IP Library Granted Patent US 8,864,423
Granted Patent B2
US 8,864,423 · App. 12/349,927 · Granted Oct 21, 2014

Geomembrane protective cover

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,864,423
App. No.
12/349,927
Granted
Oct 21, 2014
Kind
B2
Abstract

A pond liner system includes a geomembrane liner ( 12 ), a binder ( 22 ) and a particulate ( 24 ). The geomembrane liner ( 12 ) has a submerged portion ( 14 ), an exposed portion ( 15 ) and an anchor portion ( 16 ). The binder ( 22 ) adheres to the exposed portion ( 15 ) of the geomembrane liner, and the particulate ( 24 ) adheres to the binder ( 22 ). A method of applying a protective cover to the exposed portion ( 15 ) of the geomembrane liner includes spraying the binder ( 22 ) onto the liner ( 12 ), allowing the binder ( 22 ) to partially cure, and spreading the particulate ( 24 ) over the partially cured binder ( 22 ).

Claims (25)

1. A pond lining system for use in a basin located within the ground, wherein the basin includes a bottom, sloped walls, and a bank which provides a transition between the sloped walls and a surrounding ground surface, the pond lining system comprising:

a polymeric geomembrane liner having a base portion adapted to be positioned within the basin and wherein the base portion is below a water surface when water is received in the basin, an intermediate portion adapted to be positioned on the bank which is above the water surface and substantially parallel thereto, and an anchor portion adapted to be positioned below ground and spaced from the base portion by said intermediate portion;

a urethane binder layer adhesively secured over and to the intermediate portion of the geomembrane liner and above the water surface when water is received in the basin, the base portion and the anchor portion being substantially devoid of said urethane binder layer, said urethane binder layer disposed in a uniform and uninterrupted layer; and

a particulate embedded in the urethane binder layer, the particulate being a mixture of dirt and sand.

2. The pond lining system of claim 1 where said intermediate portion is positioned between said base portion and said anchor portion so that said anchor portion is positioned away from the base portion.

3. A pond lining system for use in a basin located within the ground, wherein the basin includes a bottom, sloped walls and a bank which provides a transition between the sloped walls and a surrounding ground surface, the pond lining system comprising:

a polymeric geomembrane liner having a base portion adapted to be positioned in the basin and below water received in the basin, an exposed intermediate portion, and an anchor portion adapted to be positioned below ground and spaced from the base portion, said exposed intermediate portion adapted to be positioned between said base portion and said anchor portion so that said anchor portion is adapted to be positioned away from the water and so that said exposed intermediate portion is on the bank and above the water surface and substantially parallel with the bank;

a urethane binder layer; and

a fine particulate layer, wherein a first side of said urethane binder layer is affixed to said exposed intermediate portion of said geomembrane liner by adhesive properties of the urethane binder layer so that said urethane binder layer is positioned primarily on said exposed intermediate portion and in a uniform and uninterrupted layer, wherein a second side of said urethane binder layer is affixed to said fine particulate layer by the adhesive properties of the urethane binder layer, and wherein said base portion and said anchor portion are substantially devoid of said urethane binder layer.

4. The pond lining system of claim 3 where said fine particulate layer is a dirt and sand composition.

5. The pond lining system of claim 4 where said dirt and sand composition is at least twenty-five percent sand.

6. The pond lining system of claim 3 where the polymeric geomembrane liner is a thermoplastic membrane.

7. The pond lining system of claim 3 where the polymeric geomembrane liner is a thermoset membrane.

8. The pond lining system of claim 3 where a portion of said urethane binder layer extends toward said base portion.

9. A method of installing a geomembrane liner used in a basin located within the ground, wherein the basin includes a bottom, sloped walls and a bank which provides a transition between the sloped walls and a surrounding ground surface, the pond lining system comprising:

positioning the geomembrane liner in a desired location, the geomembrane liner including a top surface and a base portion, an intermediate portion, and an anchor portion;

spraying a urethane binder on the top surface of the intermediate portion of said geomembrane liner so as to form a uniform binder layer, and leaving the top surface of said base portion and said anchor portion devoid of said urethane binder;

allowing said urethane binder layer to partially cure so that it is tacky;

distributing a particulate over said urethane binder layer by using a blowing device;

allowing said urethane binder layer to fully cure and bond to said top surface of the intermediate portion and said particulate;

covering the anchor portion of said geomembrane liner with soil; and

covering the base portion of said geomembrane liner with water so that a substantial portion of said intermediate portion and said particulate with said binder is above the water and substantially parallel thereto.

10. The method of claim 9 where said particulate is a dirt and sand composition.

11. The method of claim 9 where the anchor portion is positioned away from the base portion.

12. The method of claim 9 wherein covering the base portion of said geomembrane liner with water so that a portion of said intermediate portion and said particulate with said urethane binder layer extends below the water.

Assignments (4)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 26, 2022
From: FIRESTONE BUILDING PRODUCTS COMPANY, LLC
To: HOLCIM TECHNOLOGY LTD
Reel/Frame 060920/0869 →
CORRECTIVE ASSIGNMENT TO CORRECT THE INCORRECT APPL. NO. 13/389,145 PREVIOUSLY RECORDED AT REEL: 027501 FRAME: 0322. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Jan 15, 2018
From: FIRESTONE DIVERSIFIED PRODUCTS, LLC
To: FIRESTONE BUILDING PRODUCTS COMPANY, LLC
Reel/Frame 045071/0576 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 9, 2012
From: FIRESTONE DIVERSIFIED PRODUCTS, LLC
To: FIRESTONE BUILDING PRODUCTS COMPANY, LLC
Reel/Frame 027501/0318 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 5, 2009
From: OLIVEIRA, PAUL
To: FIRESTONE DIVERSIFIED PRODUCTS, LLC
Reel/Frame 022212/0886 →