IP Library Patent Application 12576913
Patent Application
App. No. 12/576,913

Physical Event Management During Asset Tracking

Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US None
App. No.
12/576,913
Abstract

Techniques for physical event management while tracking physical assets are disclosed. In one aspect, data identifying locations of interest in a journey of an asset is received. A position fix for the asset is received and a determination is made that the asset is within a location of interest. In another aspect, data identifying one or more milestones in a journey of the asset is received. An event notification is received from a tag coupled to the asset, and it is determined that there is a problem in the shipment of the asset. In yet another aspect, data identifying one or more actions that should be taken after events of interest in a journey of the asset is received. An event notification is received from a tag coupled to the asset, and it is determined that a particular action should be taken.

Claims (77)

1 . A computer-implemented method, comprising:

receiving milestone data for an asset, the milestone data identifying one or more milestones in a journey of the asset, each milestone having an associated location;

receiving an event notification from a tag coupled to the asset, the event notification describing a physical state of the asset;

determining that there is a problem in the shipment of the asset from the milestone data and the physical state of the asset;

generating a warning notification, the warning notification warning of the problem in the shipment of the asset.

2 . The method of claim 1 , wherein the problem is a future problem in the shipment of the asset that will occur if corrective action is not taken.

3 . The method of claim 1 , wherein the milestone data comprises an estimated schedule of the journey of the asset.

4 . The method of claim 1 , wherein the milestone data comprises an enterprise policy, the enterprise policy specifying relative milestones in the journey of the asset.

5 . The method of claim 1 , wherein:

the milestone data includes a scheduled arrival time for the asset;

determining that there is a problem in the shipment of the asset comprises determining that the asset will be late arriving at the destination location.

6 . The method of claim 1 , wherein:

the milestone data includes a scheduled departure time by which the asset should leave a location; and

determining that there is a problem in the shipment of the asset comprises determining that the asset will be late leaving the location.

7 . The method of claim 6 , wherein the location is chosen from the group consisting of: an origin location and a port.

8 . The method of claim 1 , wherein:

the milestone data includes a vessel cut-off deadline; and

determining that there is a problem in the shipment of the asset comprises determining that the asset will miss the vessel cut-off deadline.

9 . The method of claim 1 , wherein determining that there is a problem in the shipment of the asset comprises determining that the asset was not on a conveyance at a scheduled time of departure for the conveyance.

10 . The method of claim 1 , wherein:

the milestone data includes a deadline by which the asset should arrive at a port; and

determining that there is a problem in the shipment of the asset comprises determining that the asset will not arrive at the port by the deadline.

11 . The method of claim 1 , wherein:

the milestone data includes a deadline by which the asset should clear customs; and

determining that there is a problem in the shipment of the asset comprises determining that the asset will not clear customs by the deadline.

12 . The method of claim 1 , wherein:

the milestone data includes a deadline by which the asset should be unsealed; and

determining that there is a problem in the shipment of the asset comprises determining that the asset will not be unsealed by the deadline.

13 . A system comprising:

a processor; and

a computer readable medium coupled to the processor and including instructions, which, when executed by the processor, causes the processor to perform operations comprising:

receiving milestone data for an asset, the milestone data identifying one or more milestones in a journey of the asset, each milestone having an associated location;

receiving an event notification from a tag coupled to the asset, the event notification describing a physical state of the asset;

determining that there is a problem in the shipment of the asset from the milestone data and the physical state of the asset;

generating a warning notification, the warning notification warning of the problem in the shipment of the asset.

14 . A computer-implemented method, comprising:

receiving dependent process data for an asset, the dependent process data identifying one or more actions that should be taken after events of interest in a journey of the asset;

receiving an event notification from a tag coupled to the asset, the event notification describing a physical state of the asset;

determining, from the event notification that an event has occurred, and then determining, from the dependent process data that a particular action should be taken; and

generating an action notification, the action notification indicating that the particular action should be taken.

15 . The method of claim 14 , wherein the action notification instructs a system to take the particular action.

16 . The method of claim 15 , wherein instructing the system to take the particular action comprises instructing the system through a system-to-system interface.

17 . The method of claim 15 , wherein instructing the system to take the particular action comprises instructing the system using an electronic data interchange message.

18 . The method of claim 15 , wherein the system is chosen from the group consisting of: an order management system, a warehouse management system, a transportation management system, a supply chain planning system, a manufacturing execution system, a visibility system, and a supply chain exception management system.

19 . The method of claim 14 , wherein:

the event notification indicates that the asset has been discharged at a port of discharge; and

the particular action is scheduling a pickup of the asset at the port of discharge.

20 . The method of claim 14 , wherein:

determining that a particular action should be taken includes determining from the event notification that the asset will be discharged within a threshold amount of time; and

the particular action is initializing a process to select a transportation provider to pick up the asset.

21 . The method of claim 14 , wherein:

the event notification includes a location of the asset;

determining that a particular action should be taken includes determining from the location of the asset that the asset is expected to arrive at a destination location at a particular time; and

the particular action is scheduling workers to be at the destination location to unload the asset at the particular time.

22 . The method of claim 14 , wherein:

the event notification includes a location of the asset;

determining that a particular action should be taken includes determining form the location of the asset that the asset is expected to arrive at a destination location within a threshold amount of time; and

the particular action is scheduling a delivery window during which the asset will be delivered.

23 . The method of claim 14 , wherein:

the event notification includes a location of the asset;

determining that a particular action should be taken includes determining from the location of the asset that the asset will arrive at a destination location within a threshold lead time; and

the action notification indicates that a warehouse management system should update its virtual inventory to include the contents of the asset.

24 . The method of claim 14 , wherein:

the event notification includes a location of the asset;

determining that a particular action should be taken includes determining that the asset has arrived at a deconsolidation facility; and

the particular action is confirming that contents of the assets should be split, and then executing a split of the asset contents.

25 . The method of claim 14 , wherein:

the event notification indicates that an asset containing a particular item has arrived at a destination location;

determining that a particular action should be taken includes calculating an updated lead time for the particular item based on the event notification, and then determining that lead time data for the particular item should be updated; and

the action notification indicates that a supply chain management system should update a lead time for the particular item to be the updated lead time.

26 . A system comprising:

a processor; and

a computer readable medium coupled to the processor and including instructions, which, when executed by the processor, causes the processor to perform operations comprising:

receiving dependent process data for an asset, the dependent process data identifying one or more actions that should be taken after events of interest in a journey of the asset;

receiving an event notification from a tag coupled to the asset, the event notification describing a physical state of the asset;

determining, from the event notification that an event notification has occurred, and then determining, from the dependent process data that a particular action should be taken; and

generating an action notification, the action notification indicating that the particular action should be taken.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 25, 2012
From: SAVI NETWORKS LLC
To: DEAL MAGIC, INC.; SAVI TECHNOLOGY, INC.
Reel/Frame 028270/0077 →
CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNEE'S NAME FROM SAVI NETWORKS INC. TO SAVI NETWORKS LLC PREVIOUSLY RECORDED ON REEL 023714 FRAME 0803. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT OF INTEREST. Recorded Mar 23, 2010
From: COVA, NICHOLAS D.; SUBRAMANIYAM, NALINI
To: SAVI NETWORKS LLC
Reel/Frame 024124/0408 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 29, 2009
From: COVA, NICHOLAS D.; SUBRAMANIYAM, NALINI
To: SAVI NETWORKS INC.
Reel/Frame 023714/0803 →