBH
To: I T A G INNOVATIONS-TECHNOLOGIE AG
Reel/Frame 022767/0359 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 22, 2007
From: BROTZMANN, KARL
To: KARL BROTZMANN CONSULTING GMBH
Reel/Frame 019470/0527 →