Steam power plant with steam turbine extraction control

Inventors: Julia Kirchner (Gernsheim, DE); Volker Schüle (Leimen, DE); Stefan Hellweg (Oetigheim, DE)
Assignee: ALSTOM Technology Ltd
F01K7/34F01K7/22F01K7/226F01K7/24F01K7/345
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,151,185
App. No.
14/046,132
Granted
Oct 6, 2015
Kind
B2
Abstract

Provided is a power plant and a method of operating thereof. The power plant includes a boiler for heating process fluids; and a multistage first steam turbine with an outlet line that passes through the boiler. The outlet line includes an extraction line that is configured and arranged to extract steam from an intermediate stage of the first steam turbine and heat at least one of the process fluids.

Claims (24)

1. A power plant comprising:

a boiler for heating process fluids;

a multistage first steam turbine with an outlet line that passes through the boiler, the outlet line comprising an extraction line configured and arranged to extract steam from an intermediate stage of the first steam turbine and heat at least one of the process fluids; and

a control system comprising:

an extraction control valve, in the extraction line, for modulating flowrate through the extraction line, wherein the extraction line is connected to the outlet line upstream of the boiler;

a temperature measurement device configured and arranged to measure a temperature (T 3 ) of process fluid in the outlet line upstream of the boiler between the boiler and the first steam turbine; and

a controller configured and arranged to modulate the extraction control valve based on the temperature measurement.

2. The power plant of claim 1 comprising:

a boiler feed water line that passes through the boiler;

a first preheater in the boiler feed water line upstream of the boiler; and

a steam line, fluidly connecting the outlet line upstream of the boiler to the first preheater so as to enable pre-heating of boiler feed water passing through the boiler feed water line.

3. The power plant of claim 2 wherein the extraction line is connected to the outlet line upstream of the steam line.

4. The power plant of claim 2 wherein the extraction line is connected to the outlet line between the boiler and the steam line.

5. The power plant of claim 2 wherein the extraction line is connected to the steam line at a connection point.

6. The power plant of claim 5 compromising:

a valve, in the steam line, either side of the connection point to fluidly and selectively connect the extraction line to either the outlet line or the first preheater.

7. The power plant of claim 2 comprising:

a second preheater, in the boiler feed water line, downstream of the first preheater, wherein the extraction line is fluidly connected to the second preheater to enable pre-heating of boiler feed water pass thorough the boiler feed water line with extracted steam.

8. A method for operating a power plant that includes a boiler for heating process fluids and a multistage first steam turbine having an outlet line that passes through the boiler, the method comprising:

monitoring a temperature (T 1 , T 3 , T 4 ) of the outlet line upstream of the boiler between the boiler and the first steam turbine;

extracting steam from an intermediate stage of the first steam turbine via an extraction control valve connected to the outlet line upstream of the boiler; and

using the extracted steam to heat at least one of the process fluids in order to control the monitored temperature (T 1 , T 3 , T 4 ).

9. The method of claim 8 wherein the heating step includes heating process fluid in the outlet line between the boiler and the first steam turbine.

10. The method of claim 8 further including feeding the boiler with boiler feed water wherein the process fluid of the heating step includes the boiler feed water.

Assignments (4)
CORRECTIVE ASSIGNMENT TO CORRECT THE RECEIVING PARTY'S ADDRESS PREVIOUSLY RECORDED ON REEL 71474 FRAME 283. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Jun 30, 2025
From: GENERAL ELECTRIC TECHNOLOGY GMBH
To: GE VERNOVA INFRASTRUCTURE TECHNOLOGY LLC
Reel/Frame 071771/0479 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 3, 2025
From: GENERAL ELECTRIC TECHNOLOGY GMBH
To: GE VERNOVA INFRASTRUCTURE TECHNOLOGY LLC
Reel/Frame 071474/0283 →
CHANGE OF NAME Recorded Aug 17, 2016
From: ALSTOM TECHNOLOGY LTD
To: GENERAL ELECTRIC TECHNOLOGY GMBH
Reel/Frame 039714/0578 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 28, 2013
From: KIRCHNER, JULIA; SCHUELE, VOLKER; HELLWEG, STEFAN
To: ALSTOM TECHNOLOGY LTD
Reel/Frame 031488/0357 →
Priority Claims (1)
EP 12187352 · Oct 5, 2012 · regional
Continuity (1)
Related Publication 20140096522A1 · Apr 10, 2014