Method of reeling and unreeling an internally clad metal pipeline

Inventors: John Arthur Mair (Aberdeen, GB); Thomas Schüller (Wittingen, DE); Gernold Holler (Wittingen-Knesebeck, DE); Friedrich Henneicke (Wittingen, DE); Joachim Banse (Wittingen, DE)
Assignee: Subsea 7 Limited
F16L1/161F16L1/203
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,894,327
App. No.
13/504,127
Granted
Nov 25, 2014
Kind
B2
Abstract

A method is disclosed for reeling or unreeling a pipeline having an inner corrosion-resistant metallic liner that is tightly fitted within the pipeline. To minimize or avoid wrinkling of the liner during the reeling or unreeling, a length of the pipeline is internally pressurized in a two-stage pressurizing process, and then the length of pipeline is reeled or unreeled, as the case may be. In the first stage of the pressurizing process, the length of the pipeline is filled with fluid at an elevated pressure, and in the second stage the fluid pressure is raised to a higher pressure, which may be 25 bars or more, absolute.

Claims (45)

1. A method for reeling a pipeline while extending the pipeline with an additional pipeline section, the pipeline having an inner corrosion-resistant metallic liner that is tightly fitted within the pipeline, wherein, to minimize or avoid wrinkling of the liner during the reeling, the method comprises the following steps:

providing a fluid connection between the pipeline and pumping/pressurizing equipment via a manifold mounted on a flange of a pipe laying reel;

internally pressurizing a length of the pipeline in a two-stage pressurizing process comprising:

a first stage comprising filling the length of the pipeline with fluid, the fluid being delivered at a first pressure in the range of 5 to 25 bar absolute; and

comprising further pressurizing the fluid to raise the fluid pressure from the first pressure to a second pressure of greater than 25 bar absolute;

connecting a leading end of the pipeline to a reel via the manifold;

reeling the length of the pipeline into the reel while pressurized to the second pressure;

depressurizing the length of the pipeline; and

joining a further pipeline section to a trailing end of the length of the pipeline.

2. The method according to claim 1 , wherein a first pump is used for filing the length of the pipeline with fluid and thereby pressurizing it to the first pressure, and a second pump is used for raising the fluid pressure to the second pressure, wherein the second pump has a smaller volumetric delivery but a higher pressure than the first pump.

3. The method according to claim 1 , wherein a pump of high volumetric delivery is used for filling the length of the pipeline with fluid and thereby pressurizing the pipeline to the first pressure and a pressure accumulator is used for raising the fluid pressure to the second pressure.

4. The method according to claim 1 , wherein the second pressure is at least 30 bar absolute.

5. The method according to claim 1 , wherein, after joining a further pipeline section to a trailing end of the length of the pipeline, there is a repetition of the two-stage pressurizing process and the reeling step for a length of the further pipeline section.

6. The method according to claim 1 , wherein the first stage of the two-stage pressurizing process comprises:

pumping a movable plug along the length of the pipeline towards the trailing end of the pipeline and

locking the plug near the trailing end of the length of pipeline, so that the length is filled with fluid; and

raising the pressure of the fluid from the first pressure to the second pressure.

7. The method according to claim 1 , wherein the second pressure is more than 25 bar absolute and a multi-stage pump is used to internally pressurize the length of pipeline to the second pressure.

8. The method according to claim 7 , wherein the pressurizing step comprises pumping a movable plug along the length of the pipeline towards the trailing end of the pipeline and locking the plug near the trailing end of the length of pipeline, so that the length is filled with fluid and the fluid pressure increases to more than 25 bar absolute.

9. The method according to claim 1 , wherein the fluid is water.

10. A method for reeling or unreeling a pipeline having an inner corrosion-resistant metallic liner that is tightly fitted within the pipeline, wherein, to minimize or avoid wrinkling of the liner during the reeling or unreeling, the method comprises the following steps:

providing a fluid connection between the pipeline and pumping/pressurizing equipment via a manifold mounted on a flange of a pipe laying reel;

internally pressurizing a length of the pipeline in a two-stage pressurizing process, in the first stage of which the length of the pipeline is filled with fluid at a first elevated pressure and in the second stage of which the fluid pressure of the fluid filling the length of the pipeline is raised from the first elevated pressure to a second pressure that is greater than the first pressure; and

unreeling the length of the pipeline while pressurized to the second pressure or connecting a leading end of the pipeline to a reel via the manifold and reeling the length of the pipeline while pressurized to the second pressure.

