US 7,937,193 · App. 11/342,853 · Granted May 3, 2011

Method and apparatus for coordinating railway line of road and yard planners

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,937,193
App. No.
11/342,853
Granted
May 3, 2011
Kind
B2
Abstract

A scheduling system and method for moving plural objects through a multipath system described as a freight railway scheduling system. The scheduling system utilizes a resource scheduler to minimize resource exception while at the same time minimizing the global costs associated with the solution. The achievable movement plan can be used to assist in the control of, or to automatically control, the movement of trains through the system. Similar movement planners exist for moving trains in yards or terminals. Coordination is achieved and system efficiency improved by interfacing the line of road and yard planners.

Claims (12)

1. A railway scheduling system for scheduling the movement of trains through a rail network having line of road track and yard tracks comprising

a movement planner for a rail yard for scheduling the movement of cars through the yard, each car having an incremental cost associated with it, the yard movement planner optimizing the total costs of the movement of the cars through the yard, wherein the yard movement planner provides a schedule for individual cars of a specific train to perform specific tasks at specific locations in the rail yard and evaluates the specific locations to determine availability of the specific location; and

an interface for communicating information about determined availability at a specific location in the yard for the specific train to a line of road movement planner to optimize the total costs of the movement of the trains through the rail network;

wherein the movement planner for the line of road is configured for scheduling trains over the line of road, each train having an incremental cost associated with it, the line of road movement planner optimizing the total cost of the movement of the trains over the line of road, wherein the line of road movement planner schedules the movement of the specific train as a function of the determined availability at a specific location in the yard.

2. The system of claim 1 wherein the line of road movement planner delays the movement of the specific train into the yard in response to the communication from the yard movement planner.

3. The system of claim 1 wherein the line of road movement planner alters an arrival at the yard of a sequence of trains as a function of the scheduling of the selected train.

4. A method for scheduling the movement of trains through a rail network having line of road track and yard tracks comprising:

scheduling the movement of cars through a rail yard using a movement planner for the rail yard, each car having an incremental cost associated with it, the yard movement planner optimizing the total costs of the movement of the cars through the yard, wherein the yard movement planner provides a schedule for individual cars of a specific train to perform specific tasks at specific locations in the rail yard and evaluates the specific locations to determine availability of the specific locations;

communicating information about determined availability at a specific location in the yard for the specific train to a line of road movement planner to optimize the total costs of the movement of the trains through the rail network; and

scheduling trains over the line of road using the line of road movement planner, each train having an incremental cost associated with it, the line of road movement planner optimizing the total cost of the movement of the trains over the line of road, wherein the line of road movement planner schedules the movement of the specific train as a function of the determined availability at the specific location in the yard.

5. The method of claim 4 , wherein the specific location in the yard includes at least one of receiving track, hump track, maintenance track and classification track.

6. The method of claim 4 wherein the line of road movement planner alters an arrival at the yard of a sequence of trains as a function of the scheduling of the selected train.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 6, 2018
From: GENERAL ELECTRIC COMPANY
To: GE GLOBAL SOURCING LLC
Reel/Frame 047736/0178 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 23, 2006
From: PHILP, JOSEPH WESLEY; WILLS, MITCHELL SCOTT; MACEO, JOANNE
To: GENERAL ELECTRIC COMPANY
Reel/Frame 017920/0531 →