Building energy storage system with peak load contribution cost optimization

Inventor: Mohammad N. ElBsat (Milwaukee, WI)
Assignee: Johnson Controls Technology Company
G05F1/66G05B13/026G05B15/02G06Q10/04G06Q50/06H02J3/32H02J7/0068H02J13/0006G05B2219/2614G05B2219/2642H02J3/003
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,036,249
App. No.
16/383,228
Granted
Jun 15, 2021
Kind
B2
Abstract

An energy storage system for a building includes a battery and an energy storage controller. The battery is configured to store electrical energy purchased from a utility and to discharge stored electrical energy for use in satisfying a building energy load. The energy storage controller is configured to generate a cost function including a peak load contribution (PLC) term. The PLC term represents a cost based on electrical energy purchased from the utility during coincidental peak hours in an optimization period. The controller is configured to modify the cost function by applying a peak hours mask to the PLC term. The peak hours mask identifies one or more hours in the optimization period as projected peak hours and causes the energy storage controller to disregard the electrical energy purchased from the utility during any hours not identified as projected peak hours when calculating a value for the PLC term.

Claims (54)

1. A central plant comprising:

one or more storage devices configured to store one or more resources purchased from a utility or generated by the central plant and to discharge the one or more resources for use in satisfying a building load; and

a controller configured to:

obtain a cost function comprising a peak load contribution (PLC) term, wherein the PLC term represents a cost based on an amount of the one or more resources purchased from the utility during coincidental peak (CP) hours of an optimization period comprising a plurality of time steps, the CP hours comprising a subset of the plurality of time steps, wherein the cost is a function of one or more decision variables representing an amount of the one or more resources to store in the one more storage devices or discharge from the one or more storage devices during each of the plurality of time steps;

modify the cost function by applying a peak hours mask to the PLC term, wherein the peak hours mask identifies one or more hours in the optimization period as projected peak hours and causes the controller to assign substantially zero cost, in the PLC term, to the one or more resources purchased from the utility during any hours not identified as projected peak hours; and

allocate, to each of the time steps within the optimization period, an amount of the one or more resources to store in the one or more storage devices or discharge from the one or more storage devices during the time step by performing an optimization of the modified cost function to determine values of the decision variables.

2. The central plant of claim 1 , wherein the CP hours comprise one or more hours of the optimization period during which regional demand peaks occur for a geographic region in which the building is located.

3. The central plant of claim 1 , wherein:

the CP hours are unknown prior to the optimization period; and

the projected peak hours comprise an estimate of the CP hours and are identified prior to the optimization period.

4. The central plant of claim 1 , wherein the peak hours mask comprises a vector of binary values, each of the binary values corresponding to an hour of the optimization period and indicating whether the corresponding hour is a projected peak hour.

5. The central plant of claim 1 , wherein the controller is configured to create the peak hours mask based on user input defining the projected peak hours.

6. The central plant of claim 1 , wherein the controller is configured to:

predict regional demand peaks for a geographic region in which the building is located;

define the projected peak hours based on the predicted regional demand peaks; and

create the peak hours mask using the projected peak hours.

7. The central plant of claim 6 , wherein the controller is configured to predict the regional demand peaks based on at least one of load history data and weather data for the geographic region in which the building is located.

8. The central plant of claim 1 , wherein:

the PLC term comprises a rate factor defining a cost per unit of the one or more resources purchased from the utility during the CP hours; and

the controller is configured to:

identify a geographic region in which the building is located; and

calculate the rate factor based on one or more parameters that depend on the identified geographic region.

9. The central plant of claim 1 , wherein the one or more one or more storage devices comprise one or more of a hot water storage tank or a cold thermal energy storage tank.

10. The central plant of claim 1 , wherein the one or more resources comprise one or more of hot water, cold water, or steam.

