Chemical process for primary system material passivation during hot functional testing of nuclear power plants

Inventors: Rachel L. Devito (Gibsonia, PA); Jason P. Mazzoccoli (Pittsburgh, PA); Edward J. Silva (Vernon, CT); Deborah J. Buckley (Evans City, PA); Richard J. Jacko (Murrysville, PA); William A. Byers (Murrysville, PA)
Assignee: Westinghouse Electric Company LLC
G21C17/0225C23F11/18C23F11/187G21C21/00
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,453,576
App. No.
14/812,051
Granted
Oct 22, 2019
Kind
B2
Abstract

The present invention relates to a pre-core hot functional testing (HFT) preconditioning process, which includes the introduction of chemical additives, e.g., zinc, into coolant water that circulates through the primary system of a new nuclear power plant, at various temperatures. The chemical additives contact the primary system surfaces, which results in the formation of a protective zinc-containing oxide film on the fresh surfaces to control corrosion release and deposition during subsequent normal operation of the nuclear power plant. The method includes a series of three chemistry phases to optimize the passivation process: 1) an alkaline-reducing phase, 2) an acid-reducing phase and 3) an acid-oxidizing phase.

Claims (42)

1. A method of passivating a metal surface in a primary system of a new nuclear power plant having a nuclear core and coolant water flowing through the primary system, comprising:

heating the primary system to a simulated normal operating temperature prior to an initial loading of fuel in the nuclear core;

initiating an addition of zinc to the coolant water at a temperature greater than or equal to about 350° F. prior to reaching the simulated normal operating temperature;

achieving a target zinc concentration in the coolant water from greater than 40 to 300 ppb at the simulated normal operating temperature;

conducting hot functional testing in the primary system at the target zinc concentration and the simulated normal operating temperature;

allowing the zinc to contact the metal surface in the primary system; and

forming an initial zinc-containing oxide film on the metal surface.

2. The method of claim 1 , wherein the zinc is added in the form of zinc acetate.

3. The method of claim 1 , further comprising adding base to the coolant water.

4. The method of claim 3 , wherein the base is selected from the group consisting of lithium hydroxide, potassium hydroxide and mixtures thereof.

5. The method of claim 4 , wherein the lithium hydroxide has a concentration sufficient for the coolant water to have a pH from 6.9 to 7.4 at the operating temperature or from 9.5 to 10.1 at 25° C.

6. The method of claim 5 , wherein the concentration of lithium in the coolant water is from 0.3 ppm to 2.0 ppm.

7. The method of claim 3 , further comprising adding boric acid to the coolant water.

8. The method of claim 7 , wherein the boric acid is added in an amount to such that there is a concentration of 100 ppm boron or less.

9. The method of claim 3 , further comprising adding hydrogen.

10. The method of claim 9 , wherein a concentration of the hydrogen in the coolant water is selected from a value or a range consisting of at least 4 cc/kg, from 4 to 50 cc/kg, from 4 to 15 cc/kg, from 15 to 30 cc/kg, and 4.5 cc/kg.

11. The method of claim 9 , wherein the adding of the zinc, the lithium hydroxide and the hydrogen is initiated when the coolant water has a temperature of 350° F. or higher and less than the simulated normal operating temperature of the coolant water.

12. A method for passivating a metal surface in a primary system of a new nuclear power plant during pre-core hot functional testing, the nuclear power plant having a nuclear core and coolant water flowing through the primary system, comprising:

heating the primary system to a simulated normal operating temperature prior to an initial loading of fuel in the nuclear core;

achieving an alkaline-reducing phase, comprising:

adding hydroxide in an amount sufficient to maintain the coolant water at an alkaline pH;

initiating an addition of zinc to the coolant water at a temperature greater than or equal to about 350° F. prior to reaching the simulated normal operating temperature;

achieving a target zinc concentration in the coolant water from greater than 40 to 300 ppb at the simulated normal operating temperature;

conducting the pre-core hot functional testing at the target zinc concentration and the simulated normal operating temperature;

allowing the zinc to contact the metal surface in the primary system; and

forming a zinc-containing oxide film on the metal surface;

then initiating an acid-reducing phase, comprising:

borating the coolant water; and

then initiating an acid-oxidizing phase, comprising:

removing hydrogen from the coolant water.

