IP Library Granted Patent US 8,712,558
Granted Patent B2
US 8,712,558 · App. 13/139,291 · Granted Apr 29, 2014

Data center management unit with improved disaster prevention and recovery

Inventors: Wilbert Ingels (Ternat, BE); Niko Vinken (Anzegem, BE)
Assignee: Racktivity NV
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,712,558
App. No.
13/139,291
Granted
Apr 29, 2014
Kind
B2
Abstract

A data center management unit for managing and controlling power distribution to computers in a data center includes a power inlet, a plurality of power outlets for providing power to respective ones of the computers, and a processor. In addition thereto, the data center management unit includes a memory for storing logged parameters or events. The processor in the data center management unit takes measures for disaster prevention and/or disaster recovery based on the logged parameters or events. The measures for disaster prevention or disaster recovery comprise generating alert messages, de-activating one or more power outlets, activating one or more power outlets and/or re-activating a power outlet that has been de-activated earlier.

Claims (57)

1. A data center management unit for managing and controlling power distribution to computers in a data center, said data center management unit comprising a power inlet, a plurality of power outlets for providing power to respective ones of said computers, and a processor,

wherein said data center management unit further comprises memory for storing one or more logged parameters or events,

wherein said processor is able to take measures for disaster prevention to avoid power outages of computers or racks of computers in said data center and/or measures for disaster recovery to reboot computers or racks of computers in said data center after a power outage, said measures for disaster prevention and/or disaster recovery including:

generating alert messages;

de-activating one or more power outlets of said plurality of power outlets;

activating one or more power outlets of said plurality of power outlets; and

re-activating a power outlet that has been de-activated earlier,

wherein said processor is adapted to analyse changes in time of values of said logged parameters or events comprising a comparison of short term values, logged for a short term between zero and fifteen minutes, and long term values, logged for a long term being 1 day or more, of said logged parameters or events, and

wherein said processor is adapted to take one or more of said measures for disaster prevention and/or disaster recovery based on said comparison of short term values and long term values of logged parameters or events.

2. A data center management unit according to claim 1 ,

wherein said data center management unit comprises a mechanism configured for detecting micro-interruptions in power, measuring durations of said micro-interruptions, and measuring phase shifts in relation to such micro-interruptions.

3. A data center management unit according to claim 1 ,

wherein said data center management unit further comprises:

power metering circuitry for measuring overall power consumption at said power inlet; and wherein

said processor is adapted to apply a first priority scheme for de-activating power outlets of said plurality of power outlets in a first priority order whenever said overall power consumption exceeds an overall threshold.

4. A data center management unit according to claim 3 ,

wherein said first priority scheme is based on comparison of long term values, logged for a long term being 1 day or more, and short term values, logged for a short term between zero and fifteen minutes, of said logged parameter values or events; and

wherein in case of equal priority based on said comparison a power outlet which is more recently activated is prioritized for de-activation.

5. A data center management unit according to claim 1 ,

wherein said processor is adapted to apply a second priority scheme for re-activating power outlets out of said plurality of power outlets in a second priority order after a power outage.

6. A data center management unit according to claim 5 ,

wherein said second priority scheme is based on comparison of long term values, logged for a long term being 1 day or more, and short term values, logged for a short term between zero and fifteen minutes, of said logged parameters or events.

7. A data center management unit according to claim 1 ,

wherein said processor is adapted to de-activate a power outlet of said plurality of power outlets whenever a power measurement for said power outlet exceeds a predetermined per-outlet threshold.

8. A data center management unit according to claim 1 ,

said data center management unit further comprising memory for storing one or more parameter values during start-up of a computer out of said computers.

9. A data center management unit according to claim 8 ,

wherein said processor is adapted to determine sequence and timing of re-starting said computers after a power disaster based on said parameter values stored during start-up of said computer.

10. A data center management unit according to claim 8 ,

wherein said processor is adapted to instruct deactivation of a computer or alerting when parameter values measured during operation of said computer approach said parameter values stored during start-up of said computer within predetermined limits.

11. A data center management unit according to claim 1 ,

said data center management unit further comprising memory for storing the frequency spectrum of current and voltage measured at a power outlet of said plurality of power outlets.

12. A data center management unit according to claim 11 ,

wherein said processor is adapted to analyse harmonics in said frequency spectrum for threat and failure prediction.

13. A data center management unit according to claim 1 ,

wherein said logged parameters or events comprise one or more of the following:

temperature in said data center;

humidity in said data center;

airflow in said data center;

current measured at a power outlet of said plurality of power outlets;

total harmonic distortion or THD;

power factor of a plurality of said power outlets;

voltage measured at said power inlet;

energy consumed by a power outlet of said plurality of power outlets;

power consumed by a power outlet of said plurality of power outlets;

leakage current at a power outlet of said plurality of power outlets;

short circuit events.

14. A method for managing and controlling power distribution towards computers in a data center via a data center management unit comprising a power inlet, a plurality of power outlets and a processor,

wherein said method comprises:

storing one or more logged parameters or events; and

taking measures for disaster prevention to avoid power outages of computers or racks of computers in said data center and/or measures for disaster recovery to reboot computers or racks of computers in said data center after a power outage, said measures for disaster prevention and/or disaster recovery including:

generating alert messages;

de-activating one or more power outlets of said plurality of power outlets;

activating one or more power outlets of said plurality of power outlets; and

re-activating a power outlet that has been de-activated earlier,

wherein said method comprises analysing changes in time of values of said logged parameters or events comprising a comparison of short term values, logged for a short term between zero and fifteen minutes, and long term values, logged for a long term being 1 day or more, of said logged parameters or events,

and wherein said method comprises taking one or more of said measures for disaster prevention and/or disaster recovery based on said comparison of short term values and long term values of said logged parameters or events.

Assignments (3)
CHANGE OF NAME Recorded Mar 8, 2019
From: INCUBAID BUSINESS CENTER NV
To: GIG TECHNOLOGY NV
Reel/Frame 048549/0974 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 4, 2019
From: RACKTIVITY NV
To: INCUBAID BUSINESS CENTER NV
Reel/Frame 048492/0052 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 11, 2011
From: INGELS, WILBERT; VINKEN, NIKO
To: RACKTIVITY NV
Reel/Frame 026429/0484 →
Priority Claims (1)
EP 09075537 · Dec 3, 2009 · regional
Continuity (1)
Related Publication 20110320834A1 · Dec 29, 2011