US 10,819,602 · App. 16/210,141 · Granted Oct 27, 2020

Inferring physical layer connection status of generic cables from planned single-end connection events

Inventors: Gene Malone (Kernersville, NC); Andrew P. Roberts (Wrexham, GB); Peter Smith (Chester, GB); Eric W. Sybesma (Edina, MN)
Assignees: CommScope Technologies LLC; CommScope Connectivity UK Limited
H04L43/0811G06F13/364H04L41/24
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,819,602
App. No.
16/210,141
Granted
Oct 27, 2020
Kind
B2
Abstract

A work order is generated. The work order comprises a first work order step specifying that a port of a first network element is to be connected to a port of a second network element using a cable. The first and second network elements are configured to detect when connections are made at the specified ports of the first network element and the second network element. A management system is configured to update information it maintains to indicate that there is a connection between the specified port of the first network element and the specified port of the second network element if connections made at the specified ports of the first and second network elements are detected during a period in which the first work order step of the first work order is expected to be performed. A similar technique can be used for disconnecting a cable.

Claims (33)

1. A method comprising:

generating a first work order comprising a first work order step specifying that a port of a first network element is to be connected to a port of a second network element using a cable;

detecting, using the first network element, when a connection is made at the specified port of the first network element using the cable, and reading physical layer information about the cable from a first connector of the cable; and

determining, by an electronic work order application, if connection of the cable to the first network element complies with the first work order based on the physical layer information read from the first connector.

2. The method of claim 1 , further comprising, altering a visual indicator at the specified port of the first network element in response to determining that connection of the cable to the first network element complies with the first work order.

3. The method of claim 1 , further comprising:

detecting, using the second network element, when a connection is made at the specified port of the second network element, and reading the physical layer information about the cable from a second connector of the cable; and

determining, by an electronic work order application, if connection of the cable to the second network element complies with the first work order based on the physical layer information read from the second connector.

4. The method of claim 1 , wherein the first network element and the second network element comprise first and second managed network elements, respectively.

5. The method of claim 1 , wherein the first and second network elements comprise at least one of a patch panel, an optical distribution frame, a splitter tray, a switch, and a router.

6. The method of claim 1 , wherein each of the first and second network elements includes at least one of EEPROM-based PLM technology and RFID PLM technology.

7. The method of claim 1 , wherein the cable comprises at least one of a fiber optic cable and a copper cable.

8. The method of claim 1 , wherein the physical layer information comprises an identifier.

9. The method of claim 1 , wherein the cable comprises a storage device that stores the physical layer information.

10. The method of claim 3 , further comprising, altering a visual indicator at the specified port of the second network element in response to determining that connection of the cable to the first network element complies with the first work order.

11. A system comprising:

a first network element comprising at least one port, wherein the first network element is configured to detect when a cable is connected to the port of the first network element;

a second network element comprising at least one port, wherein the second network element is configured to detect when a cable is connected to the port of the second network element; and

a management system communicatively coupled to the first network element and the second network element;

wherein the management system is configured to generate a first work order comprising a first work order step specifying that the port of a first network element is to be connected to the port of the second network element using the cable;

wherein the management system is configured to detect, using the first network element, when a connection is made at the specified port of the first network element using the cable, and read physical layer information about the cable from a first connector of the cable; and

wherein the management system is configured to determine if connection of the cable to the first network element complies with the first work order based on the physical layer information read from the first connector.

12. The system of claim 11 , further comprising a visual indicator at the specified port of the first network element, wherein the management system is configured to alter the visual indicator at the specified port of the first network element in response to determining that connection of the cable to the first network element complies with the first work order.

13. The system of claim 11 , further comprising:

wherein the management system is configured to detect, using the second network element, when a connection is made at the specified port of the second network element, and read the physical layer information about the cable from a second connector of the cable; and

wherein the management system is configured to determine if connection of the cable to the second network element complies with the first work order based on the physical layer information read from the second connector.

14. The system of claim 11 , wherein the cable comprises at least one of a fiber optic cable and a copper cable.

15. The system of claim 11 , wherein the first network element and the second network element comprise first and second managed network elements, respectively.

16. The system of claim 11 , wherein the first and second network elements comprise at least one of a patch panel, an optical distribution frame, a splitter tray, a switch, and a router.

17. The system of claim 11 , wherein each of the first and second network elements includes at least one of EEPROM-based PLM technology and RFID PLM technology.

18. The system of claim 11 , wherein the physical layer information comprises an identifier.

19. The system of claim 11 , wherein the cable comprises a storage device that stores the physical layer information.

20. The system of claim 13 , further comprising a visual indicator at the specified port of the second network element, wherein the management system is configured to alter the visual indicator at the specified port of the second network element in response to determining that connection of the cable to the first network element complies with the first work order.

Assignments (8)
SECURITY INTEREST Recorded Dec 17, 2024
From: ARRIS ENTERPRISES LLC; COMMSCOPE TECHNOLOGIES LLC; COMMSCOPE INC., OF NORTH CAROLINA; OUTDOOR WIRELESS NETWORKS LLC; RUCKUS IP HOLDINGS LLC
To: APOLLO ADMINISTRATIVE AGENCY LLC
Reel/Frame 069889/0114 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: TYCO ELECTRONICS CORPORATION
To: ADC TELECOMMUNICATIONS, INC.
Reel/Frame 047707/0679 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: ADC TELECOMMUNICATIONS, INC.; TE CONNECTIVITY SOLUTIONS GMBH
To: TYCO ELECTRONICS SERVICES GMBH
Reel/Frame 047707/0751 →
CHANGE OF NAME Recorded Dec 7, 2018
From: TYCO ELECTRONICS UK INFRASTRUCTURE LIMITED
To: COMMSCOPE CONNECTIVITY UK LIMITED
Reel/Frame 047708/0156 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: MALONE, GENE; ROBERTS, ANDREW P.; SMITH, PETER; SYBESMA, ERIC W.
To: TYCO ELECTRONICS CORPORATION; TYCO ELECTRONICS UK LTD.; ADC TELECOMMUNICATIONS, INC.
Reel/Frame 047707/0548 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: TYCO ELECTRONICS UK LTD.
To: TYCO ELECTRONICS UK INFRASTRUCTURE LIMITED
Reel/Frame 048897/0311 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: COMMSCOPE EMEA LIMITED
To: COMMSCOPE TECHNOLOGIES LLC
Reel/Frame 048906/0001 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 7, 2018
From: TYCO ELECTRONICS SERVICES GMBH
To: COMMSCOPE EMEA LIMITED
Reel/Frame 047741/0042 →