IP Library Granted Patent US 8,344,532
Granted Patent B2
US 8,344,532 · App. 12/600,453 · Granted Jan 1, 2013

Rotor blade adjustment device for a wind turbine

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,344,532
App. No.
12/600,453
Granted
Jan 1, 2013
Kind
B2
Abstract

A wind turbine includes a rotor having adjustable rotor blades for driving a generator and an adjusting device for the rotor blades provided with an actuator that comprises at least an excitation winding. The adjusting device includes a torque-reducing device that automatically reduces drag torque of the actuator. The torque-reducing device includes a current divider that switches the current through the excitation winding in such a manner that the current flows completely through the excitation coil when the motor is in operation and the current only partly flows through the excitation coil when coasting (slip operation). As a result, when coasting, the magnetization of the excitation winding is reduced about the adjusting device, whereby the increase of the speed torque characteristic curve can be determined, thus improving the ratio of the adjusting device when coasting.

Claims (15)

1. A wind energy installation comprising a rotor having adjustable rotor blades for driving a generator and an adjustment device configured to adjust the adjustable rotor blades, the adjustment device comprising (i) an actuating motor having at least one field winding and (ii) a torque weakening device configured to automatically reduce a drag torque of the actuating motor,

wherein the torque weakening device has a current divider configured to switch a current through the at least one field winding such that all of the current flows through the at least one field winding during motor operation and only part of the current flows through the at least one field winding during slip operation.

2. The wind energy installation of claim 1 , further comprising a switching element configured to be switched on passively during slip operation.

3. The wind energy installation of claim 1 , wherein the current divider has a branch in parallel with the field winding with a resistance and a switching element configured to be switched on during slip operation.

4. The wind energy installation of claim 3 , wherein the current divider comprises a plurality of stages with a plurality of parallel resistances of different value, each of which is configured to be selectively connected to the switching element.

5. The wind energy installation of claim 2 , wherein the current divider comprises a field winding divided into at least two winding elements and wherein the switching element is configured to interrupt the current during slip operation using at least one but not all of the winding elements.

6. The wind energy installation of claim 5 , further comprising a plurality of winding elements configured to be selectively connected to the switching element.

7. The wind energy installation of claim 4 , further comprising a selection switch configured to select one of the plurality of resistances.

8. The wind energy installation of claim 6 , further comprising a selection switch configured to select one of the plurality of winding elements.

9. The wind energy installation of claim 7 or 8 , wherein the selection switch and the switching element are combined.

10. An adjustment device configured to adjust rotor blades of a wind energy installation, the adjustment device comprising:

an actuating motor having at least one field winding; and

a torque weakening device configured to automatically reduce a drag torque of the actuating motor and having a current divider configured to switch a current through the at least one field winding such that all of the current flows through the at least one field winding during motor operation and only part of the current flows through the at least one field winding during slip operation.

11. The adjustment device of claim 10 , comprising the current divider as claimed in one of claims 2 to 7 .

12. The wind energy installation of claim 1 , wherein the current divider comprises a field winding divided into at least two winding elements and wherein a switching element is configured to interrupt the current during slip operation using at least one but not all of the winding elements.

Assignments (3)
CHANGE OF NAME Recorded Jan 23, 2015
From: REPOWER SYSTEMS SE
To: SENVION SE
Reel/Frame 034806/0074 →
CHANGE OF NAME Recorded Jan 21, 2015
From: REPOWER SYSTEMS AG
To: REPOWER SYSTEMS SE
Reel/Frame 034786/0585 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 12, 2010
From: LETAS, HEINZ-HERMANN
To: REPOWER SYSTEMS AG
Reel/Frame 024831/0558 →