IP Library Granted Patent US 10,415,819
Granted Patent B2
US 10,415,819 · App. 15/091,221 · Granted Sep 17, 2019

High temperature sub-critical boiler with common steam cooled wall between furnace and convection pass

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,415,819
App. No.
15/091,221
Granted
Sep 17, 2019
Kind
B2
Abstract

A boiler is disclosed in which the furnace is divided into a lower furnace and an upper furnace. The lower furnace uses water-cooled membrane walls, while the upper furnace uses steam-cooled membrane walls that act as superheating surfaces. The upper furnace and the convection pass are also located next to each other, so that they share a common steam-cooled wall. There is no open pass between the furnace and the convection pass.

Claims (48)

1. A boiler, comprising:

an upper furnace having steam-cooled membrane walls, the steam-cooled membrane walls comprising pipes sealed by membrane disposed between and connected to the pipes;

a lower furnace below the upper furnace, the lower furnace having water-cooled membrane walls comprising water-cooled pipes sealed by membrane disposed between and connected to the water-cooled pipes; and

a convection pass downstream of the upper furnace, the convection pass having steam-cooled membrane walls and extending downwards;

wherein the upper furnace and the convection pass share a common steam-cooled membrane wall, the common steam-cooled membrane wall being both a rear wall of the upper furnace and a front wall of the convection pass; and

a steam separator configured to deliver dry steam to a steam-cooled circuit including the common steam-cooled membrane wall; and

wherein the upper furnace includes a side wall, the convection pass includes a side wall having a lower edge, and a seal is present at a junction of the common steam-cooled membrane wall, the upper furnace side wall, and the lower edge of the convection pass side wall;

wherein the upper furnace does not contain water-cooled tube walls; and

wherein the lower furnace does not contain steam-cooled tube walls.

2. The boiler of claim 1 , wherein the steam-cooled circuit includes the steam-cooled membrane walls of the upper furnace and the steam separator is also configured to receive wet steam from a water-cooled circuit including the water-cooled membrane walls of the lower furnace.

3. The boiler of claim 2 , further comprising one or more superheaters disposed in the upper furnace or the convection pass, the one or more superheaters comprising pipes without a membrane.

4. The boiler of claim 1 , further comprising:

burners arranged to combust fuel to generate heated flue gas that flows upward through the upper furnace and then downward through the convection pass;

wherein the common steam-cooled membrane wall is heated by the heated flue gas that flows upward through the upper furnace and by the heated flue gas that flows downward through the convection pass.

5. A boiler, comprising:

a furnace having steam-cooled membrane walls forming an upper portion of the furnace, the steam-cooled membrane walls comprising pipes sealed by membrane disposed between and connected to the pipes; and

a convection pass having steam-cooled membrane walls forming at least a portion of the convection pass, and being fluidly connected to the upper portion of the furnace;

wherein the furnace and the convection pass share a common steam-cooled membrane wall comprising a single layer of pipes sealed by a single layer of membrane disposed between and connected to the single layer of pipes, the common steam-cooled membrane wall being both a rear wall of the upper furnace and a front wall of the convection pass; and

a steam separator configured to deliver dry steam to a steam-cooled circuit including the common steam-cooled membrane wall;

wherein the furnace includes an upper furnace and a lower furnace below the upper furnace, the upper furnace having the steam-cooled membrane walls and the common steam-cooled membrane wall; and the lower furnace having water-cooled membrane walls, the water-cooled membrane walls comprising water-cooled pipes sealed by membrane disposed between and connected to the water-cooled pipes;

wherein the upper furnace does not contain water-cooled tube walls; and

wherein the lower furnace does not contain steam-cooled tube walls; and

wherein the steam-cooled circuit runs sequentially through an upper furnace front wall and the common steam-cooled membrane wall, then through upper furnace side walls, then through a secondary superheater.

6. The boiler of claim 5 , wherein the steam separator includes a saturated steam inlet connected with a water-cooled circuit including the water-cooled membrane walls of the lower furnace.

7. The boiler of claim 6 , wherein the steam-cooled circuit further includes one or more superheaters disposed in the upper furnace or the convection pass and comprising pipes without membrane.

8. The boiler of claim 7 , further comprising:

burners arranged to combust fuel to generate heated flue gas that flows upward through the upper furnace and then downward through the convection pass;

wherein the common steam-cooled membrane wall is heated by the heated flue gas that flows upward through the upper furnace and by the heated flue gas that flows downward through the convection pass.

