Method for fabrication of a conductor bar

Inventors: Markus Huwyler (Muri, CH); Andreas Koepfler (Waldshut-Tiengen, DE)
Assignee: GE Renewable Technologies
H02K15/0414B29C43/003B29C43/18B29C43/36H01B13/06H02K15/105H02K15/12B29C2043/185B29K2063/00B29K2105/20B29K2309/10B29K2995/0005B29L2031/3406B29L2031/749H02K3/14H02K3/40
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,090,740
App. No.
14/881,425
Granted
Oct 2, 2018
Kind
B2
Abstract

The present disclosure relates to a method for fabrication of a conductor bar and to a use of a conductor tape with applied putty for the fabrication of a conductor bar. Described is a method for fabrication of a conductor bar including, applying a putty at one side of a conductor tape, applying a release foil at the other side of the putty opposed to the conductor tape, removing the release foil before applying the conductor tape to the narrow side of the conductor bar, providing a pressing mold with rounded edges at the inner side of the pressing mold, surrounding the conductor bar with putty and conductor tape with the pressing mold, and hot pressing the conductor bar with the pressing mold.

Claims (15)

1. A method for fabrication of a conductor bar, the method comprising;

applying a putty at one side of a conductor tape;

providing a pressing mould with rounded edges at the inner side of the pressing mould;

applying the conductor tape with the applied putty directed to the conductor bar together on the conductor bar such that the putty and tape are applied to the conductor bar in one step with the putty in a non-hardened state;

the conductor tape and applied putty placed longitudinally over top and bottom sides of the conductor bar so that the conductor tape extends over the top or bottom side and at least partially onto longitudinal sides of the conductor bar;

applying the pressing mould to the conductor bar;

hot pressing the conductor bar by means of the pressing mould; and

removing the pressing mould.

2. The method for fabrication of a conductor bar according to claim 1 , wherein the conductor tape is broader than a width of the putty applied to the conductor tape.

3. The method for fabrication of a conductor bar according to claim 1 , further comprising applying a release foil at the other side of the putty opposed to the conductor tape, and removing the release foil before applying the conductor tape to the narrow side of the conductor bar.

4. The method according to claim 1 , wherein before the hot pressing in the pressing mould the conductor bar is completely enveloped by an additional foil, and removing the additional foil after hot pressing.

5. The method according to claim 1 , wherein the conductor tape is a mica tape.

6. The method according to claim 1 , wherein the step of applying the putty with conductor tape and release foil is conducted by a winder.

7. The method according to claim 1 , wherein the pressing mould is built from four parts, an upper part, two middle parts each for a longitudinal side of the conductor bar, and a bottom part, whereas the upper part and the bottom part each have an inner radius of the edges of the inner side of 2.5 mm.

8. The method according to claim 1 , wherein the pressing mould is built from nine parts, one upper part, three upper middle parts abut the upper part, one intermediate part abuts the three middle parts at the top and abuts three further lower middle parts below, and a bottom part abuts the middle parts, whereby the pressing mould is designed to include four conductor bars.

Assignments (3)
CHANGE OF NAME Recorded Apr 7, 2017
From: ALSTOM RENEWABLE TECHNOLOGIES
To: GE RENEWABLE TECHNOLOGIES
Reel/Frame 042191/0072 →
CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNEE PREVIOUSLY RECORDED ON REEL 036863 FRAME 0588. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Jun 1, 2016
From: HUWYLER, MARKUS; KOEPFLER, ANDREAS
To: ALSTOM RENEWABLE TECHNOLOGIES
Reel/Frame 038852/0623 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 23, 2015
From: HUWYLER, MARKUS; KOEPFLER, ANDREAS
To: ALSTOM TECHNOLOGY LTD
Reel/Frame 036863/0588 →
Priority Claims (1)
EP 14189092 · Oct 15, 2014 · regional
Continuity (1)
Related Publication 20160111946A1 · Apr 21, 2016