System and method for modulating hot gas reheat utilizing multiple compressor systems

Inventors: Stephen B. Pickle (Norman, OK); John T. Knight (Moore, OK)
Assignee: JOHNSON CONTROLS TYCO IP HOLDNGS LLP
F24F11/86F24F3/044F24F3/153F24F5/001F24F11/0008F24F11/30F24F11/54F24F11/56F25B5/02F25B6/02F25B41/20
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,473,809
App. No.
16/451,916
Granted
Oct 18, 2022
Kind
B2
Abstract

A system for modulating hot gas reheat operation of a heating, ventilation, and/or air conditioning (HVAC) system with multiple compressors, wherein the HVAC system is configured to regulate air provided to multiple zones. The system includes a controller configured to respond to a call for dehumidification in the absence of a call for cooling by sequentially energizing a first compressor of the multiple compressors in a reheat mode of the first compressor, energizing a second compressor of the multiple compressors in a cooling mode of the second compressor, energizing a third compressor of the multiple compressors in a reheat mode of the third compressor initially at full capacity, and energizing a fourth compressor of the multiple compressors in a cooling mode of the fourth compressor.

Claims (35)

1. A system for modulating hot gas reheat operation of a heating, ventilation, and/or air conditioning (HVAC) system with a plurality of compressors, wherein the HVAC system is configured to regulate air provided to a plurality of zones, comprising:

a controller configured to respond to a call for dehumidification in the absence of a call for cooling by sequentially energizing a first compressor of the plurality of compressors in a reheat mode of the first compressor, energizing a second compressor of the plurality of compressors in a cooling mode of the second compressor, energizing a third compressor of the plurality of compressors in a reheat mode of the third compressor initially at full capacity, and energizing a fourth compressor of the plurality of compressors in a cooling mode of the fourth compressor.

2. The system of claim 1 , wherein the first compressor is coupled to both a first hot gas reheat circuit including a reheat coil and a first cooling circuit including a first condenser and an evaporator, the second compressor is coupled to a second cooling circuit including a second condenser and the evaporator, the third compressor is coupled to both a second hot gas reheat circuit including the reheat coil and a third cooling circuit including a third condenser and the evaporator, and the fourth compressor is coupled to a fourth cooling circuit including a fourth condenser and the evaporator.

3. The system of claim 2 , comprising a first three-way reheat valve disposed at a first junction between the first hot gas reheat circuit and the first cooling circuit, and comprising a second three-way reheat valve disposed at a second junction between the second hot gas reheat circuit and the third cooling circuit.

4. The system of claim 3 , wherein the controller is configured, when energizing the third compressor in the reheat mode initially at full capacity, to close a first drain valve disposed downstream of both the third compressor and the second three-way reheat valve, to open a second drain valve disposed downstream of both the third compressor and the second three-way reheat valve, and to subsequently close the second drain valve upon the second three-way reheat valve receiving a modulating signal.

5. The system of claim 4 , wherein the controller is configured, upon energizing the third compressor in the reheat mode initially at full capacity, to monitor a temperature of supply air to determine if the temperature of the supply air is at a neutral temperature, and when the temperature of the supply air is not at the neutral temperature, to provide the modulating signal to the second three-way reheat valve to adjust a capacity of the reheat mode of the third compressor.

6. The system of claim 1 , wherein the controller is configured to receive and to ignore a first call for cooling in a first zone of the plurality of zones while maintaining the first compressor in the reheat mode, maintaining the second compressor in the cooling mode, modulating the reheat mode of the third compressor, and maintaining the fourth compressor in the cooling mode.

7. The system of claim 6 , wherein the controller is configured to receive the first call for cooling in the first zone and a second call for cooling in a second zone of the plurality of zones and, in response to the first and second calls for cooling, to switch the third compressor to a cooling mode of the third compressor while maintaining the first compressor in the reheat mode, maintaining the second compressor in the cooling mode, and maintaining the fourth compressor in the cooling mode.

