IP Library Granted Patent US 10,533,778
Granted Patent B2
US 10,533,778 · App. 15/156,548 · Granted Jan 14, 2020

Turbo economizer used in chiller system

Inventor: Jeffrey Allen Morgan (Fishersville, VA)
Assignee: DAIKIN APPLIED AMERICAS INC.
F25B1/10F01D5/141F25B11/00F25B11/04F25B39/00F25B43/00F25B27/00F25B39/02F25B2339/0242F25B2341/0662F25B2400/0751F25B2400/13F25B2400/14F25B2400/141F25B2400/23
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,533,778
App. No.
15/156,548
Granted
Jan 14, 2020
Kind
B2
Abstract

A turbo economizer adapted to be used in a chiller system includes a nozzle, a turbine, and an economizer impeller. The nozzle introduces refrigerant into the turbo economizer. The turbine is disposed downstream of the nozzle, and the turbine is attached to a shaft rotatable about a rotation axis. A flow of the refrigerant introduced through the nozzle drives the turbine to rotate the shaft. The economizer impeller is attached to the shaft so as to be rotated in accordance with rotation of the shaft. In the turbo economizer, the nozzle reduces a pressure of the refrigerant such that a pressure of the refrigerant entering the turbo economizer is lower than a predetermined pressure, at least some of the refrigerant passes through the nozzle is introduced into the economizer impeller, and the economizer impeller increases a pressure of the refrigerant introduced thereinto to the predetermined pressure.

Claims (51)

1. A turbo economizer adapted to be used in a chiller system including a compressor which is a multi-stage centrifugal compressor including at least a first stage and a second stage, an evaporator, and a condenser connected to form a refrigeration circuit, the turbo economizer comprising:

a nozzle configured and arranged to introduce refrigerant into the turbo economizer;

a turbine disposed downstream of the nozzle, the turbine being attached to a shaft rotatable about a rotation axis, and a flow of the refrigerant introduced through the nozzle driving the turbine to rotate the shaft, the turbine being configured and arranged to separate the refrigerant introduced through the nozzle into gas refrigerant and liquid refrigerant;

a turbine gas outlet arranged to discharge the gas refrigerant from the turbine;

a turbine liquid outlet arranged to discharge the liquid refrigerant from the turbine, the turbine liquid outlet being different from the turbine gas outlet; and

an economizer impeller attached to the shaft so as to be rotated in accordance with rotation of the shaft,

the turbo economizer being connected to an intermediate stage of the compressor located between the first stage and the second stage of the compressor,

the nozzle being further configured and arranged to reduce a pressure of the refrigerant such that a pressure of the refrigerant entering the turbo economizer is lower than an intermediate pressure in the intermediate stage of the compressor,

the turbine gas outlet being connected to an inlet of the economizer impeller to introduce gas refrigerant separated at the turbine into the economizer impeller, and

the economizer impeller being configured and arranged such that the gas refrigerant is introduced into the economizer impeller at a pressure lower than the intermediate pressure and exits the economizer impeller at the intermediate pressure.

2. The turbo economizer according to claim 1 , wherein

the turbo economizer is refrigerant-powered without using a separate motor in which the turbine is driven by the flow of the refrigerant and the economizer impeller is driven by motive power from the turbine.

3. The turbo economizer according to claim 1 , wherein

the nozzle is further configured and arranged to increase a flow velocity of the refrigerant.

4. The turbo economizer according to claim 1 , wherein

the turbine is configured and arranged to reduce a flow velocity of the refrigerant.

5. The turbo economizer according to claim 1 , wherein

the turbine is a Pelton wheel turbine.

6. The turbo economizer according to claim 1 , further comprising

a bearing rotatably supporting the shaft.

7. The turbo economizer according to claim 1 , further comprising

an expander disposed downstream of the turbine,

the expander being configured and arranged to perform an expansion process on the refrigerant introduced therein, and

the refrigerant which has undergone the expansion process is introduced to the evaporator in the chiller system.

8. The turbo economizer according to claim 7 , wherein

the expander includes at least one expander impeller.

9. The turbo economizer according to claim 7 , wherein

the expander is used as a power generator driven by energy obtained in the expansion process of the refrigerant.

10. A chiller system comprising:

a refrigeration circuit including a compressor which is a multi-stage centrifugal compressor including at least a first stage and a second stage, an evaporator, and a condenser connected together; and

a turbo economizer,

the turbo economizer including

a nozzle configured and arranged to introduce refrigerant into the turbo economizer,

a turbine disposed downstream of the nozzle, the turbine being attached to a shaft rotatable about a rotation axis, and a flow of the refrigerant introduced through the nozzle driving the turbine to rotate the shaft, the turbine being configured and arranged to separate the refrigerant introduced through the nozzle into gas refrigerant and liquid refrigerant;

a turbine gas outlet arranged to discharge the gas refrigerant from the turbine;

a turbine liquid outlet arranged to discharge the liquid refrigerant from the turbine, the turbine liquid outlet being different from the turbine gas outlet; and

an economizer impeller attached to the shaft so as to be rotated in accordance with rotation of the shaft,

the turbo economizer being connected to an intermediate stage of the compressor located between the first stage and the second stage of the compressor,

the nozzle being further configured and arranged to reduce a pressure of the refrigerant such that a pressure of the refrigerant entering the turbo economizer is lower than an intermediate pressure in the intermediate stage of the compressor,

the turbine gas outlet being connected to an inlet of the economizer impeller to introduce gas refrigerant separated at the turbine into the economizer impeller, and

the economizer impeller being configured and arranged such that the gas refrigerant is introduced into the economizer impeller at a pressure lower than the intermediate pressure and exits the economizer impeller at the intermediate pressure.

11. The chiller system according to claim 10 , wherein

the turbo economizer is disposed between the evaporator and the condenser in the chiller system.

12. The chiller system according to claim 10 , wherein

the turbo economizer further includes an expander disposed downstream of the turbine, and

the expander is configured and arranged to perform an expansion process on the refrigerant introduced therein such that the refrigerant which has undergone the expansion process is introduced to the evaporator in the chiller system.

13. The chiller system according to claim 12 , wherein

the expander is used as a power generator driven by energy obtained in the expansion process of the refrigerant.

14. The chiller system according to claim 12 , wherein

the evaporator is a falling film evaporator, and

the expander is used as a pump driven by energy obtained in the expansion process of the refrigerant to circulate the refrigerant through the falling film evaporator.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 22, 2021
From: DAIKIN APPLIED AMERICAS INC.
To: DAIKIN INDUSTRIES, LTD.
Reel/Frame 058180/0318 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 17, 2016
From: MORGAN, JEFFREY ALLEN
To: DAIKIN APPLIED AMERICAS INC.
Reel/Frame 038616/0336 →
Continuity (1)
Related Publication 20170336106A1 · Nov 23, 2017