IP Library Granted Patent US 7,799,476
Granted Patent B2
US 7,799,476 · App. 10/558,982 · Granted Sep 21, 2010

Fixed IDC operation of fuel cell power plant

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,799,476
App. No.
10/558,982
Granted
Sep 21, 2010
Kind
B2
Abstract

A method for operating a fuel cell power plant to supply power to an internal load and an external load, includes the steps of evaluating power needs of the internal and external loads to determine a fixed IDC value sufficient to supply the needs; providing auxiliary power to the internal load and output power to the external load so as to maintain operation of the fuel cell power plant at the fixed IDC value; and adjusting at least one of the auxiliary power to the internal load and output power to the external load so as to maintain operation of the fuel cell power plant at the fixed IDC value. Operation within a preselected voltage range is also provided.

Claims (14)

1. A method for operating a fuel cell power plant, comprising the steps of:

evaluating power needs of an external load to determine a fixed IDC value sufficient to supply said needs; and

operating said fuel cell power plant at substantially fixed reactant flows sufficient to provide said fixed IDC value,

wherein said fuel cell power plant has an output voltage at said substantially fixed reactant flows, and further comprising the steps of comparing said output voltage to a maximum voltage of said external load, and selectively turning on an auxiliary load when said output voltage is greater than said maximum voltage whereby a portion of said output voltage is provided to said auxiliary load and remaining voltage to said external load is less than said maximum voltage.

2. The method of claim 1 , further comprising the step of evaluating the difference between said output voltage and said maximum voltage and selecting said auxiliary load to utilize said difference.

3. The method of claim 1 , wherein said auxiliary load is selected from the group consisting of AC loads, DC loads and combinations thereof.

4. The method of claim 1 , wherein the magnitude of the auxiliary load is selected to maximize power plant efficiency within the selected operating voltage range.

5. The method of claim 1 wherein the auxiliary load is selected from a set of multiple loads each of which provides known level of voltage variation.

6. The method of claim 1 , wherein reactant flows to the fuel cell power plant are held substantially constant.

7. The method of claim 1 , wherein the auxiliary load is controlled in a manner that provides a known and continuously variable level of voltage variation within a control range.

8. A method for operating a fuel cell power plant, comprising the steps of:

evaluating power needs of an external load to determine a fixed IDC value sufficient to supply said needs;

providing output power to said external load at a level provided by said fuel cell power plant at said fixed IDC value; and

adjusting said output power to said external load so as to maintain operation of said fuel cell power plant at said fixed IDC value, wherein said fuel cell power plant has an output voltage at substantially fixed reactant flows, and further comprising the steps of comparing said output voltage to a maximum voltage of said external load, and selectively turning on an auxiliary load when said output voltage is greater than said maximum voltage whereby a portion of said output voltage is provided to said auxiliary load and remaining voltage to said external load is less than said maximum voltage.

Assignments (4)
CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNEE ADDRESS PREVIOUSLY RECORDED AT REEL: 035728 FRAME: 0905. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Aug 24, 2015
From: BALLARD POWER SYSTEMS INC.
To: AUDI AG
Reel/Frame 036481/0803 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 19, 2015
From: BALLARD POWER SYSTEMS INC.
To: AUDI AG
Reel/Frame 035728/0905 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 2, 2015
From: UNITED TECHNOLOGIES CORPORATION
To: BALLARD POWER SYSTEMS INC.
Reel/Frame 035113/0609 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 19, 2013
From: UTC POWER CORPORATION
To: UNITED TECHNOLOGIES CORPORATION