IP Library Granted Patent US 7,302,917
Granted Patent B2
US 7,302,917 · App. 11/212,250 · Granted Dec 4, 2007

Chemical cleaning of a steam generator during mode 5 generator shut down

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,302,917
App. No.
11/212,250
Granted
Dec 4, 2007
Kind
B2
Abstract

A Nuclear Steam Supply Stem (NSSS) Mode 5 Steam Generator Chemical Cleaning system is disclosed which applies chemical cleaning solvent (formulated to remove SG deposits) to the secondary side of the SG using primary side supplied heat during NSS Mode 5 shutdown to maintain the desired application temperature. Mixing is achieved via nitrogen sparging.

Claims (12)

1. A method of cleaning a steam generator during mode 5 shut down operations at approximately 200 degrees F. to 210 degrees F. comprising the steps of:

using the steam generator primary side heat as the heat source to maintain the desired temperature;

injecting a precalculated amount of chemical cleaning solvent into the steam generaror;

introducing a nitrogen sparge into the steam generator to mix the solvent;

intermittently sampling the solvent to determine the cleaning effect of the solvent; and

removing the mixed solvent after a predetermined period of time.

2. A method of cleaning a steam generator as set forth in claim 1 wherein the chemical cleaning solvent is introduced into the steam generator along blowdown lines located along the bottom of the steam generator at the tubesheet.

3. A method of cleaning a steam generator as set forth in claim 1 wherein the nitrogen sparge is introduced intermittently.

4. A method of cleaning a steam generator as set forth in claim 3 wherein the sparge is introduced intermittently at a rate of 250-1500 cubic ft/minute.

5. A method of cleaning a steam generator as set forth in claim 4 wherein the nitrogen is introduced for 10 minute intervals every half hour.

6. A method of cleaning a steam generator as set forth in claim 1 wherein the mixed solvent is removed after approximately 24-36 hours.

7. A method of cleaning a steam generator as set forth in claim 1 including the step of returning the sample to the steam generator if the cleaning effect is not completed.

Assignments (2)
CHANGE OF NAME Recorded Mar 25, 2010
From: FRAMATOME ANP, INC.
To: AREVA NP INC.
Reel/Frame 024128/0638 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 15, 2007
From: REMARK, JOHN F.; EVANS, SARAH E.
To: FRAMATOME ANP, INC.
Reel/Frame 019989/0048 →