Model predictive maintenance system with integrated measurement and verification functionality

Inventors: Mohammad N. Elbsat (Milwaukee, WI); Michael J. Wenzel (Grafton, WI); Jingduo Fan (Milwaukee, WI); Robert D. Turney (Watertown, WI)
Assignee: Johnson Controls Tyco IP Holdings LLP
G06Q50/163G06N5/02G06Q10/04G06Q10/20
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,416,955
App. No.
16/687,571
Granted
Aug 16, 2022
Kind
B2
Abstract

A model predictive maintenance system for building equipment including one or more processing circuits including processors and memory storing instructions that, when executed by the processors, cause the processors to perform operations. The operations include obtaining an objective function that defines a cost of operating the building equipment and performing maintenance on the building equipment as a function of operating decisions and maintenance decisions for the building equipment for time steps within a time period. The operations include performing an optimization of the objective function to generate a maintenance and replacement strategy for the building equipment over a duration of an optimization period. The operations include estimating a savings loss predicted to result from a deviation from the maintenance and replacement strategy. The operations include adjusting an amount of savings expected to be achieved by energy conservation measures for the building equipment based on the savings loss.

Claims (56)

1. A model predictive maintenance (MPM) system for building equipment, the system comprising:

one or more processing circuits comprising one or more processors and memory storing instructions that, when executed by the one or more processors, cause the one or more processors to perform operations comprising:

obtaining an objective function that defines a cost of operating the building equipment and performing maintenance on the building equipment as a function of operating decisions and maintenance decisions for the building equipment for a plurality of time steps within a time period;

performing an optimization of the objective function to generate a maintenance and replacement strategy for the building equipment over a duration of an optimization period;

estimating a savings loss based on a predicted increase in consumption of one or more resources consumed by the building equipment during operation over the time period, the predicted increase in consumption predicted to result from a deviation from the maintenance and replacement strategy; and

causing a user device to provide an alert indicating the savings loss to a user.

2. The system of claim 1 , the operations further comprising estimating an operational cost of operating the building equipment over the duration of the optimization period based on a degradation model of the building equipment, wherein estimating the savings loss is based on the operational cost, and wherein the objective function further defines a cost of replacing the building equipment as a function of replacement decisions for the building equipment for the plurality of time steps within the time period.

3. The system of claim 1 , the operations further comprising providing a display to the user device to be displayed by the user device, the display comprising a projection of the savings loss over time due to a plurality of deviations from the maintenance and replacement strategy.

4. The system of claim 1 , the operations further comprising adjusting an amount of savings expected to be achieved by implementing one or more energy conservation measures (ECMs) for the building equipment based on the savings loss, the one or more ECMs associated with a contract between a provider of the one or more ECMs and a customer, the contract comprising the amount of savings expected to be achieved.

5. The system of claim 1 , the operations further comprising:

monitoring a degradation state of the building equipment over time; and

detecting the deviation from the maintenance and replacement strategy in response to the degradation state of the building equipment increasing after a time at which a maintenance or replacement activity is indicated by the maintenance and replacement strategy.

6. The system of claim 1 , the operations further comprising:

calculating a baseline cost predicted to result from adhering to the maintenance and replacement strategy;

calculating a second cost predicted to result from a modified maintenance and replacement strategy comprising the deviation; and

calculating a difference between the baseline cost and the second cost, the difference indicating the savings loss.

7. The system of claim 6 , the operations further comprising:

performing a second optimization of the objective function to generate the modified maintenance and replacement strategy, the second optimization performed subject to a constraint that results in a change in a time at which at least one maintenance or replacement activity occurs; and

comparing results of the second optimization to the optimization to estimate the savings loss associated with not performing the at least one maintenance or replacement activity.

8. The system of claim 1 , wherein the savings loss predicted to result from the deviation is an amount by which the cost of operating the building equipment and performing maintenance on the building equipment is estimated to increase as a result of deviating from the maintenance and replacement strategy.

9. A method for performing model predictive maintenance (MPM) of building equipment, the method comprising:

obtaining an objective function that defines a cost of operating the building equipment and performing maintenance on the building equipment as a function of operating decisions and maintenance decisions for the building equipment for a plurality of time steps within a time period;

performing an optimization of the objective function to generate a maintenance and replacement strategy for the building equipment over a duration of an optimization period;

estimating a savings loss based on a predicted increase in consumption of one or more resources consumed by the building equipment during operation over the time period, the predicted increase in consumption predicted to result from a deviation from the maintenance and replacement strategy; and

causing a user device to provide an alert indicating the savings loss to a user.

