IP Library Granted Patent US 10,670,293
Granted Patent B2
US 10,670,293 · App. 14/716,104 · Granted Jun 2, 2020

HVAC system mode detection based on control line current

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,670,293
App. No.
14/716,104
Granted
Jun 2, 2020
Kind
B2
Abstract

A monitoring system for monitoring a heating, ventilation, and air conditioning (HVAC) system of a building includes a monitoring server. The monitoring server is configured to receive an aggregate control line current value from a monitoring device. The aggregate control line current value represents a total current flowing through control lines used by a thermostat to command the HVAC system. The monitoring server is configured to determine a commanded operating mode of the HVAC system in response to the aggregate control line current value. Operating modes of the HVAC system include at least one of an idle mode and an ON mode. The monitoring server is configured to analyze a system condition of the HVAC system based on the determined commanded operating mode.

Claims (50)

1. A monitoring system for monitoring a heating, ventilation, and air conditioning (HVAC) system of a building, the monitoring system comprising:

a monitoring device installed at the building, wherein:

a thermostat activates a first operating mode of the HVAC system via a first line of a plurality of control lines,

the thermostat activates a second operating mode of the HVAC system via a second line of the plurality of control lines,

the monitoring device is configured to measure an electrical parameter related to the plurality of control lines,

the monitoring device is configured to determine an aggregate control line current value based on the electrical parameter,

the aggregate control line current value represents a total current flowing through the plurality of control lines, and

the monitoring device is configured to transmit the aggregate control line current value; and

a monitoring server configured to:

receive the aggregate control line current value from the monitoring device;

determine a commanded operating mode of the HVAC system based on the aggregate control line current value; and

analyze a system condition of the HVAC system based on the determined commanded operating mode.

2. The monitoring system of claim 1 wherein the system condition includes at least one of a detected fault of the HVAC system and a predicted fault of the HVAC system.

3. The monitoring system of claim 2 wherein the monitoring server is configured to generate an alert for at least one of a customer and a contractor in response to determining presence of at least one of the detected fault and the predicted fault.

4. The monitoring system of claim 1 wherein the monitoring server is located remotely from the building.

5. The monitoring system of claim 1 wherein:

the monitoring device includes a current sensor configured to measure a first current flowing through a conductor supplying power to the thermostat, and

the monitoring device is configured to determine the aggregate control line current value based on the first current.

6. The monitoring system of claim 1 wherein:

the monitoring device includes a voltage sensor configured to measure a voltage on an output side of a transformer associated with the plurality of control lines,

the monitoring device is configured to determine the aggregate control line current value based on an apparent transformer ratio, and

the apparent transformer ratio is based on the measured voltage of the output side of the transformer and a voltage on an input side of the transformer.

7. The monitoring system of claim 1 wherein:

the monitoring device includes a voltage sensor configured to measure a voltage associated with the plurality of control lines, and

the monitoring device is configured to determine the aggregate control line current value based on the measured voltage.

8. The monitoring system of claim 1 further comprising a second monitoring device, wherein:

the second monitoring device includes a current sensor configured to measure an aggregate control line current consumed by an outdoor unit of the HVAC system; and

the monitoring server is configured to infer, in response to the commanded operating mode of the HVAC system being unknown, the commanded operating mode using the aggregate control line current consumed by the outdoor unit.

9. The monitoring system of claim 1 wherein operating modes of the HVAC system include a plurality of operating modes including at least two of the following: a fan only mode, a heating mode, a second stage heating mode, a cooling mode, a second stage cooling mode, an auxiliary heating mode, and an emergency mode.

10. The monitoring system of claim 1 wherein the monitoring server is configured to:

store a table of aggregate control line current values with respect to operating modes of the HVAC system; and

determine the commanded operating mode of the HVAC system based on the table.

11. The monitoring system of claim 10 wherein the table includes an aggregate control line current value corresponding to each of the operating modes of the HVAC system.

12. The monitoring system of claim 11 wherein:

the table includes a first upper limit and a first lower limit that correspond to the first operating mode; and

the monitoring server is configured to determine that the commanded operating mode of the HVAC system is the first operating mode in response to the received aggregate control line current value being greater than or equal to the first lower limit and less than or equal to the first upper limit.

13. The monitoring system of claim 10 wherein the table is predefined upon commissioning of the HVAC system.

14. The monitoring system of claim 10 wherein the table is predefined based on a model number of the HVAC system.

15. The monitoring system of claim 10 wherein the monitoring server is configured to populate the table.

16. The monitoring system of claim 1 wherein the monitoring server is configured to, in response to the commanded operating mode of the HVAC system being unknown, infer the commanded operating mode based on additional data.

17. The monitoring system of claim 16 wherein the monitoring server is configured to store the inference along with the received aggregate control line current value for future use.

18. The monitoring system of claim 16 wherein the additional data includes outside ambient temperature in a geographical region of the HVAC system.

19. The monitoring system of claim 16 wherein the additional data includes supply air temperature of the HVAC system.

20. The monitoring system of claim 16 wherein the additional data includes a refrigerant line temperature of the HVAC system.

21. The monitoring system of claim 16 wherein the additional data includes a time of year.

22. The monitoring system of claim 16 wherein the additional data includes an aggregate current consumption of the HVAC system.

23. The monitoring system of claim 22 wherein the aggregate current consumption of the HVAC system includes all current drawn by components of at least one of (i) an indoor enclosure of the HVAC system and (ii) an outdoor enclosure of the HVAC system.

24. The monitoring system of claim 23 wherein the additional data includes at least one of:

a steady-state value of the aggregate current consumed by the indoor enclosure; and

a time-domain or frequency-domain signature of the aggregate current consumed by the indoor enclosure.

Assignments (7)
SECURITY INTEREST Recorded Jul 9, 2024
From: COPELAND LP
To: U.S. BANK TRUST COMPANY, NATIONAL ASSOCIATION, AS NOTES COLLATERAL AGENT
Reel/Frame 068241/0264 →
SECURITY INTEREST Recorded Jul 17, 2023
From: COPELAND LP
To: ROYAL BANK OF CANADA, AS COLLATERAL AGENT
Reel/Frame 064278/0598 →
SECURITY INTEREST Recorded Jul 17, 2023
From: COPELAND LP
To: U.S. BANK TRUST COMPANY, NATIONAL ASSOCIATION, AS NOTES COLLATERAL AGENT
Reel/Frame 064279/0327 →
SECURITY INTEREST Recorded Jul 17, 2023
From: COPELAND LP
To: WELLS FARGO BANK, NATIONAL ASSOCIATION, AS COLLATERAL AGENT
Reel/Frame 064280/0695 →
INTELLECTUAL PROPERTY ASSIGNMENT AGREEMENT Recorded May 30, 2023
From: EMERSON ELECTRIC CO.
To: EMERSUB CXIII, INC.
Reel/Frame 063804/0643 →
INTELLECTUAL PROPERTY ASSIGNMENT AGREEMENT Recorded May 30, 2023
From: EMERSUB CXIII, INC.
To: COPELAND LP
Reel/Frame 063804/0583 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 28, 2015
From: ABIPROJO, PRIOTOMO; ARENSMEIER, JEFFREY N.
To: EMERSON ELECTRIC CO.
Reel/Frame 036903/0156 →