IP Library Granted Patent US 10,253,973
Granted Patent B2
US 10,253,973 · App. 13/522,733 · Granted Apr 9, 2019

System for combined flue gas heat recovery and dust precipitation improvement as retrofit solution for existing coal-fired power stations

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,253,973
App. No.
13/522,733
Granted
Apr 9, 2019
Kind
B2
Abstract

A power plant is suggested with an additional heat transfer between the flue gas that flows through a flue gas line ( 5 ) and the feed-water in a feed-water line ( 19 ). The claimed arrangement of the first heat exchanger ( 13 ) upstream and adjacent to a precipitator ( 7 ) leads to a reduced space demand and optimizes dust precipitation as well as the pressure drop of the flue gas.

Claims (13)

1. A power plant having a boiler for combusting carbonaceous fuel and generating flue gas having dust disposed therein, said power plant comprising:

a flue gas line to convey flue gas;

a diffuser to receive and diffuse flue gas from the flue gas line;

a first heat exchanger in fluid communication with the diffuser to receive and cool flue gas from the diffuser;

a dust precipitator abuttingly connected to the first heat exchanger to receive flue gas from the first heat exchanger and remove dust from the flue gas received from the heat exchanger;

an induced draft fan downstream of the dust precipitator for raising the pressure of flue gas exiting the dust precipitator and transporting the flue gas exiting the dust precipitator towards an outlet stack; and

a second heat exchanger in parallel to a first feedwater heater, wherein heat extracted from flue gas passing through the first heat exchanger is transferred to a thermal energy carrier that flows through conduits to the second heat exchanger, and wherein the second heat exchanger is configured to heat feedwater bypassing the first feedwater heater with heat from the thermal energy carrier,

wherein the diffuser and the first heat exchanger are disposed upstream of the dust precipitator system, the diffuser is configured to reduce a velocity of flue gas flowing to both the first heat exchanger and the dust precipitator, and

wherein the first heat exchanger and the dust precipitator define respective cross-sections where the first heat exchanger and the dust precipitator directly abuttingly connect, and the respective cross sections are the same.

2. The power plant according to claim 1 , wherein the dust precipitator is an electrostatic precipitator.

3. The power plant according to claim 1 , wherein flue gas enters in a horizontal direction into the first heat exchanger and the dust precipitator.

4. The power plant according to claim 1 , further comprising: an air heater to receive flue gas therethrough, the air heater located downstream of the boiler and upstream of the first heat exchanger.

5. The power plant according to claim 1 , wherein a velocity of flue gas exiting the first heat exchanger is approximately the same as a velocity of flue gas entering the dust precipitator.

Assignments (2)
CHANGE OF NAME Recorded Aug 17, 2016
From: ALSTOM TECHNOLOGY LTD
To: GENERAL ELECTRIC TECHNOLOGY GMBH
Reel/Frame 039714/0578 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 10, 2012
From: SCHULE, VOLKER; ZIMMER, DANIEL
To: ALSTOM TECHNOLOGY LTD
Reel/Frame 029103/0424 →