Support system for an equipment item on a concrete slab

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,347,599
App. No.
14/514,723
Granted
May 24, 2016
Kind
B2
Abstract

A support system for an equipment item on a concrete slab includes at least one raised block relative to the slab and of a single piece with the slab. The block includes a metal belt delimiting the vertical walls of the block and a metal support fastened to the belt and capping the block to receive a foot of the equipment item.

Claims (16)

1. A support system for an equipment item on a concrete slab comprising:

at least one raised block relative to the concrete slab and the at least one raised block of a single piece with the concrete slab;

a metal belt delimiting vertical walls of the at least one raised block; and

a metal support fastened to the metal belt for capping the at least one raised block, with the metal support equipped to receive a foot of the equipment item, and including drop edges at a periphery of the metal support, with the drop edges surrounding the metal belt and fastened to the metal belt by welding.

2. The system as claimed in claim 1 , wherein the metal belt includes connecting means protruding inwardly to link the metal belt to the concrete slab.

3. The system as claimed in claim 1 , wherein the connecting means are studs welded onto the metal belt.

4. The system as claimed in claim 1 , wherein two raised blocks of the at least one raised block are distributed on the concrete slab in a main direction, one of the raised blocks including sliding means for the foot of the equipment item that the block supports to slide the foot of the equipment item on the block in the main direction.

5. The system as claimed in claim 4 , wherein the sliding means includes two rules extending in a longitudinal direction along two parallel guiding faces of the foot.

6. The system as claimed in claim 5 , wherein at least one of the rules also includes a tab overhanging a corner face of the foot to form an angle with a corresponding guiding face to prevent any lifting of the foot.

7. A method for producing a support system for an equipment item, the method comprising:

installing a formwork forming a metal belt to delimit a block on a top of a slab, with reinforcement for the slab and the block;

pouring to form the slab and the block delimited within the formwork of concrete; and

fastening to the metal belt

a metal support to cap the block, with the metal support equipped to receive a foot of the equipment item and including drop edges at a periphery of the metal support, with the drop edges surrounding the metal belt and being fastened to the metal belt by welding.

8. The method as claimed in claim 7 , wherein the metal belt is equipped with connecting means between the metal belt and the concrete slab and block.

9. The method as claimed in claim 7 , wherein the metal support is fastened to the metal belt by welding after the metal support's positioning has been set.

Assignments (5)
MERGER Recorded Mar 21, 2025
From: ARABELLE TECHNOLOGIES
To: ARABELLE SOLUTIONS FRANCE
Reel/Frame 070587/0348 →
NUNC PRO TUNC ASSIGNMENT Recorded Nov 26, 2024
From: GENERAL ELECTRIC TECHNOLOGY GMBH
To: POWER SOLUTIONS GAMMA FRANCE
Reel/Frame 069450/0966 →
CHANGE OF NAME Recorded Nov 26, 2024
From: POWER SOLUTIONS GAMMA FRANCE
To: ARABELLE TECHNOLOGIES
Reel/Frame 069451/0916 →
CHANGE OF NAME Recorded Aug 17, 2016
From: ALSTOM TECHNOLOGY LTD
To: GENERAL ELECTRIC TECHNOLOGY GMBH
Reel/Frame 039714/0578 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 19, 2014
From: LAFFONT, PATRICK
To: ALSTOM TECHNOLOGY LTD
Reel/Frame 034211/0039 →