IP Library Granted Patent US 8,162,110
Granted Patent B2
US 8,162,110 · App. 12/488,120 · Granted Apr 24, 2012

Rope tension equalizer and load monitor

Assignee: ThyssenKrupp Elevator Capital Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,162,110
App. No.
12/488,120
Granted
Apr 24, 2012
Kind
B2
Abstract

An apparatus for automatically equalizing the uneven tension between ropes of an elevator in combination with a load cell to determine elevator load. The load of an elevator car having multiple tension members is automatically balanced while load is measured using a single load cell. The incorporation of a load cell with an autobalancing system allows for an accurate measure of an elevator load to be taken while providing the benefits of having uniform rope lengths in the elevator system. The apparatus may have various arrangements, including an in-line configuration and a grouped configuration. The apparatus may also dampen the vibration energy that is usually imparted to an elevator car.

Claims (40)

1. A rope tension equalizer apparatus comprising:

(a) an upper sheave section, the upper sheave section having a plurality of upper sheaves;

(b) a lower sheave section, the lower sheave section having a plurality of lower sheaves;

(c) a compensation rope, the compensation rope having a first end and a second end, wherein the compensation rope is threaded through the plurality of upper sheaves and lower sheaves; and

(d) a load sensor, the load sensor being associated with the compensation rope, wherein the load sensor is configured to measure the load of an elevator car.

2. The apparatus of claim 1 , wherein the compensation rope is divided into a plurality of compensation rope portions extending between the upper sheave portion and the lower sheave portion, wherein each of the plurality of compensation rope portions bears a load.

3. The apparatus of claim 2 , wherein the sum of the load borne by each of the plurality of compensation rope portions is equal to the total load of the elevator car.

4. The apparatus of claim 3 , wherein the load of the elevator car is distributed equally to each of the plurality of compensation rope portions.

5. The apparatus of claim 4 , wherein the load sensor is a single load sensor associated with one of the plurality of compensation rope portions.

6. The apparatus of claim 5 , further comprising a computer, wherein the load measured by the single load sensor is multiplied by the number of compensation rope portions to calculate the total load of the elevator car.

7. The apparatus of claim 6 , wherein the computer is configured to control the operation of an elevator based upon the total load of the elevator car.

8. The apparatus of claim 7 , wherein the compensation rope comprises an aramid fiber rope.

9. The apparatus of claim 1 , wherein the load cell is associated with the first end of the compensation rope.

10. The apparatus of claim 1 , wherein the plurality of upper sheaves and the plurality of lower sheaves are arranged in an in-line configuration.

11. The apparatus of claim 1 , wherein the plurality of upper sheaves and the plurality of lower sheaves are arranged in a grouped configuration.

12. The apparatus of claim 1 , wherein the plurality of lower sheaves are full sheaves with bearings.

13. The apparatus of claim 1 , wherein the plurality of lower sheaves are half sheaves.

14. An elevator system, comprising:

(a) an elevator car; and

(b) a rope tension equalizer apparatus comprising

(i) an upper sheave section, the upper sheave section having a plurality of upper sheaves;

(ii) a lower sheave section, the lower sheave section having a plurality of lower sheaves and wherein the lower sheave section is supported by the elevator car;

(iii) a compensation rope, the compensation rope having a first end and a second end, wherein the compensation rope is threaded through the plurality of upper sheaves and lower sheaves; and

(iv) a load sensor, the load sensor being associated with the compensation rope, wherein the load sensor is configured to measure the load of the elevator car.

15. The system of claim 14 , wherein the compensation rope is divided into a plurality of compensation rope portions extending between the upper sheave portion and the lower sheave portion, wherein each of the plurality of compensation rope portions bears a load.

16. The system of claim 15 , wherein the sum of the load borne by each of the plurality of compensation rope portions is equal to the total load of the elevator car.

17. The system of claim 16 , wherein the load of the elevator car is distributed equally to each of the plurality of compensation rope portions.

18. The system of claim 17 , wherein the load sensor is a single load sensor associated with one of the plurality of compensation rope portions.

19. The system of claim 18 , further comprising a computer, wherein the computer multiples the number of compensation rope portions by the load measured by the single load sensor to calculate the total load of the elevator car, and wherein the computer is configured to control the operation of an elevator based upon the total load of the elevator car.

20. A method of equalizing the tension between a plurality of elevator ropes, the method comprising the following steps:

providing an elevator system, the elevator system comprising

(a) an elevator car, wherein the elevator car comprises a total load; and

(b) a rope tension equalizer apparatus comprising

(i) an upper sheave section, the upper sheave section having a plurality of upper sheaves;

(ii) a lower sheave section, the lower sheave section having a plurality of lower sheaves and wherein the lower sheave section is supported by the elevator car;

(iii) a compensation rope, the compensation rope having a first end and a second end, wherein the compensation rope is threaded through the plurality of upper sheaves and lower sheaves, and wherein the compensation rope comprises a tension; and

(iv) a load sensor, the load sensor being associated with the compensation rope, wherein the load sensor is configured to measure the load of the elevator car;

measuring the tension existing in a portion of a compensation rope;

computing the total load of the elevator car; and

directing the operation of the elevator car based upon the total load of the elevator car.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 1, 2012
From: THYSSENKRUPP ELEVATOR CAPITAL CORPORATION
To: THYSSENKRUPP ELEVATOR CORPORATION
Reel/Frame 029224/0893 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 21, 2009
From: SMITH, RORY S.; PARKER, ALAN M.; PHAN, CHI
To: THYSSENKRUPP ELEVATOR CAPITAL CORPORATION
Reel/Frame 023128/0250 →
Continuity (2)
Provisional Application 61073911 · Jun 19, 2008
Related Publication 20090314584A1 · Dec 24, 2009