IP Library Granted Patent US 8,633,607
Granted Patent B2
US 8,633,607 · App. 13/533,161 · Granted Jan 21, 2014

Method, park controller and program element for controlling a wind farm

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,633,607
App. No.
13/533,161
Granted
Jan 21, 2014
Kind
B2
Abstract

The disclosure relates to a method for controlling a wind farm, the wind farm includes at least two wind turbines, the method includes determining the required power, determining fatigue load versus power curves for each wind turbine, and based on the determined fatigue load versus power curves attributing different power settings to the wind turbines such that sum of the power settings of all wind turbines is equal to the required power. Furthermore, the invention concerns a park controller for controlling a wind farm and a program element for controlling a wind farm.

Claims (31)

1. A method for controlling a wind farm, the wind farm comprising a plurality of wind turbines, the method comprising:

determining the required power P R ;

determining fatigue load versus power curves for each of the plurality of wind turbines, and

based on the determined fatigue load versus power curves attributing different power settings P S,i to each of the wind turbines such that sum of the power settings P S,i of plurality of wind turbines is equal to the required power P R .

2. The method as set forth in claim 1 , further comprising for each of the plurality of wind turbines:

defining a mid power range P M,i comprising only one relative fatigue load maximum and wherein P A,i <P M,i <P B,I ;

defining a low power range P L,i ≦P A,i free of a relative fatigue load maximum;

defining a high power range P H,i ≧P B,i free of a relative fatigue load maximum; and

attributing the power settings such that P S,i ≠P M,i .

3. The method as set forth in claim 2 ,

wherein P A,i and/or P B,i correspond to relative or absolute fatigue load minima.

4. The method as set forth in claim 2 , further comprising for each of the plurality of wind turbines:

determining the current power settings P C,i , and

attributing new power settings P S,i such that |(P S,i −P C,i )/2|≦P A or |(P S,i −P C,i )/2|≧P B .

5. The method as set forth in claim 2 ,

wherein the low power ranges P L,i and/or mid power ranges P M,i and/or high power ranges P H,i are equal or different for all wind turbines.

6. The method as set forth in claim 2 ,

wherein at least some of the low power ranges P L,i for the plurality of wind turbines are different.

7. The method as set forth in claim 2 ,

wherein at least some of the high power ranges P H,i for the plurality of wind turbines are different.

8. The method as set forth in claim 2 ,

wherein determining fatigue load versus power curves comprises measuring wind turbine parameters.

9. The method as set forth in claim 2 ,

wherein determining fatigue load versus power curves comprises determining power versus pitch angle curves and fatigue load versus pitch angle curves.

10. The method as set forth in claim 2 ,

wherein attributing power settings to the wind turbine comprises attributing pitch angles to the wind turbines.

11. A park controller for controlling a wind farm, the wind farm comprising a plurality of wind turbines, the park controller comprising

a required power determination unit for determining the required power to be provided by the wind farm,

a fatigue load determination unit for determining the fatigue load versus power dependency of each wind turbine, and

an attribution unit for attributing different power settings to the wind turbines such that the sum of the power settings of all wind turbines is equal to the required power.

12. A program element for controlling a wind farm, the program element, when being executed by a data processer, is adapted for carrying out the method as set forth in claim 1 .

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 3, 2019
From: SIEMENS AKTIENGESELLSCHAFT
To: SIEMENS GAMESA RENEWABLE ENERGY A/S
Reel/Frame 048003/0631 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 15, 2012
From: SIEMENS WIND POWER A/S
To: SIEMENS AKTIENGESELLSCHAFT
Reel/Frame 029130/0033 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 11, 2012
From: EGEDAL, PER; STOETTRUP, MICHAEL
To: SIEMENS WIND POWER A/S
Reel/Frame 029113/0363 →