IP Library Granted Patent US 8,291,977
Granted Patent B2
US 8,291,977 · App. 12/463,996 · Granted Oct 23, 2012

Oil well plug and abandonment method

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,291,977
App. No.
12/463,996
Granted
Oct 23, 2012
Kind
B2
Abstract

A method of severing a well string that extends into an oil well from an oil platform with a deck includes supporting upper and lower sections of the well string, the lower section supported at the platform deck with a deck located string support. A shear mechanism cuts the well string at a position that can be above the deck located string support. The upper section is then lifted a selected distance and the deck located string support again supports the string at a position below the cut.

Claims (57)

1. A method of severing a well string that extends into an oil well from an oil platform with a deck, comprising the steps of:

a) supporting upper and lower sections of the well string above said deck;

b) providing a hydraulic shear mechanism having a frame and a pair of jaws, one jaw that pivotally moves relative to said frame between open and closed positions, wherein there is a open end of the frame in between the jaws that enables quick placement of the well string in between the jaws when the jaws are in the open position;

c) moving the shear mechanism to a position above the platform deck and away from the well string;

d) opening the jaws to the open position and then placing the well string in between the jaws via the open end of the frame;

e) shearing the well string to form a cut by pivoting at least one jaw relative to the frame so that the jaws are in the closed position, in said closed position the jaws abutting to form said cut and wherein a hydraulic cylinder pivots said at least one jaw relative to the frame to achieve said closed position;

f) removing the upper well string section that is above the cut of step “e”;

g) lifting the lower section of the well string upwardly a selected distance so that it provides upper and lower sections of the well string above the deck; and

h) repeating steps “a” through “f” and wherein the shear mechanism remains above the deck.

2. The method of claim 1 wherein the well string is production tubing.

3. The method of claim 1 wherein the well string is casing.

4. The method of claim 3 wherein the casing includes multiple concentric casings defining multiple layers.

5. The method of claim 4 wherein there is cementitious material between at least two of said layers.

6. The method of claim 4 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

7. The method of claim 3 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

8. The method of claim 1 wherein in step “a” slips support the well string at least in part.

9. The method of claim 1 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

10. The method of claim 9 wherein the pin rests upon a pair of spaced apart beams in step “a”.

11. The method of claim 1 , wherein the well string is a production casing.

12. A method of severing a well string that extends into an oil well from an oil platform with a deck, comprising the steps of:

a) supporting the well string at a first elevation, the well string including upper and lower sections;

b) providing a hydraulic shear mechanism that has a frame, one fixed jaw on the frame and one moving jaw that pivotally attaches to the frame, said moving jaw being movable between open and closed positions, wherein there is provided an open end in between the jaws into which an elongated section of well string can be placed by moving the well string horizontally;

c) placing the shear mechanism next to the platform deck with the moving jaw in the open position to accept the well string;

d) moving the well string and shear mechanism relative to one another so that the well string moves into the open end of the frame and wherein the well string is positioned in between the jaws;

e) shearing the well string with the shear mechanism to form a cut in the well string;

f) removing the upper, cut well string section above the cut;

g) elevating the well string a selected distance so that upper and lower well string sections are provided above said deck;

h) repeating steps “c” through “g”, wherein the shear mechanism remains above the deck.

13. The method of claim 12 wherein the well string is production tubing.

14. The method of claim 12 wherein the well string is casing.

15. The method of claim 14 wherein the casing includes multiple concentric casings defining multiple layers.

16. The method of claim 15 wherein there is cementitious material in between at least two of said layers.

17. The method of claim 15 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

18. The method of claim 14 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

19. The method of claim 12 wherein in step “a” slips support the well string at least in part.

20. The method of claim 12 wherein step “a” comprises drilling an opening through the well string and inserting a pin through the drilled opening.

21. The method of claim 20 wherein the pin rests upon a pair of spaced apart beams in step “a”.

22. The method of claim 12 wherein the well string is a production casing.

23. A method of severing a well string that extends into an oil well from an oil platform with a deck, comprising the steps of:

a) supporting the well string at a first elevation with a support that is positioned at the deck;

b) providing a hydraulic shear mechanism having a frame and a pair ofjaws, one jaw that pivotally moves relative to said frame between open and closed positions, wherein there is a open end of the frame in between the jaws that enables quick placement of the well string in between the jaws when the jaws are in the open position by moving the well string laterally into said open end and in between the jaws;

c) placing the shear mechanism next to and above the platform deck;

d) shearing the well string above the platform deck with the shear mechanism to form a cut in the well string;

e) removing an upper, cut well string section above the cut of step “d”;

f) removing the support of step “a”;

g) elevating the well string a selected distance; and

h) repeating steps “c” through “g”, wherein the shear mechanism is positioned above the deck.

24. The method of claim 23 wherein the well string is production tubing.

25. The method of claim 23 wherein the well string is casing.

26. The method of claim 25 wherein the casing includes multiple concentric casings defining multiple layers.

27. The method of claim 26 wherein there is cementitious material in between at least two of said layers.

28. The method of claim 26 wherein step “a” comprises drilling an opening through each of the concentric casings.

29. The method of claim 25 wherein in step “a” the support includes a pin, and the method includes drilling an opening through the well string and inserting the pin through the drilled opening.

30. The method of claim 23 wherein in step “a” the support includes slips that support the well string at least in part.

31. The method of claim 23 wherein in step “a” the support includes a pin, and the method includes drilling an opening through the well string and inserting the pin through the drilled opening.

32. The method of claim 31 wherein the pin rests upon a pair of spaced apart beams.

33. The method of claim 23 wherein the well string is a production casing.

Assignments (5)
RELEASE OF SECURITY INTEREST Recorded Aug 17, 2018
From: RESOLUTE III DEBTCO LLC, AS ADMINISTRATIVE AGENT
To: GULFSTREAM SERVICES, INC.
Reel/Frame 046860/0353 →
ASSIGNMENT OF INTELLECTUAL PROPERTY SECURITY AGREEMENTS Recorded Jun 28, 2018
From: ANTARES CAPITAL LP, AS TRANSFERRING ADMINISTRATIVE AGENT
To: RESOLUTE III DEBTCO LLC, AS SUCCESSOR ADMINISTRATIVE AGENT
Reel/Frame 046459/0743 →
ASSIGNMENT OF INTELLECTUAL PROPERTY SECURITY AGREEMENTS Recorded Aug 24, 2015
From: GENERAL ELECTRIC CAPITAL CORPORATION, AS THE CURRENT AND RESIGNING ADMINISTRATIVE AGENT
To: ANTARES CAPITAL LP, AS SUCCESSOR ADMINISTRATIVE AGENT
Reel/Frame 036435/0614 →
PATENT SECURITY AGREEMENT Recorded Oct 17, 2014
From: GULFSTREAM SERVICES, INC.
To: GENERAL ELECTRIC CAPITAL CORPORATION, AS COLLATERAL AGENT
Reel/Frame 034013/0444 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 14, 2012
From: MIRE, MICHAEL
To: GULFSTREAM SERVICES, INC.
Reel/Frame 028962/0783 →