IP Library Granted Patent US 7,151,974
Granted Patent B2
US 7,151,974 · App. 11/061,813 · Granted Dec 19, 2006

Controlling method for manufacturing process comprising determining a priority of manufacturing process needing recovery in response to degree of risk

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,151,974
App. No.
11/061,813
Granted
Dec 19, 2006
Kind
B2
Abstract

In a method of controlling a manufacturing process, operating conditions of plural process steps are monitored during the manufacturing process. A degree of risk is calculated for each of a malfunction operating condition step and subsequent steps. The degree of risk is classified into plural levels and is determined in accordance with a risk point on the basis of the minimum WIP, actual WIP, target WIP, and a weighting factor. A priority of the manufacturing process needing recovery is determined in response to the degree of risk, and an operating condition of the manufacturing process is controlled in response to the priority determination.

Claims (11)

1. A method of controlling a manufacturing process, comprising:

monitoring operating conditions of plural process steps during the manufacturing process;

calculating a degree of risk for each of a malfunction operating condition step and subsequent steps, in accordance with selected data from plural manufacturing control parameters preliminarily obtained under a normal operating condition of the manufacturing process;

determining a priority of the manufacturing process needing recovery in response to the degree of risk for each of the malfunction operating condition step and subsequent steps; and

controlling an operating condition of the manufacturing process responsive to said determining,

wherein the degree of risk is classified into plural levels and is determined in accordance with a risk point on the basis of the following parameters: WIP minimum, WIP actual, WIP target and a weighting factor, wherein WIP is work in progress.

2. The method according to claim 1 , further comprising:

storing information being controlled by a control method for the manufacturing process, into a host computer through a local area network, wherein the information is accessible from a plurality of servers through an intranet.

3. The method according to claim 1 , wherein the risk point is determined as follows:

Risk point=weighting factor×( WIP target− WIP actual)/( WIP target− WIP minimum).

4. The method according to claim 1 , wherein the degree of risk is classified into six levels.