IP Library Granted Patent US 7,348,734
Granted Patent B2
US 7,348,734 · App. 11/172,086 · Granted Mar 25, 2008

Method for protecting a ballast from an output ground-fault condition

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,348,734
App. No.
11/172,086
Granted
Mar 25, 2008
Kind
B2
Abstract

A method ( 700 ) for protecting a ballast from an output ground-fault condition includes the steps of applying power to the ballast (step 710 ), providing a startup delay period for a DC-to-DC converter (step 730 ), monitoring a voltage across a DC blocking capacitor (step 740 ), preventing startup of the DC-to-DC converter in response to the voltage across the DC blocking capacitor being greater than a threshold value during the startup delay period (step 750 ), and allowing startup of the DC-to-DC converter in response to the voltage across the DC blocking capacitor being less than the threshold value throughout the startup delay period (step 760 ). Preferably, the steps of monitoring (step 740 ), preventing (step 750 ), and allowing (step 760 ) are implemented by a microcontroller, and the DC-to-DC converter is preferably implemented as either a Sepic converter or a buck converter.

Claims (31)

1. A method for protecting a ballast from an output ground-fault condition, the method comprising the steps of:

applying power to the ballast;

providing a startup delay period for a DC-to-DC converter;

monitoring a voltage across a direct current (DC) blocking capacitor, wherein the DC blocking capacitor is operably coupled in series with the at least one gas discharge lamp;

preventing startup of the DC-to-DC converter, in response to the voltage across the DC blocking capacitor being greater than a predetermined threshold value during the startup delay period; and

allowing startup of the DC-to-DC converter, in response to the voltage across the DC blocking capacitor being less than the predetermined threshold value throughout the startup delay period.

2. The method of claim 1 , further comprising the step of activating a microcontroller, wherein the step of activating the microcontroller is executed between the steps of applying power to the ballast and providing a startup delay period for a DC-to-DC converter.

3. The method of claim 2 , wherein the step of monitoring a voltage across a DC blocking capacitor is executed via the microcontroller.

4. The method of claim 3 , wherein the steps of preventing startup of the DC-to-DC converter and allowing startup of the DC-to-DC converter are executed via the microcontroller.

5. The method of claim 1 , wherein the DC-to-DC converter is one of: (i) a Sepic converter; and (ii) a buck converter.

6. The method of claim 1 , wherein the predetermined threshold value is on the order of about 100 millivolts.

7. A method for protecting a ballast for powering at least one gas discharge lamp from an output ground-fault condition, the method comprising the steps of:

applying power to the ballast;

activating a microcontroller;

providing a startup delay period for a Sepic converter;

monitoring a voltage across a direct current (DC) blocking capacitor that is operably coupled in series with the at least one gas discharge lamp;

preventing startup of the Sepic converter, in response to the voltage across the DC blocking capacitor being greater than a predetermined threshold value during the startup delay period; and

allowing startup of the Sepic converter, in response to the voltage across the DC blocking capacitor being less than a predetermined threshold value throughout the startup delay period.

8. The method of claim 7 , wherein the step of monitoring a voltage across a DC blocking capacitor is executed via the microcontroller.

9. The method of claim 8 , wherein the steps of preventing startup of the Sepic converter and allowing startup of the Sepic converter are executed via the microcontroller.

10. The method of claim 7 , wherein the predetermined threshold value is on the order of about 100 millivolts.

11. A method for protecting a ballast for powering at least one gas discharge lamp from an output ground-fault condition, the method comprising the steps of:

applying power to the ballast;

activating a microcontroller;

providing a startup delay period for a buck converter;

monitoring a voltage across a direct current (DC) blocking capacitor that is operatively coupled in series with the at least one gas discharge lamp;

preventing startup of the buck converter, in response to the voltage across the DC blocking capacitor being greater than a predetermined threshold value during the startup delay period; and

allowing startup of the buck converter, in response to the voltage across the DC blocking capacitor being less than the predetermined threshold value throughout the startup delay period.

12. The method of claim 11 , wherein the step of monitoring a voltage across a DC blocking capacitor is executed via the microcontroller.

13. The method of claim 12 , wherein the steps of preventing startup of the buck converter and allowing startup of the buck converter are executed via the microcontroller.

14. The method of claim 11 , wherein the predetermined threshold value is on the order of about 100 millivolts.

Assignments (2)
MERGER Recorded Dec 29, 2010
From: OSRAM SYLVANIA INC.
To: OSRAM SYLVANIA INC.
Reel/Frame 025549/0690 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 30, 2005
From: YADLAPALLI, NAVEEN
To: OSRAM SYLVANIA, INC.
Reel/Frame 016755/0701 →