8. The system of claim 7 , wherein the controller is configured to receive the first call for cooling in the first zone, to receive the second call for cooling in the second zone, to receive a third call for cooling in a third zone of the plurality of zones, to ignore the third call for cooling, and, in response to the first and second calls for cooling, to maintain the first compressor in the reheat mode and to maintain the second, third, and fourth compressors in the cooling mode.

9. The system of claim 8 , wherein the controller is configured to receive the first call for cooling in the first zone, the second call for cooling in the second zone, to receive the third call for cooling in the third zone, to receive a fourth call for cooling in a fourth zone of the plurality of zones, and, in response to the first, second, third, and fourth calls for cooling, to switch the first compressor to a cooling mode of the first compressor while maintaining the second, third, and fourth compressors in the cooling mode.

10. The system of claim 9 , wherein the controller is configured, when switching the first compressor to the cooling mode of the first compressor, to open a third drain valve disposed downstream of both the first compressor and the first three-way reheat valve and to close a fourth drain valve disposed downstream of both the first compressor and the first three-way reheat valve.

11. The system of claim 9 , wherein the controller is configured, once the fourth call for cooling in the fourth zone is met, to switch the first compressor to the reheat mode of the first compressor, while maintaining the second, third, and fourth compressors in the cooling mode.

12. The system of claim 11 , wherein the controller is configured, once the third call for cooling the third zone is met, to maintaining the first compressor in the reheat mode and the second, third, and fourth compressors in the cooling mode.

13. The system of claim 12 , wherein the controller is configured, once the second call for cooling is met, to initially switch the third compressor to the reheat mode of the third compressor at full capacity initially and then modulate the reheat mode, while maintaining the first compressor in the reheat mode and the second and fourth compressors in the cooling mode.

14. The system of claim 13 , wherein the controller is configured, once the first call for cooling is met, to maintain the first and second compressors in the reheat mode and the second and fourth compressors in the cooling mode.

15. The system of claim 14 , wherein the controller is configured, once the call for dehumidification is met, to sequentially switch the second and fourth compressors off, to initially switch the first compressor to the cooling mode for a first duration of time and then switch off the first compressor, and then initially switch the third compressor to the cooling mode for a second duration of time and then switch off the third compressor.

16. A system for modulating hot gas reheat operation of a heating, ventilation, and/or air conditioning (HVAC) system, wherein the HVAC system is configured to regulate air provided to a plurality of zones, comprising;

a first compressor coupled to both a first hot gas reheat circuit including a reheat coil and a first cooling circuit including a first condenser and an evaporator;

a second compressor coupled to a second cooling circuit including a second condenser and the evaporator;

a third compressor coupled to both a second hot gas reheat circuit including the reheat coil and a third cooling circuit including a third condenser and the evaporator;

a fourth compressor coupled to a fourth cooling circuit including a fourth condenser and the evaporator;

a first multi-directional reheat valve disposed at a first junction between the first hot gas reheat circuit and the first cooling circuit;

a second multi-directional reheat valve disposed at a second junction between the second hot gas reheat circuit and the third cooling circuit; and

a controller configured to receive a call for dehumidification in the absence of a call for cooling and respond to the call for dehumidification by sequentially energizing the first compressor in a reheat mode of the first compressor, energizing the second compressor in a cooling mode of the second compressor, energizing the third compressor in a reheat mode of the third compressor initially at full capacity, and energizing the fourth compressor in a cooling mode of the fourth compressor.

17. The system of claim 16 , wherein the controller is configured, upon energizing the third compressor in the reheat mode initially at full capacity, to monitor a temperature of supply air to determine if the temperature of the supply air is at a neutral temperature, and when the temperature of the supply air is not at the neutral temperature, to provide a modulating signal to the second multi-directional reheat valve to adjust a capacity of the reheat mode of the third compressor.

