IP Library Granted Patent US 11,258,394
Granted Patent B2
US 11,258,394 · App. 15/567,175 · Granted Feb 22, 2022

Method for detection of upcoming pole slip

Inventors: Albert Fahringer (Kossen Osterreich, AT); Erich Kruckenhauser (Munster Osterreich, AT)
Assignee: INNIO Jenbacher GmbH & Co OG
H02P29/024G01R31/343H02K19/36H02P9/009H02P9/02H02P29/0241H02P2101/15
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,258,394
App. No.
15/567,175
Granted
Feb 22, 2022
Kind
B2
Abstract

A method for detecting an imminent pole slip of a synchronous generator electrically connected to a power supply network, whereby a signal characteristic of a power fault is detected and an imminent pole slip is determined via a predefinable value when a load angle of the synchronous generator increases, whereby the following steps are performed. Determination of a first load angle during operation without a power fault, determination of a generator frequency as a function of time when a power fault occurs, and precalculation of a second value of a load angle resulting from the power fault by adding the first value of the load angle to a load angle difference occurring during the power fault, whereby this load angle difference is caused by a deviation of a generator frequency relative to a power frequency.

Claims (26)

1. A method for detecting an imminent pole slip of a synchronous generator electrically connected to a power supply network, wherein a signal characteristic of a power fault is detected and an imminent pole slip is determined based on a pre-defined value when a load angle of the synchronous generator increases, comprising the following steps:

determining a first load angle during operation of the synchronous generator without a power fault,

determining a synchronous generator frequency as a function of time when a power fault occurs, and

precalculating a second value of a load angle resulting from the power fault by adding the first value of the load angle to a load angle difference occurring during the power fault, wherein this load angle difference is caused by a deviation of the synchronous generator frequency relative to a power frequency of a power grid, wherein the power fault comprises a power outage of the synchronous generator, wherein, on exceeding a second predefinable value for the second load angle resulting from the power fault, the synchronous generator is disconnected from the power supply network.

2. The method according to claim 1 , wherein after detecting a signal characteristic of a power fault, the load angle difference is determined between a polar wheel voltage and a synchronous generator voltage, wherein the load angle difference is caused by a deviation of the synchronous generator frequency relative to the power frequency.

3. The method according to claim 1 , wherein the first load angle in the operation without a power fault is determined by measuring a synchronous generator voltage, and a synchronous generator current.

4. The method according to claim 1 , wherein, from the calculated second value of the load angle resulting from the power fault, a decision is derived as to whether the synchronous generator should remain connected to the power supply network.

5. The method according to claim 1 , wherein, on exceeding a first predefinable value for the second load angle resulting from the power fault, at least one measure is taken to reduce the load angle.

6. A device for determining a load angle of a synchronous generator with a rotor electrically connected to a power supply network, comprising

at least one measuring device used to determine a frequency of a synchronous generator voltage and/or a synchronous generator current of the synchronous generator,

at least one rotary speed measuring device for determining a rotary speed,

and at least one controller designed to perform the following steps:

determine a first load angle during operation of the synchronous generator without a power fault,

determine a synchronous generator frequency as a function of time when a power fault occurs, and

precalculate a second value of a load angle resulting from the power fault by adding the first value of the load angle to a load angle difference occurring during the power fault, wherein this load angle difference is caused by a deviation of the synchronous generator frequency relative to a power frequency of a power grid, wherein the power fault comprises a power outage of the synchronous generator, wherein, on exceeding a second predefinable value for the second load angle resulting from the power fault, the synchronous generator is disconnected from the power supply network.

7. The device according to claim 6 , wherein the device further consists of a mechanical power source that is mechanically coupled to the synchronous generator.

8. The device according to claim 7 , wherein the mechanical power source is an internal combustion engine, in particular a stationary engine.

9. The device according to claim 7 , wherein the mechanical power source is a wind power plant, a hydroelectric power plant or a gas turbine.

10. A controller, configured to:

determine a first load angle during operation of a synchronous generator without a power fault,

determine a synchronous generator frequency as a function of time when a power fault occurs, and

precalculate a second value of a load angle resulting from the power fault by adding the first value of the load angle to a load angle difference occurring during the power fault, wherein this load angle difference is caused by a deviation of the synchronous generator frequency relative to a power frequency of a power grid, wherein the power fault comprises a power outage of the synchronous generator, wherein, on exceeding a second predefinable value for the second load angle resulting from the power fault, the synchronous generator is disconnected from a power supply network.

11. The controller of claim 10 , wherein after detecting a signal characteristic of a power fault, the load angle difference is determined between a polar wheel voltage and a synchronous generator voltage, wherein the load angle difference is caused by a deviation of the synchronous generator frequency relative to the power frequency.

12. The controller of claim 10 , wherein the first load angle is determined by measuring a synchronous generator voltage and a synchronous generator current.

13. The controller of claim 10 , wherein, from the calculated second value of the load angle resulting from the power fault, a decision is derived as to whether the synchronous generator should remain connected to the power supply network.

14. The controller of claim 10 , wherein, on exceeding a first predefinable value for the second load angle resulting from the power fault, at least one measure is taken to reduce the first load angle.

Assignments (3)
CHANGE OF NAME Recorded Apr 6, 2019
From: GE JENBACHER GMBH & CO OG
To: INNIO JENBACHER GMBH & CO OG
Reel/Frame 049046/0174 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 18, 2018
From: FAHRINGER, ALBERT; KRUCKENHAUSER, ERICH
To: GE JENBACHER GMBH & CO OG
Reel/Frame 047209/0829 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 17, 2018
From: FAHRINGER, ALBERT
To: GE JENBACHER GMBH & CO OG
Reel/Frame 047189/0087 →
Priority Claims (1)
AT A 233/2015 · Apr 17, 2015 · national
Continuity (1)
Related Publication 20180102725A1 · Apr 12, 2018