Load restoration in a high or medium voltage substation

Inventor: Wolfgang Wimmer (Langenthal, CH)
Assignee: ABB Schweiz AG
H02H7/28H02H3/05H02H3/06Y02E60/723Y04S10/16Y04S10/525
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,374,415
App. No.
15/293,960
Granted
Aug 6, 2019
Kind
B2
Abstract

The present invention is concerned with simplified configuration as well as supervision and testing of load restoration functions in high or medium voltage substations of electrical power transmission or distribution networks. The invention takes advantage of the fact that all information for load restoration is available from a standardized configuration representation and from dynamically observable events. Specifically, the IEC 61850 Substation Configuration Description (SCD) file includes the substation single line, the bus bar or breaker failure protection functionality related to it, and the way how reclosing commands can be conveyed for the restoration process. A load restore function or load transfer application observes the execution of a protection trip function and the concurrent connection state of the bays to bus bars in order to automatically restore the power flow across a failed bus bar segment to a parallel healthy bus bar segment.

Claims (39)

1. A load restoration method in a substation with a bus bar connectable to a plurality of bays and loads, comprising:

reading a standardized configuration description of a substation automation system and obtaining therefrom a static topology representative of at least a part of the substation,

observing a switch status of a switching device of the substation,

establishing a dynamic substation topology upon observation of a status change of the switch status,

observing a trip isolating a segment of the bus bar,

identifying an orphan bay previously connected to the isolated bus bar segment,

identifying connecting switching devices between the orphan bay and an un-tripped bus bar segment, and

issuing close commands on behalf of the connecting switching devices to connect the orphan bay to the un-tripped bus bar segment.

2. The method according to claim 1 , comprising

establishing, based on the dynamic substation topology, for each bay a connecting node to which the bay is connected, and

identifying an orphan bay with a connecting node being part of the isolated bus bar segment.

3. The method according to claim 1 , comprising

establishing, based on the dynamic substation topology, protection zones for the bus bar, and establishing, for each bay a connecting protection zone to which the bay is connected, and

identifying the orphan bay with a connecting protection zone related to the isolated bus bar segment.

4. The method according to claim 1 , comprising, between the steps of observing the trip and identifying the orphan bay, the step of waiting for a delay time of at least 0.5 seconds.

5. The method of claim 1 , wherein the un-tripped bus bar segment is different from the isolated segment of the bus bar.

6. The method of claim 1 , further comprising

issuing an open command to a disconnector in the isolated bus bar segment to connect the orphan bay to the un-tripped bus bar segment.

7. The method of claim 6 , further comprising

issuing a close command to a bay circuit breaker of the orphan bay to connect the orphan bay to the un-tripped bus bar segment.

8. An apparatus comprising an Intelligent Electronic Device IED in a substation with a bus bar connectable to a plurality of bays and loads, the IED configured to:

read a standardized configuration description of a substation automation system and obtain therefrom a static topology representative of at least a part of the substation;

observe a switch status of a switching device of the substation;

establish a dynamic substation topology upon observation of a status change of the switch status;

observe a trip isolating a segment of the bus bar;

identify an orphan bay previously connected to the isolated bus bar segment;

identify connecting switching devices between the orphan bay and an un-tripped bus bar segment, and

issue close commands on behalf of the connecting switching devices to connect the orphan bay to the un-tripped bus bar segment.

9. The apparatus of claim 8 , wherein the IED is further configured to:

establish, based on the dynamic substation topology, for each bay a connecting node to which the bay is connected; and

identify an orphan bay with a connecting node being part of the isolated bus bar segment.

10. The apparatus of claim 8 , wherein the IED is further configured to:

establish, based on the dynamic substation topology, protection zones for the bus bar;

establish, for each bay a connecting protection zone to which the bay is connected, and

identify the orphan bay with a connecting protection zone related to the isolated bus bar segment.

11. The apparatus of claim 8 , wherein the IED is further configured to wait for a delay time of at least 0.5 seconds between the observing of the trip and the identifying of the orphan bay.

12. The apparatus of claim 8 , wherein the un-tripped bus bar segment is different from the isolated segment of the bus bar.

13. The apparatus of claim 8 , wherein the IED is further configured to issue an open command to a disconnector in the isolated bus bar segment to connect the orphan bay to the un-tripped bus bar segment.

14. The method of claim 13 , wherein the IED is further configured to issue a close command to a bay circuit breaker of the orphan bay to connect the orphan bay to the un-tripped bus bar segment.

Assignments (4)
MERGER Recorded Nov 13, 2023
From: HITACHI ENERGY SWITZERLAND AG
To: HITACHI ENERGY LTD
Reel/Frame 065549/0576 →
CHANGE OF NAME Recorded Dec 31, 2021
From: ABB POWER GRIDS SWITZERLAND AG
To: HITACHI ENERGY SWITZERLAND AG
Reel/Frame 058666/0540 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 6, 2020
From: ABB SCHWEIZ AG
To: ABB POWER GRIDS SWITZERLAND AG
Reel/Frame 052916/0001 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 18, 2017
From: WIMMER, WOLFGANG
To: ABB SCHWEIZ AG
Reel/Frame 043893/0496 →
Priority Claims (1)
EP 14165203 · Apr 17, 2014 · regional
Continuity (2)
Continuation PCTEP2015057379 · Apr 2, 2015
Related Publication 20170033553A1 · Feb 2, 2017