IP Library Granted Patent US 9,273,866
Granted Patent B2
US 9,273,866 · App. 14/124,250 · Granted Mar 1, 2016

Geothermal assisted power generation

Inventors: Brad William Mullard (Rutherford, AU); Behdad Moghtaderi (Callaghan, AU)
Assignee: NEWCASTLE INNOVATION LIMITED
F22D1/003F01K13/00F01K27/00F03G6/065F03G6/067F03G7/04Y02E10/10Y02E10/46
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,273,866
App. No.
14/124,250
Granted
Mar 1, 2016
Kind
B2
Abstract

In a coal fired power plant ( 17 ) incorporating a feed-water heater ( 10 ), energy is provided to the feed-water heater by pumping geothermal hot water through supply and return pipes ( 15, 16 ) from a geothermal reservoir ( 14 ) located beneath an adjacent coal seam ( 19 ). The coal seam acts as an insulating layer, increasing the temperature of the geothermal reservoir ( 14 ). Solar heat collectors ( 21 ) and ( 25 ) can also be provided to boost the temperature of the geothermal hot water and/or the feed water.

Claims (6)

1. A geothermal assisted coal-fired power plant including a furnace arranged to heat feed-water into steam, a turbine driven by the steam and in turn driving an electrical generator, a condenser arranged to receive exhaust steam from the turbine, cooling and condensing it back to water, and a feed-water heater arranged to reheat water from the condenser before feeding it back to the furnace, wherein the power plant uses coal taken from one or more coal seams in the vicinity of the power plant, and the feed-water heater is provided with energy from a geothermal reservoir located beneath at least one of the coal seams.

2. A geothermal assisted power plant as claimed in claim 1 wherein the coal seam acts as an insulating heat flow barrier, keeping the temperature of the geothermal reservoir at a higher level than would be the case in the absence of the coal seam.

3. A geothermal assisted power plant as claimed in claim 1 wherein the energy from the geothermal reservoir is provided by pumping geothermally heated water from the reservoir, circulating this geothermal hot water through the feed-water heater, and then returning it to the geothermal reservoir for re-heating.

4. A geothermal assisted power plant as claimed in claim 3 wherein both the coal seam and the geothermal reservoir are located some distance from the power plant with the geothermal hot water re-circulated through insulated supply and return pipelines.

5. A geothermal assisted power plant as claimed in claim 4 wherein the temperature of the geothermal hot water in the supply pipeline is boosted by one or more solar collectors located along the supply pipeline.

6. A geothermal assisted power plant as claimed in claim 1 wherein the temperature of the feed-water is boosted by one or more solar collectors.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 1, 2017
From: NEWCASTLE INNOVATION LIMITED
To: THE UNIVERSITY OF NEWCASTLE
Reel/Frame 044277/0822 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 4, 2014
From: MULLARD, BRAD WILLIAM; MOGHTADERI, BEHDAD
To: NEWCASTLE INNOVATION LIMITED
Reel/Frame 032344/0051 →
Priority Claims (1)
AU 2011902528 · Jun 27, 2011 · national
Continuity (1)
Related Publication 20140116045A1 · May 1, 2014