18. The system of claim 17 , comprising a first drain valve and a second drain valve disposed downstream of both the third compressor and the second multi-directional reheat valve.

19. The system of claim 18 , wherein the controller is configured, when energizing the third compressor in the reheat mode initially at full capacity, to close the first drain valve, to open the second drain valve, and to subsequently close the second drain valve upon the second multi-directional reheat valve receiving the modulating signal.

20. The system of claim 19 , wherein the controller is configured, upon receiving calls for cooling from two different zones of the plurality of zones, to switch the third compressor to a cooling mode of the third compressor while maintaining the first compressor in the reheat mode and the second and fourth compressors in the cooling mode.

21. The system of claim 20 , wherein the controller is configured, upon receiving calls for cooling from four different zones of the plurality of zones, to switch the first compressor to a cooling mode of the first compressor while maintaining the first, second, and third compressors in the cooling mode.

22. The system of claim 21 , wherein the controller is configured, once the call for cooling from a single zone of the plurality of zones is met, to switch the first compressor to the reheat mode, while maintaining the second, third, and fourth compressors in the cooling mode.

23. The system of claim 22 , wherein the controller is configured, once the call for cooling from three zones of the plurality of zones is met, to initially switch the third compressor to the reheat mode at full capacity and then subsequently modulate the reheat mode, while maintaining the first compressor in the reheat mode and the second and fourth compressors in the cooling mode.

24. A system for modulating hot gas reheat operation of a heating, ventilation, and/or air conditioning (HVAC) system, wherein the HVAC system is configured to regulate air provided to a plurality of zones, comprising:

a controller configured to respond to a call for dehumidification in the absence of a call for cooling by sequentially energizing a first compressor in a reheat mode of the first compressor, energizing a second compressor in a cooling mode of the second compressor, energizing a third compressor in a reheat mode of the third compressor initially at full capacity, and energizing a fourth compressor in a cooling mode of the fourth compressor, wherein the controller is configured, upon energizing the third compressor in the reheat mode initially at full capacity, to monitor a temperature of supply air to determine if the temperature of the supply air is at a neutral temperature, and when the temperature of the supply air is not at the neutral temperature, to provide a modulating signal to a multi-directional reheat valve to adjust a capacity of the reheat mode of the third compressor.

25. The system of claim 24 , wherein the first compressor is coupled to both a first hot gas reheat circuit including a reheat coil and a first cooling circuit including a first condenser and an evaporator, the second compressor is coupled to a second cooling circuit including a second condenser and the evaporator, the third compressor is coupled to both a second hot gas reheat circuit including the reheat coil and a third cooling circuit including a third condenser and the evaporator, and the fourth compressor is coupled to a fourth cooling circuit including a fourth condenser and the evaporator.

26. The system of claim 25 , wherein the multi-directional reheat valve is disposed at a junction between the second hot gas reheat circuit and the third cooling circuit.

Assignments (5)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 30, 2025
From: JOHNSON CONTROLS TECHNOLOGY COMPANY
To: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
Reel/Frame 072298/0096 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 24, 2025
From: TYCO FIRE & SECURITY GMBH
To: JOHNSON CONTROLS LIGHT COMMERCIAL IP GMBH
Reel/Frame 070179/0435 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 24, 2024
From: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
To: TYCO FIRE & SECURITY GMBH
Reel/Frame 067832/0947 →
NUNC PRO TUNC ASSIGNMENT Recorded Feb 4, 2022
From: JOHNSON CONTROLS TECHNOLOGY COMPANY
To: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
Reel/Frame 058959/0764 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 25, 2019
From: PICKLE, STEPHEN B.; KNIGHT, JOHN
To: JOHNSON CONTROLS TECHNOLOGY COMPANY
Reel/Frame 049583/0045 →
Continuity (2)
Provisional Application 62808503 · Feb 21, 2019
Related Publication 20200271340A1 · Aug 27, 2020