System and method of assembling and installing commercial roofing

Inventors: Brig Jeffs (New Harmony, UT); Edson Harker (Hurricane, UT); James Barlow (Colorado City, AZ); James Harker (Colorado City, UT); Nathan Jessop (Hildale, UT); Sam Williams (Colorado City, AZ); Thomas Harker (Hurricane, UT)
Assignee: Innovatech, LLC
E04D15/04B60L50/50B60R11/06B62D21/18E04D15/00B60L2200/40B60Y2200/49E04D2015/042
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,655,335
App. No.
15/813,117
Granted
May 19, 2020
Kind
B2
Abstract

A system for assembling roofing at ground level has an adjustable-length center frame separating a first assembly side from a second assembly side; a first cantilevered gantry on the first assembly side and a second cantilevered gantry on a second side, each cantilevered gantry moveable along the length of the center frame; a plurality of outrigger beams coupled to opposing ends of the center beam, each outrigger beam having a catwalk thereon; a first joist railing and a second joist railing on each assembly side, each joist railing configured to receive an end of an open web joist; and a base frame comprising a plurality of wheels. Once the roofing section has been assembled, hoisting the assembled roofing section to the top of a structure.

Claims (10)

1. A method of assembling roofing, the method comprising:

placing a plurality of open web joists between a first joist railing of a first assembly side and a second joist railing of the first assembly side;

placing another plurality of open web joists between a first joist railing of a second assembly side and a second joist railing of the second assembly side;

mounting and welding one or more purlins of the plurality of open web joists on the first assembly side and second assembly side, respectively;

placing corrugated steel sheathing on a first cantilevered gantry of a first assembly side;

moving the first cantilevered gantry along the length of a center frame;

removing the corrugated steel sheathing from the first cantilevered gantry as it travels on the center frame;

securing the corrugated steel sheathing to the plurality of open web joists on the first assembly side, which forms an assembled roofing section;

hoisting the assembled roofing section to a top of a structure for securing thereto.

2. The method of claim 1 , further comprising a motor to move the first cantilevered gantry along the center frame.

Assignments (2)
CHANGE OF NAME Recorded Jan 25, 2022
From: INNOVATECH, LLC
To: INNOVATECH SYSTEMS, LLC
Reel/Frame 058838/0221 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 7, 2020
From: HARKER, JAMES; HARKER, EDSON; JEFFS, BRIGG; BARLOW, JAMES; JESSOP, NATHAN; WILLIAMS, SAM; HARKER, THOMAS
To: INNOVATECH, LLC
Reel/Frame 052330/0418 →
Continuity (3)
Provisional Application 62421448 · Nov 14, 2016
Provisional Application 62550855 · Aug 28, 2017
Related Publication 20180135306A1 · May 17, 2018
Cited By (2)
US 12,246,401 US 12,291,875