11. A method for allocating one or more resources in a central plant, the method comprising:

obtaining a cost function comprising a peak load contribution (PLC) term, wherein the PLC term represents a cost based on an amount of the one or more resources purchased from the utility during coincidental peak (CP) hours of an optimization period comprising a plurality of time steps, the CP hours comprising a subset of the plurality of time steps, wherein the cost is a function of one or more decision variables representing an amount of the one or more resources to store in one or more storage devices or to discharge from the one or more storage devices during each of the plurality of time steps;

modifying the cost function by applying a peak hours mask to the PLC term, wherein the peak hours mask identifies one or more hours in the optimization period as projected peak hours and causes the one or more resources purchased from the utility during any hours not identified as projected peak hours to be assigned substantially zero cost in the PLC term;

allocating, to each of the time steps within the optimization period, an amount of the one or more resources to store in the one or more storage devices or discharge from the one or more storage devices during the time step by performing an optimization of the modified cost function to determine values of the decision variables.

12. The method of claim 11 , wherein the CP hours comprise one or more hours of the optimization period during which regional demand peaks occur for a geographic region in which the building is located.

13. The method of claim 11 , wherein:

the CP hours are unknown prior to the optimization period; and

the projected peak hours comprise an estimate of the CP hours and are identified prior to the optimization period.

14. The method of claim 11 , wherein the peak hours mask comprises a vector of binary values, each of the binary values corresponding to an hour of the optimization period and indicating whether the corresponding hour is a projected peak hour.

15. The method of claim 11 , further comprising:

predicting regional demand peaks for a geographic region in which the building is located;

defining the projected peak hours based on the predicted regional demand peaks; and

creating the peak hours mask using the projected peak hours.

16. The method of claim 15 , wherein the regional demand peaks are predicted based on at least one of load history data and weather data for the geographic region in which the building is located.

17. The method of claim 11 , wherein the PLC term comprises a rate factor defining a cost per unit of the electrical energy purchased from the utility during the CP hours;

the method further comprising:

identifying a geographic region in which the building is located; and

calculating the rate factor based on one or more parameters that depend on the identified geographic region.

18. An energy cost optimization system for a building, the system comprising:

HVAC equipment configured to consume one or more resources purchased from a utility or generated by a central plant for use in satisfying a building energy load; and

a controller configured to:

obtain a cost function comprising a peak load contribution (PLC) term, wherein the PLC term represents a cost based on an amount of the one or more resources purchased from the utility during coincidental peak (CP) hours of an optimization period comprising a plurality of time steps, the CP hours comprising a subset of the plurality of time steps in the optimization period, wherein the cost is a function of one or more decision variables representing an amount of the one or more resources to be consumed by the HVAC equipment during each of the plurality of time steps;

modify the cost function by applying a peak hours mask to the PLC term, wherein the peak hours mask identifies one or more hours in the optimization period as projected peak hours and causes the controller to assign substantially zero cost, in the PLC term, to the one or more resources purchased from the utility during any hours not identified as projected peak hours; and

allocate, to each of the time steps within the optimization period, an amount of the one or more resources to be consumed by the HVAC equipment during the time step by performing an optimization process of the modified cost function to determine values of the decision variables.

19. The energy cost optimization system of claim 18 , wherein the peak hours mask comprises a vector of binary values, each of the binary values corresponding to an hour of the optimization period and indicating whether the corresponding hour is a projected peak hour.

20. The energy cost optimization system of claim 18 , wherein:

the PLC term comprises a rate factor defining a cost per unit of the electrical energy purchased from the utility during the CP hours; and

the controller is configured to:

identify a geographic region in which the building is located; and

calculate the rate factor based on one or more parameters that depend on the identified geographic region.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 9, 2024
From: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
To: TYCO FIRE & SECURITY GMBH
Reel/Frame 067056/0552 →
NUNC PRO TUNC ASSIGNMENT Recorded Feb 4, 2022
From: JOHNSON CONTROLS TECHNOLOGY COMPANY
To: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
Reel/Frame 058959/0764 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 15, 2019
From: ELBSAT, MOHAMMAD N.
To: JOHNSON CONTROLS TECHNOLOGY COMPANY
Reel/Frame 049186/0606 →
Continuity (2)
Continuation 15405234 · Jan 12, 2017
Related Publication 20190235556A1 · Aug 1, 2019
Cited By (10)
US 12,260,140 US 12,282,975 US 12,386,325 US 12,393,385 US 12,406,218 US 12,424,329 US 12,431,621 US 12,687,314 US 12,695,189 US 12,719,167