IP Library Granted Patent US 10,428,695
Granted Patent B2
US 10,428,695 · App. 15/574,629 · Granted Oct 1, 2019

Combined cycle plant, device for controlling said plant, and method for starting up said plant

Inventors: Masayuki Kayahara (Kanagawa, JP); Elvio Rubio (London, GB); Pablo Ratia (London, GB); Daniel Carlos Mora (London, GB)
Assignee: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
F01K23/101F01D19/00F01K7/165F01K13/02F01K23/10F01K23/16F02C7/26F01D15/10F05D2270/053Y02E20/16
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,428,695
App. No.
15/574,629
Granted
Oct 1, 2019
Kind
B2
Abstract

In a combined cycle plant, a device for controlling a combined cycle plant, and a method for starting up a combined cycle plant, the time for starting up the combined cycle plant can be shortened by providing: a gas turbine having a compressor, a combustor, and a turbine; a heat recovery steam generator for generating steam by means of the exhaust heat of exhaust gas from the gas turbine. A steam turbine is driven by the steam generated by the heat recovery steam generator; and a control device is configured to set a standby load for the gas turbine during a start-up continuously to change in accordance with a change in metal temperature of the steam turbine.

Claims (44)

1. A device for controlling a combined cycle plant, the combined cycle plant including a gas turbine, a heat recovery steam generator, and a steam turbine, the device comprising:

a controller configured to set a standby load to continuously change in accordance with a change in metal temperature of the steam turbine, the standby load being a load retained on the gas turbine when the gas turbine is started up;

wherein the controller is configured to:

acquire the metal temperature of the steam turbine;

set the standby load based on the metal temperature acquired, and to continuously adjust the standby load in accordance with the change in metal temperature of the steam turbine; and

start up and drive the gas turbine such that a load of the gas turbine reaches the standby load and the load of the gas turbine is retained on the standby load.

2. A combined cycle plant comprising:

a gas turbine including a compressor, a combustor, and a turbine;

a heat recovery steam generator configured to generate steam by exhaust heat of exhaust gas from the gas turbine;

a steam turbine to be driven by means of steam generated by the heat recovery steam generator; and

the device according to claim 1 .

3. The combined cycle plant according to claim 2 ,

wherein the standby load is a function of the metal temperature and increases in accordance with a rise of the metal temperature.

4. The combined cycle plant according to claim 3 ,

wherein the standby load is a function including a low temperature region and a high temperature region with respect to the metal temperature, and a changing rate of the standby load with respect to the metal temperature in the low temperature region and that in the high temperature region are varied from each other.

5. The combined cycle plant according to claim 4 ,

wherein the changing rate of the standby load in the high temperature region is set to be greater than the changing rate of the standby load in the low temperature region.

6. The combined cycle plant according to claim 2 ,

wherein the standby load is set to a constant value in a region in which the metal temperature is equal to or lower than a lower limit temperature set in advance.

7. The combined cycle plant according to claim 2 ,

wherein the standby load is set to a constant value in a region in which the metal temperature is equal to or higher than an upper limit temperature set in advance.

8. A combined cycle plant comprising:

a gas turbine including a compressor, a combustor, and a turbine;

a heat recovery steam generator configured to generate steam by exhaust heat of exhaust gas from the gas turbine;

a steam turbine driven by steam generated by the heat recovery steam generator; and

the device according to claim 1 .

9. The combined cycle plant according to claim 8 ,

wherein the increasing load rate is a function of the metal temperature and increases in accordance with a rise of the metal temperature.

10. The combined cycle plant according to claim 9 ,

wherein the increasing load rate is a function including a low temperature region and a high temperature region with respect to the metal temperature, and a changing rate of the increasing load rate with respect to the metal temperature in the low temperature region and that in the high temperature region are varied from each other.

11. The combined cycle plant according to claim 10 ,

wherein the changing rate of the increasing load rate in the high temperature region is set to be greater than the changing rate of the increasing load rate in the low temperature region.

12. The combined cycle plant according to claim 8 ,

wherein the increasing load rate is set to a constant value in a region in which the metal temperature is equal to or lower than a lower limit temperature set in advance.

13. The combined cycle plant according to claim 8 ,

wherein the increasing load rate is set to a constant value in a region in which the metal temperature is equal to or higher than an upper limit temperature set in advance.

14. The device according to claim 1 , wherein the controller is configured to set an increasing load rate of the steam turbine during a start-up to continuously change in accordance with a change in metal temperature of the steam turbine.

15. A method of starting up a combined cycle plant, the combined cycle plant including a gas turbine, a heat recovery steam generator, and a steam turbine, and said method comprising:

setting during a start-up a standby load to continuously change in accordance with a change in metal temperature of the steam turbine, the standby load being a load retained on the gas turbine when the gas turbine is started up;

wherein said setting the standby load during the start-up comprises:

acquiring the metal temperature of the steam turbine;

setting the standby load based on the metal temperature acquired, and continuously adjusting the standby load in accordance with the change in metal temperature of the steam turbine; and

starting up and driving the gas turbine such that a load of the gas turbine reaches the standby load and the load of the gas turbine is retained on the standby load.

16. The method according to claim 15 , further comprising setting during a start-up an increasing load rate of the steam turbine to continuously change in accordance with a change in metal temperature of the steam turbine.

Assignments (3)
CORRECTIVE ASSIGNMENT TO CORRECT THE REMOVING PATENT APPLICATION NUMBER 11921683 PREVIOUSLY RECORDED AT REEL: 054975 FRAME: 0438. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded May 26, 2023
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 063787/0867 →
CHANGE OF NAME Recorded Jan 13, 2021
From: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
To: MITSUBISHI POWER, LTD.
Reel/Frame 054975/0438 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 16, 2017
From: KAYAHARA, MASAYUKI; RUBIO, ELVIO; RATIA, PABLO; MORA, DANIEL CARLOS
To: MITSUBISHI HITACHI POWER SYSTEMS, LTD.
Reel/Frame 044152/0805 →
Priority Claims (1)
JP 2015-110628 · May 29, 2015 · national
Continuity (1)
Related Publication 20180135468A1 · May 17, 2018