13. The method of claim 12 , further comprising adding an oxygen scavenger to the coolant water prior to initiating the alkaline-reducing phase.

14. A method of controlling the addition of zinc into coolant water flowing through a primary system and a nuclear core of a nuclear power plant during a preconditioning prior to an initial fuel load and normal power operation, comprising:

heating the primary system to a simulated normal operating temperature prior to an initial loading of fuel in the nuclear core;

achieving an alkaline-reducing phase, comprising:

initiating an addition of zinc, hydroxide and hydrogen to the coolant water at a temperature greater than or equal to about 350° F. prior to reaching the simulated normal operating temperature;

achieving a target zinc concentration from greater than 40 to 300 ppb in the coolant water at the simulated normal operating temperature;

establishing a plateau at the simulated normal operating temperature; and

conducting the pre-core hot functional testing at the target zinc concentration during the plateau;

initiating an acid-reducing phase to simulate a plant shutdown chemistry condition, comprising:

adding boric acid to the coolant water; and

initiating an acid-oxidizing phase, comprising:

removing hydrogen from the coolant water.

Assignments (9)
RELEASE OF SECURITY INTEREST IN PATENTS Recorded Jan 30, 2024
From: CREDIT SUISSE AG, CAYMAN ISLANDS, AS COLLATERAL AGENT
To: WESTINGHOUSE ELECTRIC COMPANY LLC; FAUSKE AND ASSOCIATES LLC
Reel/Frame 066380/0392 →
RELEASE OF SECURITY INTEREST IN PATENTS Recorded Jan 30, 2024
From: BANK OF MONTREAL, AS COLLATERAL AGENT
To: WESTINGHOUSE ELECTRIC COMPANY LLC; BHI ENERGY I SPECIALTY SERVICES LLC
Reel/Frame 066380/0599 →
SECURITY INTEREST Recorded Jan 26, 2024
From: WESTINGHOUSE ELECTRIC COMPANY LLC; BHI ENERGY I SPECIALTY SERVICES LLC; STONE & WEBSTER, L.L.C. (FORMERLY STONE & WEBSTER, INC.)
To: DEUTSCHE BANK AG NEW YORK BRANCH, AS COLLATERAL AGENT
Reel/Frame 066373/0604 →
PATENT SECURITY AGREEMENT Recorded May 27, 2022
From: WESTINGHOUSE ELECTRIC COMPANY LLC; BHI ENERGY I SPECIALTY SERVICES LLC
To: BANK OF MONTREAL, AS COLLATERAL AGENT
Reel/Frame 060791/0372 →
RELEASE OF SECURITY INTEREST IN PATENTS Recorded Aug 1, 2019
From: GOLDMAN SACHS BANK USA, AS COLLATERAL AGENT
To: WESTINGHOUSE ELECTRIC COMPANY LLC; FAUSKE AND ASSOCIATES LLC
Reel/Frame 049937/0032 →
SECURITY INTEREST Recorded Aug 1, 2018
From: WESTINGHOUSE ELECTRIC COMPANY LLC; FAUSKE AND ASSOCIATES LLC
To: CREDIT SUISSE AG, CAYMAN ISLANDS BRANCH, AS COLLATERAL AGENT
Reel/Frame 046708/0222 →
SECURITY INTEREST Recorded Aug 1, 2018
From: WESTINGHOUSE ELECTRIC COMPANY LLC; FAUSKE AND ASSOCIATES LLC
To: GOLDMAN SACHS BANK USA, AS COLLATERAL AGENT
Reel/Frame 046708/0332 →
SECURITY INTEREST Recorded Aug 1, 2018
From: WESTINGHOUSE ELECTRIC COMPANY LLC; FAUSKE AND ASSOCIATES LLC
To: BANK OF MONTREAL, AS ADMINISTRATIVE AGENT
Reel/Frame 046708/0639 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 29, 2015
From: DEVITO, RACHEL L.; MAZZOCCOLI, JASON P.; SILVA, EDWARD J.; BUCKLEY, DEBORAH J.; JACKO, RICHARD J.; BYERS, WILLIAM A.
To: WESTINGHOUSE ELECTRIC COMPANY LLC
Reel/Frame 036206/0164 →