9. A method of operating a boiler, comprising:

combusting fuel to generate heated flue gas that flows sequentially upwards through an upper furnace and downwards through a convection pass; and

sending superheated steam through a common steam-cooled membrane wall to capture heat energy from the heated flue gas and further superheat the superheated steam;

wherein the common steam-cooled membrane wall is heated both by the heated flue gas flowing upward through the upper furnace and by the heated flue gas flowing downward through the convection pass;

wherein the common steam-cooled membrane wall is both a rear wall of the upper furnace and a front wall of the convection pass;

wherein the superheated steam sent through the common steam-cooled membrane wall is generated from water that is heated in a lower furnace located below the upper furnace to obtain wet steam that is subsequently separated in a steam separator to obtain water and dry steam;

wherein the upper furnace does not contain water-cooled tube walls; and

wherein the lower furnace does not contain steam-cooled tube walls; and

wherein the steam-cooled circuit runs sequentially through an upper furnace front wall and the common steam-cooled membrane wall, then through upper furnace side walls, then through a secondary superheater.

10. The method of claim 9 , wherein the dry steam passes through at least one superheater prior to being sent to the common steam-cooled membrane wall.

11. The method of claim 10 , wherein the common steam-cooled membrane wall comprises a single layer of pipes separated by membrane therebetween.

12. The method of claim 11 , wherein the upper furnace includes a side wall, the convection pass includes a side wall having a lower edge, and a seal is present at a junction of the common steam-cooled membrane wall, the upper furnace side wall, and the lower edge of the convection pass side wall.

13. The boiler of claim 1 , wherein the water-cooled tube walls comprise carbon steel.

14. The boiler of claim 5 , wherein the water-cooled tube walls comprise carbon steel.

15. The method of claim 9 , wherein the water-cooled tube walls comprise carbon steel.

16. The boiler of claim 13 , wherein the steam-cooled tube walls comprise stainless steel.

17. The boiler of claim 14 , wherein the steam-cooled tube walls comprise stainless steel.

18. The method of claim 15 , wherein the steam-cooled tube walls comprise stainless steel.

19. The boiler of claim 1 , wherein the upper furnace comprises an arch surface.

20. The boiler of claim 5 , wherein the boiler further comprises a baffle wall that divides the convection pass into a front convection pass and a rear convection pass, the front convection pass containing a reheater and the rear convection pass containing a primary superheater.

Assignments (6)
SECURITY INTEREST Recorded Jul 18, 2025
From: BABCOCK & WILCOX ENTERPRISES, INC.; THE BABCOCK & WILCOX COMPANY; DIAMOND POWER INTERNATIONAL, LLC; BABCOCK & WILCOX SPIG, INC.; BABCOCK & WILCOX CANADA CORP.; BABCOCK & WILCOX FPS INC.
To: B. RILEY FINANCIAL, INC.
Reel/Frame 072053/0943 →
SECURITY INTEREST Recorded Mar 3, 2025
From: BABCOCK & WILCOX ENTERPRISES, INC.; THE BABCOCK & WILCOX COMPANY; DIAMOND POWER INTERNATIONAL, LLC; BABCOCK & WILCOX SPIG, INC.; BABCOCK & WILCOX CANADA CORP.; BABCOCK & WILCOX FPS INC.
To: PENSION BENEFIT GUARANTY CORPORATION
Reel/Frame 070380/0647 →
RELEASE OF SECURITY INTEREST Recorded Sep 13, 2024
From: MSD PCOF PARTNERS XLV, LLC
To: THE BABCOCK & WILCOX COMPANY; DIAMOND POWER INTERNATIONAL, LLC; AMERICON LLC
Reel/Frame 069017/0362 →
SECURITY INTEREST Recorded Jan 19, 2024
From: BABCOCK & WILCOX ENTERPRISES, INC.; THE BABCOCK & WILCOX COMPANY; DIAMOND POWER INTERNATIONAL, LLC; BABCOCK & WILCOX SPIG, INC.; BABCOCK & WILCOX CANADA CORP.; BABCOCK & WILCOX FPS INC.
To: AXOS BANK, AS ADMINISTRATIVE AGENT
Reel/Frame 066354/0765 →
SECURITY INTEREST Recorded Jul 22, 2021
From: THE BABCOCK & WILCOX COMPANY (F/K/A BABCOCK & WILCOX POWER GENERATION GROUP, INC.); BABCOCK & WILCOX SPIG, INC.; BABCOCK & WILCOX TECHNOLOGY, LLC; DIAMOND POWER INTERNATIONAL, LLC (F/K/A DIAMOND POWER INTERNATIONAL, INC.)
To: MSD PCOF PARTNERS XLV, LLC, AS AGENT
Reel/Frame 056962/0486 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 28, 2016
From: WELLS, ERIC L; DETZEL, ROGER A; BENNETT, ALBERT J; THAYER, STEVEN D
To: THE BABCOCK & WILCOX COMPANY
Reel/Frame 038406/0815 →