IP Library Granted Patent US 8,920,540
Granted Patent B2
US 8,920,540 · App. 13/852,517 · Granted Dec 30, 2014

Compact air quality control system compartment for aluminium production plant

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,920,540
App. No.
13/852,517
Granted
Dec 30, 2014
Kind
B2
Abstract

A first contact reactor, mechanical separator device, one or more second contact reactors, silo, filter, one or more fans each equipped with one or more vibration dampers, an optional wet scrubber and stack are each integrated into a single compact air quality control system (AQCS) compartment. Additionally, a process gas cooling system may be integrated into the compact AQCS compartment. Benefits of the subject compact AQCS compartment includes footprint reduction, operating cost reduction from reduced pressure drop due to reduced ductwork, capital cost reduction from reduced ductwork, noise reduction, weather protection and increased adaptability to meet specific system requirements.

Claims (31)

1. A compact air quality control system compartment comprising:

each of the following vertically arranged one above another and fluidly connected within a single housing:

a first contact reactor fluidly connected with an electrolytic cell;

a separator device;

one or more second contact reactors with a fluidly connected silo;

a filter system;

a fan equipped with vibration dampers for vibration isolation; and

a stack in fluid communication with the atmosphere.

2. The compartment of claim 1 wherein said first contact reactor is arranged for supply of adsorbent from said second contact reactors.

3. The compartment of claim 1 wherein said separator device supplies separated adsorbent to said electrolytic cell.

4. The compartment of claim 1 wherein said second contact reactors are arranged for supply of adsorbent from said associated silo.

5. The compartment of claim 1 wherein said vibration dampers reduce fan vibrations by approximately 90 percent.

6. The compartment of claim 1 further comprising a wet scrubber arranged vertically between said fan and said stack.

7. The compartment of claim 1 wherein said vibration dampers comprise a plurality of seal springs.

8. The compartment of claim 1 wherein said vibration dampers comprise rubber components.

9. The compartment of claim 1 wherein said vibration dampers isolate vibrations from said fan for vibration reduction.

10. A method of treating process effluent gases from an electrolytic cell in a compact AQCS compartment, said method comprising:

passing process effluent gases from said electrolytic cell through said compartment comprising each of the following vertically arranged one above another and fluidly connected within a single housing: a first contact reactor with an adsorbent,

a separator device for removal of adsorbent,

one or more second contact reactors with a fluidly connected silo with an adsorbent,

a filter for dust and adsorbent collection to produce cleaned gas,

a fan equipped with vibration dampers for vibration isolation, and

a stack fluidly connected with the atmosphere for cleaned gas release.

11. The method of claim 10 wherein said absorbent is alumina.

12. The method of claim 10 further comprising a fluidly connected wet scrubber arranged between said fan and said stack for passage and further treatment of cleaned gas.

13. The method of claim 10 wherein said adsorbent removed by said separator device is recycled to said electrolytic cell.

14. The method of claim 10 wherein said dust and adsorbent collected by said filter are used in said first contact reactor.

15. The method of claim 10 wherein said vibration dampers reduce fan vibration by approximately 90 percent.

16. The method of claim 10 wherein said vibration dampers comprise a plurality of seal springs or rubber components.

17. The method of claim 10 wherein the first contact reactor is for removal of at least a portion of hydrogen fluoride and sulphur dioxide in said effluent gases with the adsorbent.

18. The method of claim 10 wherein the one or more second contact reactors are for removal of at least a portion of hydrogen fluoride and sulphur dioxide in said effluent gases with the adsorbent.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 18, 2021
From: GENERAL ELECTRIC TECHNOLOGY GMBH
To: REEL ALESA AG
Reel/Frame 057217/0145 →
CHANGE OF NAME Recorded Aug 17, 2016
From: ALSTOM TECHNOLOGY LTD
To: GENERAL ELECTRIC TECHNOLOGY GMBH
Reel/Frame 039714/0578 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 28, 2013
From: SORHUUS, ANDERS KENNETH; BJARNO, ODD EDGAR; AMUNDSEN, PER-ERIK
To: ALSTOM TECHNOLOGY LTD
Reel/Frame 030107/0936 →