Method for mounting wind turbine blades to a wind turbine hub

Inventors: Henrik Lynderup Hansen (Hoejerslev, DK); Jesper Moeller (Esbjerg, DK)
Assignee: Siemens Aktiengesellschaft
B66C23/185B66C13/08F03D11/04B66C1/42B66C23/36Y02E10/721Y02E10/728Y02E10/726F05B2250/30F03D1/001B66C1/108F05B2230/61
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,966,753
App. No.
13/441,178
Granted
Mar 3, 2015
Kind
B2
Abstract

A method for mounting a wind turbine blade to a wind turbine hub by use of a crane boom is provided. An orientation of the blade is kept substantially horizontal when the blade is lifted off the ground and mounted to the rotor hub. Control wires, which connect the blade via the crane boom to a winch arrangement, are used for keeping the blade orientation substantially horizontal in addition to at least one bearing wire for bearing the blade weight.

Claims (20)

1. A method for mounting a wind turbine blade to a wind turbine hub, comprising:

providing a crane boom and a winch arrangement located at the bottom of the crane boom;

arranging a wind turbine blade in a lifting device, which is attached to a bearing wire and to a plurality of control wires; the control wires further attached to the winch arrangement;

keeping an orientation of the wind turbine blade substantially horizontal when the wind turbine blade is lifted off a ground and mounted to the wind turbine hub, the keeping the orientation includes adjusting the plurality of control wires via the winch arrangement;

lifting the wind turbine blade, the bearing wire bears the weight of the wing turbine blade in the lifting device during lifting; and

fixing the wind turbine blade in the substantially horizontal position to the wind turbine hub,

wherein each control wire is threaded through a pulley that is vertically located between the winch arrangement and a vertical location of the lifting device during the fixing step, and

wherein each control wire exerts a tensioning force at an angle to a lifting force exerted by the bearing wire.

2. The method as claimed in claim 1 , further comprising:

lifting the wind turbine hub to a nacelle of the wind turbine with the lifting device, and mounting the hub on the nacelle.

3. The method as claimed in claim 1 , further comprising:

lifting the wind turbine hub and the nacelle together with the lifting device and mounting the nacelle with the hub on a wind turbine tower.

4. The method as claimed in claim 1 , wherein each of the plurality of control wires are controlled independently of each other.

5. The method as claimed in claim 4 , wherein the control wires are kept pre-tensioned when the blade is lifted.

6. The method as claimed in claim 1 , wherein a first of the plurality of control wires is attached to the lifting device at a first longitudinal end and a second of plurality of control wires is attached to the lifting device at a second longitudinal end.

7. The method as claimed in claim 1 , wherein the pulley is mounted onto a sliding carriage which mores along the crane boom.

8. The method as claimed in claim 1 , wherein the bearing wire is further connected to a second winch arrangement and the lifting includes operating the second winch arrangement.

9. The method as claimed in claim 1 , wherein the lifting bearing wire is attached at a top of the lifting device.

10. The method as claimed in claim 1 , wherein forces acting on the lifting device are in different directions for the bearing wire than for the plurality of control wires.

11. The method as claimed in claim 1 , wherein the plurality of control wires are substantially not weight bearing.

Assignments (3)
CHANGE OF NAME Recorded Jul 28, 2021
From: SIEMENS WIND POWER A/S
To: SIEMENS GAMESA RENEWABLE ENERGY A/S
Reel/Frame 057434/0737 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 9, 2017
From: SIEMENS AKTIENGESELLSCHAFT
To: SIEMENS WIND POWER A/S
Reel/Frame 042294/0897 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 6, 2012
From: HANSEN, HENRIK LYNDERUP; MOELLER, JESPER
To: SIEMENS AKTIENGESELLSCHAFT
Reel/Frame 028004/0896 →
Priority Claims (3)
EP 06024336 · Nov 23, 2006 · regional
EP 06024337 · Nov 23, 2006 · regional
EP 07013724 · Jul 12, 2007 · regional
Continuity (2)
Division 11986035 · Nov 19, 2007
Related Publication 20120192402A1 · Aug 2, 2012