Gas turbine, combined cycle plant, and activation method of gas turbine

Inventors: Masakazu Inoue (Kanagawa, JP); Masayuki Murakami (Kanagawa, JP)
Assignee: Mitsubishi Hitachi Power Systems, Ltd.
F02C9/18F01D11/24F01D19/00F01D25/12F01K23/08F01K23/10F02C3/04F02C6/18F02C7/18F02C7/185F02C7/28F05D2220/72F05D2260/213Y02E20/16Y02T50/671Y02T50/676
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,655,543
App. No.
15/507,547
Granted
May 19, 2020
Kind
B2
Abstract

A gas turbine includes an air cooler that subjects compressed air extracted from a compressor to heat exchange and supplies the cooled compressed air to a cooling system of a rotor system in a turbine; an air cooler bypass line that bypasses the compressed air introduced into the air cooler; an electric valve provided in the air cooler bypass line; and a control unit. The control unit controls opening and closing of the electric valve such that, during activation of a gas turbine, a degree of opening of the electric valve is set at or below a low-level degree of opening and such that, after the load of the gas turbine has been increased, the degree of opening of the electric valve is set to be larger than the low-level degree of opening.

Claims (20)

1. A combined cycle plant comprising:

a gas turbine including:

a compressor configured to compress air;

a combustor configured to mix and combust fuel and compressed air compressed by the compressor;

a turbine configured to obtain rotational power from combustion gas generated by the combustor;

an air cooler configured to subject compressed air extracted from the compressor to heat exchange, and to supply cooled compressed air to a cooling system of a rotor system in the turbine;

an air cooler bypass line configured to allow the compressed air extracted from the compressor to bypass the air cooler;

a cooler bypass valve provided in the air cooler bypass line; and

a controller configured to control opening and closing of the cooler bypass valve such that, during activation of the gas turbine, a degree of opening of the cooler bypass valve is set at or below a pre-set predetermined low-level degree of opening, and such that, after an increase of a load of the gas turbine, the degree of opening of the cooler bypass valve is set to be larger than the low-level degree of opening, wherein the cooler bypass valve is open when the degree of opening is set at or below the low-level degree of opening;

an exhaust heat recovery boiler configured to generate steam from exhaust heat of exhaust gas discharged from the gas turbine;

a steam turbine configured to be driven by the steam generated by the exhaust heat recovery boiler;

a condenser configured to condense the steam discharged from the steam turbine and generate water;

a feed water line configured to deliver feed water, obtained from the condenser via an economizer, to the air cooler and cause the feed water to exchange heat with compressed air;

an economizer bypass line configured to bypass feed water introduced into the economizer; and

an economizer bypass valve provided in the economizer bypass line,

wherein, during activation of the gas turbine, the controller performs control to close the cooler bypass valve such that the degree of opening of the cooler bypass valve is set at or below the low-level degree of opening, in order to decrease an amount of compressed air allowed to flow through the air cooler bypass line, and at the same time, performs control to increase a degree of opening of the economizer bypass valve, in order to increase an amount of feed water allowed to flow through the economizer bypass line, and after an increase of the load of the gas turbine, the controller performs control to open the cooler bypass valve such that the degree of opening of the cooler bypass valve is set to be larger than the low-level degree of opening, in order to increase the amount of compressed air allowed to flow through the air cooler bypass line, and at the same time, performs control to decrease the degree of opening of the economizer bypass valve, in order to decrease the amount of feed water allowed to flow through the economizer bypass line.

2. The combined cycle plant according to claim 1 , wherein the gas turbine further includes a detector configured to detect the degree of opening of the cooler bypass valve, wherein, when the detector detects that the degree of opening of the cooler bypass valve is at or below the low-level degree of opening, the controller starts activating the gas turbine.

3. The combined cycle plant according to claim 2 , wherein the cooler bypass valve is configured to retain the degree of opening thereof when a control signal indicating a degree of opening or a driving source of the cooler bypass valve is cut off.

4. The combined cycle plant according to claim 1 , wherein, when an abnormal state arises during activation of the gas turbine, in which such abnormal state a clearance between a rotating system and a static system in the gas turbine becomes small, the controller performs control to decrease the degree of opening of the cooler bypass valve to or below the low-level degree of opening.

5. The combined cycle plant according to claim 1 , wherein, when an operation is performed in which the clearance between the rotating system and the static system in the gas turbine becomes small, the controller performs control to decrease the degree of opening of the cooler bypass valve to or below the low-level degree of opening.

Assignments (3)
CORRECTIVE ASSIGNMENT TO CORRECT THE REMOVING PATENT APPLICATION NUMBER 11921683 PREVIOUSLY RECORDED AT REEL: 054975 FRAME: 0438. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded May 26, 2023
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 063787/0867 →
CHANGE OF NAME Recorded Jan 13, 2021
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 054975/0438 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 28, 2017
From: INOUE, MASAKAZU; MURAKAMI, MASAYUKI
To: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
Reel/Frame 041401/0609 →
Priority Claims (1)
JP 2014-204692 · Oct 3, 2014 · national
Continuity (1)
Related Publication 20170284307A1 · Oct 5, 2017
Cited By (1)
US 12,560,107