IP Library Granted Patent US 10,000,122
Granted Patent B2
US 10,000,122 · App. 15/300,594 · Granted Jun 19, 2018

Method for operating parallel auxiliary converters in a rail vehicle

Inventors: Xiao Qiang Wu (Krefeld, DE); Nikolaj Echkilev (Dormagen, DE); Andreas Wellner (Krefeld, DE)
Assignee: SIEMENS AKTIENGESELLSCHAFT
B60L3/003H02H5/10H02J3/36H02M7/493B60L2200/26H02H3/16
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,000,122
App. No.
15/300,594
Granted
Jun 19, 2018
Kind
B2
Abstract

In a method for supplying an electrical load of a vehicle with electrical energy by auxiliary converters connected in parallel on the alternating-voltage side, a current flow between the auxiliary converters and a grounded N conductor of an energy supply network is interrupted in the presence a ground fault. The auxiliary converters connected in parallel on the alternating-voltage side are operated with fundamental-wave and pulse synchronicity. An energy supply system of a vehicle, in particular of a rail vehicle, performs this method, with the energy supply system including at least two auxiliary converters arranged in parallel, an energy supply network for supplying electrical loads, at least one switch for interrupting a current flow between the auxiliary converters and the energy supply network.

Claims (24)

1. A method of supplying an electrical load in an on-board energy supply network of a vehicle with electrical energy, said energy supply network having at least two auxiliary converters, said auxiliary converters configured to be switched in parallel on an AC voltage side and to feed the energy supply network of the vehicle, comprising the steps of:

interrupting a connection between a grounded N conductor of the energy supply network and the auxiliary converters in the event of a short circuit to ground; and

operating the auxiliary converters with phase position and frequency synchronicity by switching the auxiliary converters in parallel.

2. The method of claim 1 , wherein the short circuit to ground occurs in the energy supply network.

3. The method of claim 1 , wherein the vehicle is a rail vehicle.

4. The method of claim 1 , wherein the connection between a grounded N conductor of the energy supply network and respective auxiliary converters is interrupted by opening respective switches.

5. The method of claim 1 , wherein the auxiliary converters are operated with phase position, frequency and voltage level synchronicity.

6. A method of supplying an electrical load in an on-board energy supply network of a rail vehicle With electrical energy, said energy supply network having a grounded N conductor and at least two auxiliary converters that are switched in parallel on an AC voltage side, comprising the steps of:

switching off the auxiliary converters in the event of a short circuit to ground;

interrupting a connection between the switched-off auxiliary converters and the energy supply network by opening at least one respective switch;

switching on one of the switched-off auxiliary converters;

synchronizing the phase position and frequency of the converter that is switched-on while switching on a further auxiliary converter that was switched off; and

closing the at least one switch that interrupted the connection between the auxiliary converters and the energy supply network, once absence of the short circuit to ground has been established, thereby operating the auxiliary converters with phase position and frequency synchronicity.

7. The method of claim 6 , wherein the further auxiliary converter is synchronized with respect to phase position, frequency and voltage level.

8. An on-board energy supply system of a vehicle, comprising:

at least two auxiliary converters configured to be switched in parallel on an AC voltage side and to be synchronous in phase position and frequency;

an energy supply network configured to supply an electrical load with electrical energy and having a grounded N conductor that is connected to the converters; and

a switch configured to interrupt a connection between the grounded N conductor and the auxiliary converters of the energy supply network.

9. The energy supply system of claim 8 , configured to supply energy in a rail vehicle.

10. The energy supply system of claim 8 , further comprising at least one short circuit to ground monitoring facility.

11. The energy supply system of claim 8 , wherein each auxiliary converter is connected in parallel with others and includes a switch configured to switch the auxiliary converter on an AC voltage side of the auxiliary converter.

12. The energy supply system of claim 8 , wherein the energy supply system has a three-phase energy supply network and a single-phase energy supply network that are electrically connected to one another.

13. The energy supply system of claim 12 , wherein the electrical connection between the three-phase energy supply network and the single-phase energy supply network is implemented by an auxiliary converter.

14. The energy supply system of claim 8 , wherein the auxiliary converters are configured to be synchronous in phase position, frequency and voltage level.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 16, 2019
From: SIEMENS AKTIENGESELLSCHAFT
To: SIEMENS MOBILITY GMBH
Reel/Frame 048031/0079 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 26, 2016
From: ECHKILEV, NIKOLAJ; WELLNER, ANDREAS; WU, XIAO QIANG
To: SIEMENS AKTIENGESELLSCHAFT
Reel/Frame 040138/0739 →
Priority Claims (1)
EP 14162768 · Mar 31, 2014 · regional
Continuity (1)
Related Publication 20170207717A1 · Jul 20, 2017
Cited By (5)
US 12,233,683 US 12,237,627 US 12,334,835 US 12,368,301 US 12,576,688