Subsea wellhead assembly, a subsea installation using said wellhead assembly, and a method for completing a wellhead assembly

Inventors: Anthony Ray (Pau, FR); Patrick Marcellin (Buros, FR); Gilles Leger (St. Faust, FR)
Assignee: TOTAL SA
E21B7/12E21B33/035E21B33/043E21B34/04
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,657,525
App. No.
14/240,176
Granted
May 23, 2017
Kind
B2
Abstract

A subsea wellhead assembly comprising at least a casing housing and a casing extending down inside the well, and a tubing hanger. The tubing hanger comprises first and second valves, each valve being a fail safe valve.

Claims (11)

1. A subsea installation comprising at least:

a wellhead assembly placed at a top of a subsea well, the wellhead assembly not comprising a flow control device, said subsea wellhead assembly comprising:

a casing housing secured to the seabed and a casing extending down inside the well;

a tubing hanger having a lower end and an upper end, the lower end being adapted to suspend a tubing that extends down inside the casing and inside the well, a cylindrical space being in continuity inside the tubing and the tubing hanger for extracting an hydrocarbon fluid from the well;

and the tubing hanger comprising at least a first and a second valves located in series inside the cylindrical space, each valve of the first and second valves are fail safe valves having an opened state and a closed state, and each valve being naturally in the closed state and needing to be operated to remain in the opened state;

a manifold comprising a flow control device for transferring the hydrocarbon fluid to a storage system, and

a jumper line connected to said wellhead assembly and to said manifold, said jumper line comprising at a first end a well jumper connector adapted to be locked to the casing housing, said well jumper connector having a weight lower than ten tonnes,

wherein the upper end of the tubing hanger is adapted to be directly and only connected vertically to the well jumper connector of the jumper line.

2. The subsea installation according to claim 1 , wherein jumper line is a flexible line.

3. The subsea installation according to claim 1 , wherein the tubing hanger extends in a direction substantially perpendicular to the seabed, and the upper end of the tubing hanger is adapted to be connected to the jumper line in any angular position around said direction.

4. The subsea installation according to claim 1 , wherein the first and second valves are metal ball valves.

Assignments (3)
CORRECTIVE ASSIGNMENT TO CORRECT THE NAME OF THE ASSIGNEE PREVIOUSLY RECORDED AT REEL: 67096 FRAME: 87. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Jun 26, 2024
From: TOTALENERGIES SE (PREVIOUSLY TOTAL SA THEN TOTAL SE)
To: TOTALENERGIES ONETECH
Reel/Frame 068051/0530 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 12, 2024
From: TOTALENERGIES SE (PREVIOUSLY TOTAL SA THEN TOTAL SE)
To: TOTALENERGIES ONETECH (PREVIOUSLY TOTALENERGIES ONE TECH)
Reel/Frame 067096/0087 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 20, 2014
From: RAY, ANTHONY; MARCELLIN, PATRICK; LEGER, GILLES
To: TOTAL SA
Reel/Frame 033151/0555 →