Exhaust gas treating method

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,691,349
App. No.
12/117,419
Granted
Apr 6, 2010
Kind
B2
Abstract

An exhaust gas processing method using a device having an air preheater for preheating air for combustion in a combustion device by using an exhaust gas emitted from the combustion device; a gas-gas heater (GGH) heat recovery device composed of a heat transfer tube for recovering the heat of the exhaust gas to a heat medium; a dust collector; a wet-type desulfurization device; a gas-gas heater (GGH) re-heater composed of a heat transfer tube for heating the exhaust gas at its outlet by using the heat medium supplied from the gas-gas heater heat recovery device, which are installed in that order from the upstream to the downstream of an exhaust gas duct of the combustion device.

Claims (9)

1. A method of treating exhaust gas in an exhaust gas processing device comprising: preheating air for combustion in a combustion device by using exhaust gas emitted from the combustion device; recovering heat of the exhaust gas at an outlet of an air preheater to a heat medium; collecting dust in the exhaust gas at an outlet of a gas-gas heater heat recovery device using a dust collector; removing sulfur oxide in the exhaust gas at an outlet of the dust collector; heating the exhaust gas at the outlet of a wet-type desulfurization device by using the heat medium supplied from the gas-gas heater heat recovery device; connecting heat transfer tubes provided in each of the gas-gas heater heat recovery device and the gas-gas heater re-heater; and circulating the heat medium through the heat transfer tubes; squarely arranging the heat transfer tube of the gas-gas heater heat recovery device in the gas flow direction in such a manner that the inter-tube flow rate, which is the flow rate of the exhaust gas between the heat transfer tubes adjacent in the direction orthogonal to the gas flow direction, can be less than or equal to approximately 10 m/s, wherein at least some of the heat transfer tubes of the gas-gas heater are fin-equipped heat transfer tubes, and the fin pitch of the heat transfer tubes of the gas-gas heater heat recovery device is set at approximately 7.25 to approximately 10.16 mm, and the fin pitch of the heat transfer tubes of the gas-gas heater re-heater is set at approximately 6.35 to approximately 8.47 mm.

2. The method of claim 1 , further comprising positioning the dust collector between the wet-type desulfurization device and the gas-gas heater re-heater in the exhaust gas duct.

3. The method of claim 1 , further comprising installing, on the stage preceding the fin-equipped heat transfer tubes of the gas-gas heater re-heater, at least three stages of the heat transfer tubes comprising a bare tube, and staggeredly arranging the bare tube in the gas flow direction so that the inter-tube flow rate, which is the flow rate of the exhaust gas between the heat transfer tubes adjacent in the direction orthogonal to the gas flow direction, cannot be more than approximately 12 to approximately 16 m/s.

4. The method of claim 3 , wherein the heat transfer tubes comprising the bare tube installed in the stage preceding the fin-equipped heat transfer tubes of the gas-gas heater re-heater are one of: a part of the heat medium circulation line for circulating the heat medium through the gas-gas heater heat recovery device and the gas-gas heater re-heater, or a steam line for flowing steam that is installed separately from the heat medium circulation line.

5. The method of claim 1 , further comprising tying the heat transfer tubes of the gas-gas heater heat recovery device in bundles each having a prescribed number of heat transfer tubes, wherein the bundles each comprise heat transfer tubes of not more than eight stages arranged in the gas flow direction and have a width of approximately 3000 mm or less in the direction generally orthogonal to the gas flow direction, and dust removers are installed in front and in back of the bundles in the gas flow direction.

6. The method of claim 4 , further comprising:

providing one of the gas-gas heater heat recovery device or the gas-gas heater re-heater with dust removers;

providing at least one of differential pressure gauges and thermometers in front and in back of the bundles in the gas flow direction; and

activating, using at least one controller, the dust removers when the measured values of the at least one of differential pressure gauges and the thermometers become higher or lower than at least one predetermined value.

Assignments (2)
MERGER Recorded Feb 17, 2015
From: BABCOCK-HITACHI K.K.
To: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
Reel/Frame 035003/0333 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 24, 2008
From: MURAMOTO, KOUJI; SAITOU, TAKAYUKI; SHIMAZU, HIROMICHI; NAKAMOTO, TAKANORI; KATSUBE, TOSHIO
To: BABCOCK-HITACHI KABUSHIKI KAISHA
Reel/Frame 021286/0739 →