IP Library Granted Patent US 9,416,767
Granted Patent B2
US 9,416,767 · App. 14/275,181 · Granted Aug 16, 2016

Erecting a wind powerplant

Inventors: Alf Trede (Immenstedt, DE); Oliver Heinecke (Hamburg, DE); Carsten Eusterbarkey (Simonsberg, DE)
Assignee: SENVION SE
F03D1/001B66C1/108B66C1/62F03D1/0658F05B2230/61Y02E10/721Y02E10/728Y02P70/523
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,416,767
App. No.
14/275,181
Granted
Aug 16, 2016
Kind
B2
Abstract

A method for handling a wind powerplant's rotor hub or to handle a wind powerplant's rotor using a hoist, in particular for erecting a wind powerplant or for assembling or disassembling a rotor to and from such a powerplant, in particular a hub or a rotor being configured by means of one assembly side to the wind powerplant's tower, the hub or rotor being raised or held by the hoist. In the raised state, the hub is tilted by a tilting mechanism acting on it out of the initial, raised position by a predetermined angle of tilting, or the rotor is tilted by a tilting mechanism acting on the rotor blade roots of the rotor through a predetermined angle of tilting. A mechanism to handle a wind powerplant's rotor hub of a wind powerplant's rotor, in particular for assembling or dismantling a rotor to or from its wind powerplant.

Claims (11)

1. A method for assembling/disassembling a rotor to/from a wind powerplant, where a rotor hub, or the rotor, is mounted at one assembly side to a tower of the wind powerplant, the method comprising the steps of:

providing a tilting mechanism that is affixed to at least one of the rotor hub and rotor blade roots of the rotor, wherein the rotor hub and the rotor each define a respective center of gravity, wherein the tilting mechanism includes an actuator and an engagement point, and wherein the actuator is at least one of a telescopic cylinder, a cable winch, and a control cable to shorten and lengthen a cable;

raising the rotor hub or the rotor and holding the rotor hub or the rotor with a hoisting device with a hoisting means that engages the engagement point of the tilting mechanism, wherein the engagement point of the tilting mechanism is a force application site for the hoisting means connected thereto;

tilting the rotor hub in the raised state with the tilting mechanism, out of an initially raised position by a predetermined angle of tilt or tilting the rotor from the initial, raised position through the predetermined angle of tilt with the tilting mechanism, wherein in either tilting step, the tilting mechanism is directly connected to the hoisting device and a distance between the engagement point and either the rotor hub center of gravity or the rotor center of gravity is changed, wherein the engagement point is stationary during the tilting of the rotor hub; and

providing guide cables that do not tilt the rotor or the rotor hub, but further orient the rotor or the rotor hub.

2. The method as claimed in claim 1 , wherein the tilting mechanism is actuated or switched to initiate tilting.

3. The method of claim 1 , wherein the rotor hub or the rotor is mounted on or dismantled from the tower or a tower nacelle.

4. The method of claim 3 , wherein prior to raising the rotor hub, the tilting mechanism is connected to said rotor hub or that prior to raising the rotor the tilting mechanism is connected to said rotor.

5. The method of claim 1 , wherein the tilting mechanism is disposed between the hoisting means of said hoisting device and the rotor hub or between the hoisting means of the hoisting device and the rotor.

6. The method of claim 1 , wherein following the raising action, said tilted rotor hub or the tilted rotor each by its assembly side is configured against a hub assembly side of the tower or to a nacelle mounted on the tower.

7. The method of claim 1 , wherein the hoisting device is a crane.

Assignments (6)
CHANGE OF ADDRESS Recorded Aug 31, 2023
From: SIEMENS GAMESA RENEWABLE ENERGY SERVICE GMBH
To: SIEMENS GAMESA RENEWABLE ENERGY SERVICE GMBH
Reel/Frame 064834/0873 →
CHANGE OF NAME Recorded Oct 20, 2022
From: SENVION DEUTSCHLAND GMBH
To: SIEMENS GAMESA RENEWABLE ENERGY SERVICE GMBH
Reel/Frame 064371/0624 →
CHANGE OF NAME Recorded Sep 16, 2022
From: SENVION GMBH
To: SENVION DEUTSCHLAND GMBH
Reel/Frame 061462/0567 →
CHANGE OF NAME Recorded Aug 3, 2022
From: SENVION AG
To: SENVION GMBH
Reel/Frame 061068/0001 →
CHANGE OF NAME Recorded Jul 18, 2022
From: SENVION SE
To: SENVION AG
Reel/Frame 060692/0328 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 16, 2014
From: TREDE, ALF; HEINECKE, OLIVER; EUSTERBARKEY, CARSTEN
To: SENVION SE
Reel/Frame 033321/0770 →
Priority Claims (1)
DE 10 2007 062 428 · Dec 20, 2007 · national
Continuity (2)
Continuation 12336980 · Dec 17, 2008
Related Publication 20140319091A1 · Oct 30, 2014