US 8,794,913 · App. 12/674,249 · Granted Aug 5, 2014

Steam turbine facility

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,794,913
App. No.
12/674,249
Granted
Aug 5, 2014
Kind
B2
Abstract

A steam turbine facility suppresses the possibility of vibration from occurring and prevents a drastic increase in facility cost, thereby realizing an increase in size of the facility, even if steam conditions of 650° C. or higher are adopted. In the steam turbine facility including a high-pressure turbine, an intermediate-pressure turbine, and a low-pressure turbine, the intermediate-pressure turbine is separated into a first intermediate-pressure turbine on a high-temperature and high-pressure side and a second intermediate-pressure turbine on a low-temperature and low-temperature side. At least any one of the rotors and casings of the steam-introduction-side turbines into which steam with a temperature of 650° C. or higher is introduced is formed from Ni-based alloy, and at least any one of the overall rotors and the overall casings of the turbines are constructed by joining together a plurality of rotor members or casing members by welding.

Claims (13)

1. A steam turbine facility comprising a high-pressure turbine, an intermediate-pressure turbine, and a low-pressure turbine,

wherein the intermediate-pressure turbine is separated into a first intermediate-pressure turbine on a high-temperature and high-pressure side and a second intermediate-pressure turbine on a low-temperature and low-pressure side,

wherein the high-pressure turbine, the second intermediate-pressure turbine, and the low-pressure turbine are integrated to form an integrated structure having a casing and a rotor in common,

wherein the integrated structure and the first intermediate-pressure turbine are connected together on a same axis or are arranged on different axes from each other,

wherein at least any one of rotors and casings of steam-introduction-side turbines into which steam with a temperature of 650° C. or higher is introduced is formed from Ni-based alloy, and

wherein at least any one of overall rotors and overall casings of turbines are constructed by joining together a plurality of rotor members or casing members by welding.

2. The steam turbine facility according to claim 1 ,

wherein the integrated structure and the first intermediate-pressure turbine are connected together on the same axis, and

wherein at least any one of a rotor and a casing of the first intermediate-pressure turbine on a steam introduction side into which steam with a temperature of 650° C. or higher is introduced or at least any one of rotors and casings of the first intermediate-pressure turbine and the high-pressure turbine on a steam introduction side into which steam with a temperature of 650° C. or higher is introduced is formed from Ni-based alloy.

3. The steam turbine facility according to claim 1 ,

wherein steam with a temperature of 650° C. or higher is introduced into the first intermediate-pressure turbine,

wherein the integrated structure and the first intermediate-pressure turbine are arranged on the different axes from each other, and

wherein the first intermediate-pressure turbine is arranged at a position closer to a boiler than the integrated structure, the boiler superheating steam introduced into the high-pressure turbine and the intermediate-pressure turbine.

Assignments (3)
CORRECTIVE ASSIGNMENT TO CORRECT THE REMOVING PATENT APPLICATION NUMBER 11921683 PREVIOUSLY RECORDED AT REEL: 054975 FRAME: 0438. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded May 26, 2023
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 063787/0867 →
CHANGE OF NAME Recorded Jan 13, 2021
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 054975/0438 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 10, 2020
From: MITSUBISHI HEAVY INDUSTRIES, LTD.
To: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
Reel/Frame 052891/0576 →