10. The method of claim 9 , further comprising estimating an operational cost of operating the building equipment over the duration of the optimization period based on a degradation model of the building equipment, wherein estimating the savings loss is based on the operational cost, and wherein the objective function further defines a cost of replacing the building equipment as a function of replacement decisions for the building equipment for the plurality of time steps within the time period.

11. The method of claim 9 , further comprising providing a display to the user device to be displayed by the user device, the display comprising a projection of the savings loss over time due to a plurality of deviations from the maintenance and replacement strategy.

12. The method of claim 9 , further comprising adjusting an amount of savings expected to be achieved by implementing one or more energy conservation measures (ECMs) for the building equipment based on the savings loss, the one or more ECMs associated with a contract between a provider of the one or more ECMs and a customer, the contract comprising the amount of savings expected to be achieved.

13. The method of claim 9 , further comprising:

monitoring a degradation state of the building equipment over time; and

detecting the deviation from the maintenance and replacement strategy in response to the degradation state of the building equipment increasing after a time at which a maintenance or replacement activity is indicated by the maintenance and replacement strategy.

14. The method of claim 9 , further comprising:

calculating a baseline cost predicted to result from adhering to the maintenance and replacement strategy;

calculating a second cost predicted to result from a modified maintenance and replacement strategy comprising the deviation; and

calculating a difference between the baseline cost and the second cost, the difference indicating the savings loss.

15. A controller for performing model predictive maintenance (MPM) of building equipment, the controller comprising:

one or more processors; and

one or more non-transitory computer-readable media storing instructions that, when executed by the one or more processors, cause the one or more processors to perform operations comprising:

performing an optimization of an objective function to generate a maintenance and replacement strategy for the building equipment over a duration of an optimization period, the objective function defining a cost of operating the building equipment and performing maintenance on the building equipment as a function of operating decisions and maintenance decisions for the building equipment for a plurality of time steps within a time period;

receiving an input indicating an override of the maintenance and replacement strategy, the override removing a maintenance decision or replacement decision defined by the maintenance and replacement strategy or moving the maintenance decision or replacement decision to a different time;

estimating a savings loss based on a predicted increase in consumption of one or more resources consumed by the building equipment during operation over the time period, the predicted increase in consumption predicted to result from the override; and

causing a user device to provide an alert indicating the savings loss to a user.

16. The controller of claim 15 , the operations further comprising estimating an operational cost of operating the building equipment over the duration of the optimization period based on a degradation model of the building equipment, wherein estimating the savings loss is based on the operational cost, and wherein the objective function further defines a cost of replacing the building equipment as a function of replacement decisions for the building equipment for the plurality of time steps within the time period.

17. The controller of claim 15 , the operations further comprising providing a display to the user device to be displayed by the user device, the display comprising a projection of the savings loss over time due to a plurality of deviations from the maintenance and replacement strategy.

18. The controller of claim 15 , the operations further comprising adjusting an amount of savings expected to be achieved by implementing one or more energy conservation measures (ECMs) for the building equipment based on the savings loss, the one or more ECMs associated with a contract between a provider of the one or more ECMs and a customer, the contract comprising the amount of savings expected to be achieved.

19. The controller of claim 15 , the operations further comprising:

monitoring a degradation state of the building equipment over time; and

detecting a deviation from the maintenance and replacement strategy in response to the degradation state of the building equipment increasing after a time at which a maintenance or replacement activity is indicated by the maintenance and replacement strategy;

wherein estimated the savings loss comprises a predicted savings loss resulting from the deviation.

20. The controller of claim 15 , the operations further comprising:

calculating a baseline cost predicted to result from adhering to the maintenance and replacement strategy;

calculating a second cost predicted to result from a modified maintenance and replacement strategy comprising the override; and

calculating a difference between the baseline cost and the second cost, the difference indicating the savings loss.

21. The controller of claim 20 , the operations further comprising:

performing a second optimization of the objective function to generate the modified maintenance and replacement strategy, the second optimization performed subject to a constraint that results in a change in a time at which at least one maintenance or replacement activity occurs; and

comparing results of the second optimization to the optimization to estimate the savings loss associated with not performing the at least one maintenance or replacement activity.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 9, 2024
From: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
To: TYCO FIRE & SECURITY GMBH
Reel/Frame 067056/0552 →
NUNC PRO TUNC ASSIGNMENT Recorded Feb 4, 2022
From: JOHNSON CONTROLS TECHNOLOGY COMPANY
To: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
Reel/Frame 058959/0764 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 5, 2020
From: ELBSAT, MOHAMMAD N.; WENZEL, MICHAEL J.; FAN, JINGDUO; TURNEY, ROBERT D.
To: JOHNSON CONTROLS TECHNOLOGY COMPANY
Reel/Frame 051417/0198 →