Paint shop and method of operating a paint shop

Inventors: Hans-Georg Fritz (Ostfildern, DE); Jens Holzheimer (Tamm, DE); Dietmar Wieland (Wailblingen, DE); Frank Herre (Oberriexingen, DE); Jürgen Weschke (Weil der Stadt, DE)
Assignee: Dürr Systems GmbH
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,431,180
App. No.
13/163,316
Granted
Apr 30, 2013
Kind
B2
Abstract

In a paint plant which comprises at least one spray-painting device incorporating at least one application unit for painting workpieces and in particular motor vehicle bodies with a fluid paint, in order to enable the fluid paint overspray i.e. the paint particles which are not adhering to the workpieces that are to be painted and which are picked up and carried along in an air flow passing through the application area of the paint shop, to be re-separated from this air flow and also to enable the cleansed air flow to be returned to the application area in an air re-circulating system or else expelled into the environment of the plant, the paint shop comprises a device for separating fluid paint overspray from a stream of crude gas that contains overspray particles wherein this device comprises at least one filter element for separating the overspray from the stream of crude gas.

Claims (35)

1. A paint shop, comprising

at least one painting device incorporating at least one application unit for painting workpieces with a fluid paint and

a device for separating fluid paint overspray from a stream of crude gas which comprises at least one filter element for separating the overspray from the stream of crude gas,

wherein the device for separating fluid paint overspray from a stream of crude gas comprises at least one filter device which incorporates at least one filter element for separating the overspray from the stream of crude gas and

at least one auxiliary material reservoir for accommodating an auxiliary material,

wherein the filter device comprises at least one inlet opening through which the stream of crude gas enters the filter device,

wherein the inlet opening is configured and oriented in such a manner that the stream of crude gas enters the filter device such that it is directed into the auxiliary material reservoir in such a way that it is diverted in an interior space of the auxiliary material reservoir, and

wherein the inlet opening is in the form of an inlet channel extending in a direction of flow of the stream of crude gas and having a through-flow cross section which narrows in the direction of flow of the stream of crude gas up to a narrow section.

2. A paint shop in accordance with claim 1 , wherein the auxiliary material reservoir is provided with a balance.

3. A paint shop in accordance with claim 1 , wherein the at least one filter device is in the form of a unit comprising the following:

a filter element accommodating chamber for accommodating at least one filter element for separating the overspray from the stream of crude gas; and

at least one partition wall for separating the filter element accommodating chamber from a flow chamber of the device for separating fluid paint overspray through which the crude gas stream flows before its entry into the unit.

4. A method for the operation of a paint shop, comprising the following processing steps:

applying fluid paint to workpieces that are to be painted by means of at least one application unit of at least one painting device;

introducing a stream of crude gas containing overspray particles into a filter device; and

separating the overspray from the stream of crude gas by means of at least one filter element arranged in the filter device;

wherein the stream of crude gas is introduced into the filter device through at least one inlet opening in such a way that the stream of crude gas enters the filter device such as to be directed into an auxiliary material reservoir for accommodating an auxiliary material, wherein the stream of crude gas is diverted in an interior space of the auxiliary material reservoir, and

wherein the inlet opening is in the form of an inlet channel extending in a direction of flow of the stream of crude gas and having a through-flow cross section which narrows in the direction of flow of the stream of crude gas up to a narrow section.

5. A method in accordance with claim 4 , wherein the auxiliary material is supplied to the stream of crude gas loaded with fluid paint overspray,

wherein a mixture of auxiliary material and fluid paint overspray is arranged in the auxiliary material reservoir and the weight or the mass of the mixture in the auxiliary material reservoir is determined by means of a balance.

6. A method in accordance with claim 4 , wherein an auxiliary material reservoir is used which is provided with an agitator and a balance.

7. A method according to claim 4 , wherein the workpieces that are to be painted are vehicle bodies.

8. A method for the operation of a paint shop, comprising the following processing steps:

applying fluid paint to workpieces that are to be painted, by means of at least one application unit of at least one painting device;

introducing a stream of crude gas containing overspray particles into a filter device; and

separating the overspray from the stream of crude gas by means of at least one filter element arranged in the filter device;

wherein an auxiliary material is supplied to the stream of crude gas loaded with fluid paint overspray,

wherein a mixture of auxiliary material and fluid paint overspray is arranged in an auxiliary material reservoir and the weight or the mass of the mixture in the auxiliary material reservoir is determined by means of a balance,

wherein material is whirled up from the auxiliary material reservoir and an effectiveness of the material contained in the auxiliary material reservoir is determined by a comparison of the weight or the mass of the material contained in the auxiliary material reservoir prior to a whirling-up phase and after the whirling-up phase, and

wherein the stream of crude gas is introduced into the filter device through at least one inlet opening in such a way that the stream of crude gas enters the filter device such as to be directed into the auxiliary material reservoir for accommodating the auxiliary material,

wherein the stream of crude gas is diverted in an interior space of the auxiliary material reservoir.

9. A method in accordance with claim 8 , wherein material is extracted from the auxiliary material reservoir when a difference of the weight or mass of the material contained in the auxiliary material reservoir prior to the whirling-up phase and after the whirling-up phase falls below a given minimum value.

10. A method in accordance with claim 8 , wherein the weight or the mass of material in an auxiliary material reservoir is measured by means of a balance prior to and after a whirling-up cycle during which a plurality of whirling-up phases are carried out, and the amount of material that has been withdrawn from the auxiliary material reservoir is determined by formulating the difference.

11. A method in accordance with claim 10 , wherein the effectiveness of the material contained in the auxiliary material reservoir is determined by a comparison of the weight or the mass of the material contained in the auxiliary material reservoir prior to the whirling-up cycle and after the whirling-up cycle.

12. A method according to claim 8 , wherein the workpieces that are to be painted are vehicle bodies.

Assignments (2)
CHANGE OF NAME Recorded Apr 5, 2017
From: DÜRR SYSTEMS GMBH
To: DÜRR SYSTEMS AG
Reel/Frame 042166/0752 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 27, 2011
From: FRITZ, HANS-GEORG; HOLZHEIMER, JENS; WIELAND, DIETMAR; HERRE, FRANK; WESCHKE, JURGEN
To: DURR SYSTEMS GMBH
Reel/Frame 026659/0264 →
Priority Claims (1)
DE 10 2008 064 043 · Dec 19, 2008 · national
Continuity (2)
Continuation PCTEP2009001305 · Feb 24, 2009
Related Publication 20110274827A1 · Nov 10, 2011