Solid oxide fuel cell stack heat treatment methods and apparatus

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,142,845
App. No.
13/768,218
Granted
Sep 22, 2015
Kind
B2
Abstract

Systems and methods are provided for fuel cell stack heat treatment. An eductor may be used to recycle air into the air inlet stream or to recycle fuel into the fuel inlet stream. An eductor may also be used to exhaust air away from the furnace. The stack heat treatment may include stack sintering or conditioning. The conditioning may be conducted without using externally supplied hydrogen.

Claims (50)

1. A method for heating a fuel cell stack, comprising:

placing the fuel cell stack in a furnace, wherein the furnace comprises:

a heat source;

a base configured to support the fuel cell stack; and

an eductor;

operating the furnace to at least one of sinter or condition the fuel cell stack; and

providing cooler, higher pressure air from an air input into a motive inlet of the educator to draw lower pressure, warmer air from the fuel cell stack through a suction inlet of the educator.

2. The method of claim 1 , wherein the furnace further comprises:

a fuel input.

3. The method of claim 1 , further comprising:

mixing the cooler and warmer air in a converging portion of the eductor.

4. The method of claim 1 , further comprising:

evacuating air from a discharge outlet of the eductor away from the furnace.

5. The method of claim 1 , further comprising:

recycling at least a portion of the air from the fuel cell stack into an air inlet stream of the furnace through a discharge outlet of the eductor.

6. The method of claim 5 , wherein the eductor is located in a hot zone of the furnace.

7. The method of claim 5 , wherein the eductor is located outside a hot zone of the furnace.

8. The method of claim 7 , further comprising pre-heating the air inlet stream.

9. The method of claim 5 , further comprising pre-heating the air inlet stream before it enters the eductor.

10. The method of claim 1 , wherein the eductor is a Venturi eductor.

11. The method of claim 1 , wherein the eductor is one of a plurality of eductors, and wherein the fuel cell stack in the furnace comprises one of a plurality of fuel cell stacks placed into the furnace.

12. The method of claim 1 , wherein placing the fuel cell stack in a furnace comprises placing the fuel cell stack in the furnace at an angle of 0-90 degrees.

13. The method of claim 1 , further comprising monitoring a power consumption of the furnace.

14. The method of claim 1 , further comprising monitoring a temperature of air within the furnace.

15. The method of claim 1 , wherein the conditioning comprises electrochemically reducing the anode electrodes followed by characterizing the stack without externally supplied hydrogen.

16. The method of claim 1 , further comprising conditioning the fuel cell stack without externally supplied hydrogen.

17. The method of claim 1 , further comprising:

operating a circulation fan to mix air within the furnace.

18. The method of claim 1 , wherein operation the furnace to at least one of sinter or condition the fuel cell stack comprises operating the furnace to sinter the fuel cell stack.

19. The method of claim 1 , wherein operating the furnace to at least one of sinter or condition the fuel cell stack comprises operating the furnace to condition the fuel cell stack.

20. The method of claim 1 , wherein operation the furnace to at least one of sinter or condition the fuel cell stack comprises operating the furnace to sinter the fuel cell stack.

21. A method for heating a fuel cell stack, comprising:

placing the fuel cell stack in a furnace, wherein the furnace comprises:

a heat source;

a base configured to support the fuel cell stack; and

an eductor;

operating the furnace to at least one of sinter or condition the fuel cell stack; and

providing a lower temperature, higher pressure fuel stream into a motive inlet of the eductor to draw higher temperature, lower pressure stack fuel exhaust through a suction inlet of the eductor to recycle a mixed fuel and fuel exhaust into a fuel inlet stream of the fuel cell stack,

wherein the eductor is located in a hot zone of the furnace or outside the hot zone of the furnace.

22. The method of claim 21 ,

wherein the eductor is located outside the hot zone of the furnace.

23. The method of claim 21 , wherein the eductor is located in the hot zone of the furnace.

24. A method for heating a fuel cell stack, comprising:

placing the fuel cell stack in a furnace, wherein the furnace comprises:

a heat source;

a base configured to support the fuel cell stack; and

an eductor;

operating the furnace to at least one of sinter or condition the fuel cell stack;

providing a lower temperature, higher pressure fuel stream into a motive inlet of the eductor to draw higher temperature, lower pressure stack fuel exhaust through a suction inlet of the eductor to recycle a mixed fuel and fuel exhaust into a fuel inlet stream of the fuel cell stack; and

pre-heating the fuel inlet stream before it enters the fuel cell stack.

Assignments (3)
RELEASE OF SECURITY INTEREST Recorded Nov 29, 2018
From: U.S. BANK NATIONAL ASSOCIATION, AS COLLATERAL AGENT
To: BLOOM ENERGY CORPORATION
Reel/Frame 047686/0121 →
SECURITY INTEREST Recorded Dec 15, 2015
From: BLOOM ENERGY CORPORATION
To: U.S. BANK NATIONAL ASSOCIATION, AS COLLATERAL AGENT
Reel/Frame 037301/0093 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 31, 2014
From: GOTTMANN, MATTHIAS; COUSE, STEPHEN; MCELROY, JAMES; HALLUM, RYAN; HILTON, JAKOB; RISIC, KURT; RAMANAN, NATARAJAN; GASDA, MICHAEL
To: BLOOM ENERGY CORPORATION
Reel/Frame 034083/0137 →