Method and system for performing operations on a wind turbine

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,735,808
App. No.
11/638,863
Granted
Jun 15, 2010
Kind
B2
Abstract

A wind turbine has a nacelle frame and a first hoist substantially permanently mounted on the frame. The method comprises the processes of hoisting a second, more powerful hoist and crane on the frame with the first hoist; removably mounting the second hoist and the crane on the nacelle frame; hoisting a winch using the second hoist and the crane on the frame, and removably mounting the winch on said frame; performing operations involving handling heavy parts employing said winch; and removing and lowering said winch, crane, and second hoist from the frame.

Claims (40)

1. A method of providing heavy lift capability to a wind turbine having a nacelle frame and a first hoist substantially permanently mounted on said nacelle frame for maintenance operations, said method comprising:

utilizing said first hoist to lift a second hoist on said nacelle frame, said second hoist capable of lifting a heavier load than said first hoist;

mounting said second hoist on said nacelle frame;

mounting a crane proximate a rear portion of said nacelle frame;

utilizing said second hoist and said crane to lift a winch to said nacelle frame;

mounting said winch to said nacelle frame; and,

performing lifting and lowering operations with at least said winch that involve handling heavy parts of said wind turbine.

2. The method of claim 1 , wherein mounting said crane on said nacelle frame is completed such that said crane is removable.

3. The method of claim 2 , wherein mounting the winch on the nacelle frame is completed such that said winch is removable.

4. The method of claim 1 , further comprising moving said first hoist along an upper section member of said nacelle frame.

5. The method of claim 4 wherein said moving said first hoist comprises moving on one or more wheels or one or more rails along said upper section member.

6. The method of claim 5 wherein said winch is hoisted on said nacelle frame together with a coupling structure for mounting said winch to said nacelle frame.

7. The method of claim 1 , further comprising moving said winch along an upper section member of said nacelle frame.

8. The method of claim 7 wherein said moving said winch comprises moving on one or more wheels or one or more rails along said upper section member.

9. The method of claim 1 , wherein said winch is capable of lifting heavier parts of said wind turbine than said first or second hoists.

10. The method of claim 1 , further comprising removing and lowering said winch from said nacelle frame.

11. The method of claim 10 , further comprising removing and lowering said crane from said nacelle frame.

12. A method for performing operations on a wind turbine that involve handling heavy parts, said wind turbine comprising a nacelle frame with a first hoist permanently mounted on said nacelle frame such that said first hoist is capable of moving in at least a lengthways direction along said nacelle frame, said method comprising:

lifting a second hoist to said nacelle frame using said first hoist, said second hoist capable of lifting a heavier load than said first hoist;

mounting said second hoist on said nacelle frame;

hoisting a cable winch on the nacelle frame by said second hoist;

mounting said winch on said nacelle frame such that said winch is capable of moving along said nacelle frame parallel to said first hoist;

performing operations with said winch that involve handling said heavy parts of said wind turbine;

removing and lowering said winch from said nacelle frame using said second hoist; and

removing said second hoist from said nacelle frame and lowering said second hoist using said first hoist.

13. The method of claim 12 , further comprising moving at least one of said first hoist and said winch along said nacelle frame on one or more wheels or one or more rails.

14. A system for performing operations on a wind turbine nacelle frame comprising:

a first hoist substantially permanently mounted along an upper section member of said nacelle frame; and,

a second hoist adapted to be positioned along a lower section member of said nacelle frame by said first hoist;

wherein said first hoist can translate in at least one direction relative to said second hoist.

15. The system of claim 14 , wherein said first hoist is mounted on a structure consisting of one or more wheels or one or more rails along said upper section member of said nacelle frame.

16. The system of claim 14 , wherein a winch is adapted to be hoisted to said upper portion of said nacelle frame by said second hoist, said winch suitable for handling one or more parts of said wind turbine selected from the group comprising: a generator, a gearbox, and a transformer of said wind turbine.

17. A nacelle frame assembly for a wind turbine comprising:

a nacelle frame having an upper section member and a lower section member;

a first hoist substantially permanently mounted along said upper section member, said first hoist capable of movement along said upper section member;

a second hoist temporarily mounted along said lower section member of said nacelle frame;

a crane temporarily positioned at a rear portion of said nacelle frame and coupled to said second hoist; and,

a winch temporarily mounted along said upper section member of said nacelle frame;

wherein said winch is used to move heavy wind turbine parts to and from said nacelle frame.

18. The nacelle frame assembly of claim 17 , wherein said winch is capable of movement along one or more rails of said upper section member.

Assignments (8)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 4, 2017
From: GE RENEWABLE TECHNOLOGIES
To: GE RENEWABLE TECHNOLOGIES WIND B.V.
Reel/Frame 044117/0056 →
CHANGE OF NAME Recorded Sep 2, 2017
From: ALSTOM RENEWABLE TECHNOLOGIES
To: GE RENEWABLE TECHNOLOGIES
Reel/Frame 043749/0761 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 10, 2017
From: ALSTOM RENOVABLES ESPAÑA, S.L.U.
To: ALSTOM RENEWABLE TECHNOLOGIES
Reel/Frame 042325/0649 →
CHANGE OF NAME Recorded May 9, 2017
From: ALSTOM HYDRO ESPAÑA, S.L.U.
To: ALSTOM RENOVABLES ESPAÑA, S.L.
Reel/Frame 042286/0195 →
MERGER Recorded Mar 28, 2017
From: ALSTOM WIND, S.L.U.
To: ALSTOM HYDRO ESPAÑA, S.L.U.
Reel/Frame 042103/0935 →
RE-RECORD TO CORRECT THE ASSIGNOR NAME PREVIOUSLY RECORDED AT REEL/FRAME 028820/0843 Recorded Aug 28, 2012
From: ECOTECNIA, SOCIEDAD COOPERATIVA CATALANA LIMITADA (ECOTECNIA, S. COOP.C.L.)
To: ECOTECNIA ENERGIAS RENOVABLES S.L.
Reel/Frame 028932/0012 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 21, 2012
From: ECOTENCNIA SOCIEDAD COOPERATIVA LIMITADA (ECOTECNIA, S.COOP.C.L.)
To: ECOTECNIA ENERGIAS RENOVABLES S.L.
Reel/Frame 028820/0843 →
CHANGE OF NAME Recorded Aug 21, 2012
From: ECOTECNIA ENERGIAS RENOVABLES S.L.
To: ALSTOM WIND S.L.
Reel/Frame 028824/0275 →