Abstract

A method and apparatus for stick-building large buildings (e.g., single-family homes, townhouses, apartment complexes, commercial structures, multi-story buildings, buildings legally or physically too large or oddly shaped to be transported substantially intact via public roads, etc.) within a factory is presented. The factory can be constructed on or near the intended building destination(s). The factory can include a large enclosed structure that shelters the construction process, the raw materials and/or workers from the extremes or effects of the natural elements. Inside the factory, one or more buildings are constructed using stick-building construction techniques (e.g., constructing the building from raw materials without pre-manufactured panels or modular sections). The factory can use assembly line and/or assembly point stick-building techniques.

Claims (28)

1 . A building manufacturing facility comprising:

an enclosed building;

a materials source; and

a construction area within the enclosed building, wherein the construction area is configured to receive materials from the materials source and to enable stick-building of a large building within the enclosed building using the materials, wherein the enclosed building is configured to enable the large building to be moved from the enclosed building to another location.

2 . The building manufacturing facility of claim 1 , wherein the materials source is within the enclosed building.

3 . The building manufacturing facility of claim 1 , wherein the materials source is a storage area.

4 . The building manufacturing facility of claim 1 further comprising:

a delivery alley, wherein the materials are delivered via the delivery alley to the materials source.

5 . The building manufacturing facility of claim 1 , wherein the large building has more than one level.

6 . The building manufacturing facility of claim 1 , wherein the large building cannot be legally transported via public roads.

7 . The building manufacturing facility of claim 1 , wherein the construction area includes an assembly line.

8 . The building manufacturing facility of claim 1 , wherein the construction area includes an assembly point at which the large building is substantially completely constructed.

9 . A method of building a large building comprising:

receiving materials from a materials source at a construction area within an enclosed building;

stick-building the large building within the enclosed building using the materials, and

transporting the large building substantially intact from the enclosed building to another location.

10 . The method of claim 9 , wherein the materials source is within the enclosed building.

11 . The method of claim 9 , wherein the materials source is a storage area.

12 . The method of claim 9 further comprising:

delivering the materials to the materials source a delivery alley.

13 . The method of claim 9 , wherein the large building has more than one level.

14 . The method of claim 9 , wherein the large building cannot be legally transported via public roads.

15 . The method of claim 9 , wherein the construction area includes an assembly line.

16 . The method of claim 9 , wherein the construction area includes an assembly point at which the large building is substantially completely constructed.

17 . The method of claim 9 , wherein stick-building the large home includes stick-building a planted roof.

18 . The method of claim 17 , wherein the planted roof includes a watering system connected to the plumbing system of the large building.

19 . The method of claim 9 , wherein the other location is the large building's substantially permanent building site.

20 . The method of claim 9 , wherein the other location is a temporary storage location.

Assignments (5)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 3, 2012
From: ONO, TERRY
To: CUSTOM QUALITY HOMES, LLC
Reel/Frame 028734/0397 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 12, 2010
From: CUSTOM QUALITY HOMES, LLC
To: ONO, TERRY
Reel/Frame 024221/0566 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 28, 2007
From: PRIDDY, MATTHEW
To: CUSTOM QUALITY HOMES L.L.C.
Reel/Frame 020171/0309 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 28, 2007
From: RHODES, JAMES
To: CUSTOM QUALITY HOMES L.L.C.
Reel/Frame 020171/0314 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 28, 2007
From: RHODES DESIGN AND DEVELOPMENT CORPORATION
To: CUSTOM QUALITY HOMES, L.L.C.