11. The method according to claim 10 , wherein a first pump is used for filling the length of the pipeline with fluid at an elevated pressure and a second pump, having a smaller volumetric delivery than the first pump but a relatively higher delivery pressure, is used for raising the fluid pressure to the higher pressure.

12. The method according to claim 10 , wherein a pump of high volumetric delivery is used for filling the length of the pipeline with fluid at an elevated pressure and a pressure accumulator is used for raising the fluid pressure to the higher pressure.

13. The method according to claim 10 , wherein the elevated pressure has a value in the range 5 to 25 bar absolute and the higher pressure is greater than 25 bar absolute.

14. The method according to claim 13 , wherein the higher pressure is at least 30 bar absolute.

15. The method according to claim 10 for reeling the pipeline, wherein, after the length of the pipeline has been reeled onto the reel, a further pipeline section is joined to a trailing end of the pipeline, followed by a repetition of the two-stage pressurizing process and the reeling or unreeling step for a length of the further pipeline section.

16. The method according to claim 10 , wherein the first stage of the two-stage pressurizing process comprises:

pumping a movable plug along the length of the pipeline towards the trailing end of the pipeline and locking the plug near the trailing end of the length of the pipeline, so that the length is filled with fluid, and

raising the pressure of the fluid from the elevated pressure to the higher pressure.

17. The method according to claim 10 , wherein the higher pressure is more than 25 bar absolute and a multi-stage pump is used to internally pressurize the length of pipeline to the higher pressure.

18. The method according to claim 17 for reeling the pipeline, wherein, after the length of the pipeline has been reeled onto the reel, a further pipeline section is joined to a trailing end of the pipeline, followed by a repetition of the pressurizing step and the reeling or unreeling step for the length of the further pipeline section.

19. The method according to claim 17 , wherein the pressurizing step comprises pumping a movable plug along the length of the pipeline towards the trailing end of the pipeline and locking the plug near the trailing end of the length of pipeline, so that the length is filled with fluid and the fluid pressure increases to more than 25 bar absolute.

20. A method of pipe laying in which a pipeline is unreeled from a pipe laying reel on a pipe lay barge, the pipeline having an inner corrosion-resistant metallic liner closely fitted within an outer pipe that is less corrosion-resistant, and the pipeline being filled with an internal fluid pressurized to a first absolute pressure of 5 to 25 bar, the method comprising the operations of:

providing a fluid connection between the pipeline and pumping/pressurizing equipment via a manifold mounted on a flange of the pipe laying reel;

pressurizing the pipeline by raising the pressure of the internal fluid filling the pipeline from the first absolute pressure to a second absolute pressure of at least 25 bar;

unwinding the pipeline from the reel while the absolute pressure of at least 25 bar is maintained in the pipeline;

laying the pipeline on the seabed; and

depressurizing the pipeline.

21. The method according to claim 20 in which the pressurizing operation is performed by firstly operating a pumping system to fill the length of pipeline with fluid at a first absolute pressure below 25 bar and thereafter raising the pressure to a second absolute pressure of at least 30 bar.

22. The method according to claim 20 in which the absolute pressure in the pipeline is maintained at a level of at least 30 bar by connecting an accumulator to the pipeline during the unwinding operation.

23. The method according to claim 22 in which the accumulator is mounted on the pipe laying reel.

24. The method according to claim 20 , wherein the fluid is water.

Assignments (3)
CHANGE OF ADDRESS Recorded Apr 19, 2017
From: SUBSEA 7 LIMITED
To: SUBSEA 7 LIMITED
Reel/Frame 042285/0541 →
CHANGE OF ADDRESS Recorded Oct 16, 2014
From: SUBSEA 7 LIMITED
To: SUBSEA 7 LIMITED
Reel/Frame 034014/0607 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 10, 2012
From: MAIR, JOHN ARTHUR; SCHULLER, THOMAS; HOLLER, GERNOLD; HENNEICKE, FRIEDRICH; BANSE, JOACHIM
To: SUBSEA 7 LIMITED
Reel/Frame 028561/0714 →
Priority Claims (2)
GB 0918768.3 · Oct 26, 2009 · national
GB 1005795.8 · Apr 7, 2010 · national
Continuity (1)
Related Publication 20120269581A1 · Oct 25, 2012